Level Crossing Removal Project

Level Crossing Removal Project
The logo of the Level Crossing Removal Project, showing multiple small red circles and black text for the project name.
The newly elevated Reservoir railway station showing the project's elevated designs with a road in the foreground.
Elevated rail near the rebuilt Preston station.
Project overview
FormedMarch 2015
TypeProject team
JurisdictionMelbourne
HeadquartersMelbourne
EmployeesIncrease 382 (June 2018)
Minister responsible
Project executive
  • Matt Thorpe[1], Acting CEO
Parent departmentDepartment of Transport and Planning
Parent authorityMajor Transport Infrastructure Authority
Websitebigbuild.vic.gov.au

The Level Crossing Removal Project (LXRP) is an infrastructure upgrade program by the Government of Victoria, Australia, to remove and grade-separate 110 level crossings and to rebuild 51 railway stations on the metropolitan and regional rail network of the state capital Melbourne. The project aims to improve network efficiency, rail safety, and reduce traffic congestion.

After pledging the removal of 50 level crossings at the 2014 Victorian state election, the Andrews Government committed $2.4 billion in the 2015–2016 budget to remove the first 20 crossings by 2018. The next 30 crossings were notionally funded through the hypothecation of the sale proceeds from the privatisation of the Port of Melbourne.[2] Prior to the 2018 state election, the government committed to remove a further 25 level crossings, using a new prioritisation framework.[3] In 2021, the government announced a further ten level crossing removals and four level crossing closures would occur by 2025, bringing the total planned level crossing removals to 85 by 2025.[4][5] In 2022, the Andrews government announced the removal of an additional 25 level crossings by 2030, bringing the total to 110.

Previously its own administrative agency, in 2019 the LXRP became a project within the Major Transport Infrastructure Authority, an office of the Victorian Department of Transport and Planning.[6] As of August 2024, 84 crossings have been removed and 48 train stations have been built or rebuilt as part of the project.[7]

Background

When Melbourne's rail network was built, many road-railway crossings were via level crossing rather than bridges or underpasses due to the city's flat topography and sparse population. As traffic levels increased, these became bottlenecks for road and rail traffic, limiting the speed and frequency of train services. In 1954, the State Government established a committee to look at the removal of level crossings at Clifton Hill, Elsternwick, Footscray, Moorabbin, and Newport.[8][9] These projects were completed by 1960.[10]

In 1983, the level crossing at Station Street, Box Hill, was removed. Other level crossing removals include Dorset Road, Boronia, in 1998 and Middleborough Road, Laburnum, in 2007.[11] In the early 2010s, level crossings were removed at Nunawading (2010), Springvale (2014), Sunshine (2014) and Mitcham (2014).[12][13][14]

A black and white photo of the level crossing at Clayton Road, Clayton with manually operated gates before its removal.
The level crossing at Clayton Road, Clayton prior to its removal.

As of 2014, there were 176 level crossings left on metropolitan Melbourne's rail network (5 of which involved tram lines) and 228 places where railways had been separated from roads;[15] by the end of the Level Crossing Removal Project (LXRP), 66 level crossings will remain.[16] Over two-thirds of these grade separations were constructed between 1863 and 1918, with fewer than one level crossing removal per year between 1918 and 2015. The commitment by the government to remove 110 level crossings over sixteen years, by 2030, represents the fastest rate of crossing removals in Melbourne's history.[17]

History

2014 election commitments

A Z-Class tram crossing the tram-train level crossing at Kooyong Station.
The crossing at Glenferrie Road, Kooyong was not included on the original removal list, despite being marked as a priority by VicRoads.

In June 2014, five months prior to the Victorian state election, VicRoads compiled a report of the most dangerous level crossings in Victoria and handed it to the Napthine Liberal-Nationals government.[18] In its 2014 state election manifesto, the then Labor opposition announced that, if elected, it would remove 50 level crossings by grade separation, with 20 to be removed by 2018. Although the majority of crossings announced by Opposition Leader Daniel Andrews were included in the priority list, ten of the crossings highlighted by VicRoads were not on the opposition's list.[19] The sites of all 50 level crossing removals were progressively announced over the following two years after the election of the Andrews government in November 2014.[20]

In September 2016, the Port of Melbourne lease concluded, providing $9.7 billion for infrastructure, including funding for the remaining 30 level crossing removals to be completed by mid-2022.[21]

2018 election commitments

A large yellow sign next to the Cramer Street, Preston level crossing indicating that it will be removed.
A project sign in 2020 indicating that the crossing at Cramer Street, Preston will be removed.

In October 2018, the LXRP surpassed the State Government's 2014 election commitment of removing 20 level crossings by 2018, having officially removed 29 crossings.[22] In the lead up to the 2018 state election, Victorian Premier Daniel Andrews pledged to remove a further 25 level crossings across Melbourne at a cost of $6.6 billion by 2025. The locations of the additional removals were announced progressively over the course of 2018 through a new prioritisation framework based on safety, congestion, and proximity to emergency services.[3]

2021 additional commitments

In July 2021, the State Government announced the removal of an additional ten level crossings and four closures by the end of 2025 at a cost of $2.5 billion.[5] These removals will include the reconstruction of five stations across the network, with stations to be rebuilt at Croydon, Keon Park, Narre Warren, Parkdale, and Ringwood East. At the conclusion of these additional 35 removals, the Pakenham, Cranbourne, and Lilydale lines will have no road level crossings for their entire length, with these announcements pushing the number of crossing removals to 85 by 2025.[23]

2022 election commitments

In the lead up to the 2022 state election, the Andrews government announced a further 25 level crossing removals, bringing the total number of removals to 110 by 2030. Many of these removals will be delivered together and include a number of closures. In September 2022, the premier announced eight crossings would be removed in Brunswick on the Upfield line.[24][25] The eight crossings would be removed by 2027 and would include the rebuilding of Jewell, Brunswick, and Anstey stations.[25] The government announced elevated rail would be built along the corridor from Royal Park to Moreland Road, meeting the elevated rail built as part of the 2022 level crossing removal works, and would include an upgrade of the Upfield Bike Path.[24]

In October 2022, the government committed to removing an extra four level crossings on the Ballarat line between Caroline Springs and Melton stations by 2028. Proposed removal methods for the level crossings at Exford Road and Coburns Road is by constructing a rail trench (since revised to a rail bridge) and lowering Melton station, while the roads will be elevated over tracks to get rid of the Hopkins Road and Ferris Road level crossings.[26] Seven more crossing removals and two closures were announced in October 2022 for the Frankston line.[27] These level crossings would be removed by 2029 and would make the line level crossing free for its entire length.[27] Four stations will be rebuilt as part of the removals at Highett, Mordialloc, Aspendale and Seaford.[28]

On 21 and 25 October 2022, the Andrews government announced an additional two level crossing removals for the Sunbury line and one on the Hurstbridge line. These crossings are located at Old Calder Highway and Watsons Road, Diggers Rest, and Ruthven St, Macleod. These crossings will be removed by 2026 via the construction of a road bridge for the Sunbury line removals and a rail bridge for the Hurstbridge line.[29] At the conclusion of these removals, the Sunbury line will be fully level crossing free.[30]

The government announced an additional three removals and two closures on the Werribee line on 27 October 2022.[31][32] Along with the four already removed on the Werribee line, these removals would make the line level crossing free by 2030, and allow for additional services and the construction of the Geelong Fast Rail project.[32] The crossings at Hudsons Road, Spotswood, Maddox Road, Newport, and Maidstone Street, Altona. These crossings will be removed with a combination of rail over and road over, and will include a newly elevated Spotswood station.[33] The crossings at Anderson Street, Yarraville, and Champion Road, Newport will be closed during the project. Pedestrian links will still remain with a plan to upgrade local roads to accommodate the closure of these crossings.[33]

Governance

The landscaped forecourt of Middle Gorge Station.
Middle Gorge station, opened as part of the Mernda rail extension in 2018.

The Level Crossing Removal Authority (LXRA) was formed in May 2015 as an administrative office of the then-new Department of Economic Development, Jobs, Transport and Resources to deliver the project.[34][35][36]

Later, the LXRA led delivery of other rail projects, including extension of the South Morang line to Mernda, upgrades of the Hurstbridge and Cranbourne lines, as well as a rebuilt Frankston station. The authority also delivered a new stabling facility north of Wyndham Vale station and train storage at Kananook.[37][38]

The LXRA was abolished as an independent administrative office following the 2018 state election, and its functions were absorbed into the newly formed Major Transport Infrastructure Authority at the Department of Transport.[39]

Architecture and urban design

The coloured windows at Bell railway station, Preston with the staircase leading to the platform in the foreground
The interior of the rebuilt Bell station in Preston, showing stained glass windows behind the staircase that leads to the city-bound platform.

The LXRP has used several different design approaches to removing level crossings, tailoring designs to different urban settings around Melbourne.[40] Most projects, particularly those in the denser inner- and middle-suburbs, have involved lowering the rail line into a trench or elevating the rail line above the road. Some projects in outer suburbs, such as Gap Road near Sunbury station or Station Street near Beaconsfield station, have involved lowering or raising the road without altering the existing rail corridor. This is enabled by the additional space surrounding the railway line.[40]

As noted by University of Melbourne researchers in 2016, the scale of the project had significant urban renewal implications for the city:

Each crossing removal affects, on average, at least a kilometre of rail corridor and, within the urban area, this usually includes a station. In some instances, topography has required the removal of more than one crossing to meet rail engineering requirements as well as longer sections of corridor becoming part of the works. On the face of it, this means that the current seventy-five crossing removals could result in seventy-five kilometres of transformed rail corridors and fifty-seven new stations – more than a quarter of Melbourne’s total.[40]

The researchers emphasised the urban benefits from new elevated rail over trenched rail, including the creation of new parkland and open space, arguing wider benefits could be achieved beyond reducing traffic congestion.[41] One study examined the local public health positive and negative impacts from the removal of level crossings on the Upfield line, including significant construction impacts.[42] The study found that by improving road connections the project could help induce more car usage, but that this could be offset by improving pedestrian and cycling connections.[43]

Awards

The LXRP has received numerous awards for their different projects in the categories of sustainability, architecture, and urban design. The Reservoir station project was presented the 'Special Prize Exterior' award in the Passenger Stations category at the World Architecture and Design Award at the 2021 Prix Versailles.[44][45] The Toorak Road level crossing removal topped the infrastructure category of the Australian Institute of Landscape Architects awards due to the design of the new public parkland, cycling paths, and open space.[46] The elevated rail project from Moreland to Coburg stations saw landscape architects Tract win the Infrastructure Award of Excellence for their landscape and urban design work on the project, with the judging panel "particularly impressed with the urban renewal of the area".[46][47] The Bell to Moreland project was also awarded a score of 98 points from the Infrastructure Sustainability Council (ISC), the highest rating ever awarded in Australia.[48]

Elevated rail

Recreational space created by the LXRP beneath the newly elevated rail line at Clayton station in Melbourne's south-east
Recreational space created by the LXRP beneath the newly elevated rail line at Clayton station in Melbourne's south-east

Some of the most significant changes to Melbourne's urban structure from the LXRP have resulted from the construction of large sections of elevated rail, something that was relatively rare in Melbourne.[49] In 2016, the government announced that 8.3 kilometres (5.2 mi) of elevated rail would be built in Melbourne's south-eastern suburbs to remove nine level crossings on the Pakenham and Cranbourne rail corridor and build five new elevated stations at Carnegie, Murrumbeena, Hughesdale, Clayton and Noble Park.[49]

Dubbed "sky rail" by opponents and some media outlets, the LXRP spurred significant local opposition due to concerns over visual and noise impacts, and lack of consultation.[50][51] The project became a political issue in the 2018 state election, although one opinion poll commissioned by The Age newspaper found 60% of Victorians supported the use of elevated rail to remove level crossings, and the government was returned at the election with an increased majority.[52][53] Prior to the election, the government announced more sections of elevated rail on the Pakenham line.[54]

Some experts argued elevated rail offered a better urban outcome than trenched rail, providing opportunities for more open space, economic development, better local connections and less disruption from construction.[50][55] The Caulfield to Dandenong level crossing removals created a large new section of open parkland, dubbed a "linear park".[40] This included 22.5 hectares (56 acres) of new open space, sports courts, playgrounds, new walking and cycling trails, and expanded station forecourts.[56][57] As part of the project, the Djerring Trail was created, a 17-kilometre (11 mi) shared-use path along the rail corridor. In the year after the elevated rail opened in 2018, the media reported that many residents, including some who were opposed to the project, were happy with the outcome and utilised the new open space.[58][59]

Tree removal

The elevated rail bridge under construction at Lower Plenty Road, Rosanna.
Construction at the level crossing removal at Lower Plenty Road near Rosanna railway station in 2018, with mature river red gums in background.

The removal of mature trees for level crossing removal works has been a source of controversy with some local residents and project critics.[60][61] Due to the nature of the LXRP, trees need to be cut down or relocated from the site to allow for construction works. This is a particular issue for projects where the rail line is lowered into a trench, such as the planned level crossing removals near Glen Huntly station, which have required significant mature tree removal along the planned one-kilometre (0.6 mi) rail trench.[62][63] An elevated rail design was chosen to remove the level crossings near Rosanna station in part to minimise the loss of native trees, as a proposed rail trench would have required the removal of hundreds of mature river red gum trees along the corridor.[64][65]

According to a newspaper report, more than 10,000 trees have been cut down since 2014 to allow for the construction of Victorian infrastructure projects—including hundreds of trees for the LXRP.[60] During the level crossing removal at Moreland Road, a campaign against the removal of 100 mature trees was unsuccessful, with a local councillor claiming only three or four trees remained at the conclusion of the project.[60] In response, the government has stated more trees were planted than were there originally, as part of expanded parkland at the site.[60] The state opposition has highlighted and campaigned on tree loss due to major infrastructure projects.[60]

Railway heritage

Moreland railway station shows the integration of the old heritage station into the new elevated design.
LXRP retention of the heritage-listed Mentone railway station at street-level as a heritage deck and park, above the newly lowered station.

The loss of heritage railways stations and the impact on heritage architecture has been a source of controversy and a key design consideration for the project. During the removal of a level crossing or rebuild of a railway station, heritage station buildings or existing railway infrastructure may be impacted. Some heritage buildings have been demolished, while others have been retained, moved or adapted for other uses, such as at Clayton and Mentone stations.[66][67]

At the Warrigal Road level crossing removal, Kingston Council have called for heritage protection for the heritage Parkdale railway station buildings.[68] This request has been denied by the Department of Environment, Land, Water and Planning as well as Heritage Victoria on grounds that the structure is "not of state-level cultural heritage significance".[69] Nonetheless, in response to the local campaign to preserve the original heritage station building, the LXRP announced it would retain and repurpose the building within the precinct, although the extent of the retention is not clear.[70][71]

Other crossing removals have had their heritage structures restored for reuse. At Moreland station, the original heritage station building that opened in 1884 was restored and turned into additional station facilities.[72] Heritage restorations are common across the removals, with other examples including the signals box at Gardiner railway station turning into bike parking, and the station building at North Williamstown railway station being restored into community and station facilities.[73][74]

Crossing closures

The use of road closures to remove level crossings has been a source of controversy. The government has used crossing closures in select cases where there are nearby crossing removal projects or existing grade-separated major roads. For example, the crossings at Anderson Street, Yarraville, and Champion Road, Newport will be closed at the same time as the rail line will be elevated above Hudsons Road in nearby Spotswood and at Maddox Road in Newport with new grade-separated pedestrian and cycling crossings also built.[33] According to the government, this solution is required is due to the constrained site, significant heritage impacts that would arise from grade separation, and the relatively low level of car traffic on the roads.[33] Some local residents, however, have objected to the road closures, arguing there would be significant impacts to local car journeys.[75] Similar objections were raised during the 2022 state election by the state opposition over the closure of Latrobe Street in Cheltenham, which similarly is located close to two other grade separated crossings completed in 2020.[76]

New and amalgamated stations

The amalgamated Union station, January 2024

Due to a large portion of level crossings also having adjacently located stations, many stations have been rebuilt as part of the project. Rebuilt stations have subsequently delivered improve facilities for passengers, including new toilet facilities, drinking fountains, increased levels of accessibility, better integration with surrounding transport connections, and higher quality architectural designs, amongst other benefits.[77]

Whilst the majority of stations demolished as part of the project have been rebuilt and reopened, a few projects have resulted in the amalgamation of stations. Whilst controversial, these instances have usually only occurred due to the close proximity between existing stations, reducing the negative impact on users. Amalgamated stations have allowed for improved station locations, faster journey times, and higher quality facilities.[78] One amalgamation has included Mont Albert and Surrey Hills stations on the Belgrave and Lilydale lines. In 2023, these two stations were closed and amalgamated into the new Union station located in-between the two former locations as part of the removals of Mont Albert and Union roads project.[79] This amalgamation has received criticism, with opponents highlighting how the increased distances from the two shopping centres on Union Road and Hamilton Street will negatively impact local mobility.[80] Despite community criticism, this project was completed in 2023 with the removal of two level crossings and the opening of the new Union station.[81]

Reception

Political

A modern train (HCMT) approaches platform 2 at the newly elevated Carnegie railway station.
A HCMT approaches platform 2 at the newly elevated Carnegie railway station.

The LXRP has generally been seen as a political success for the Andrews government. Journalist Benita Kolovos argued it was the quick rollout of the program and the visible, tangible benefits it delivered to communities that drove its electoral success.[82] She wrote: "It was promised at the 2014 election, construction began in the first year of the Andrews government’s term and several were completed before the 2018 election. Commuters benefited from more trains, drivers from less traffic."[82] The government's messaging on the project has focused on these localised benefits, public safety, and the prevalence of level crossings within Melbourne. Minister for Transport Infrastructure Jacinta Allan said in 2021: "Every Victorian knows the dinging sound of boom gates coming down and the frustration that comes with it, that’s why we’re getting rid of them – saving lives, easing congestion and getting you home sooner."[83]

But controversy over design choices and the cost of the project has also prompted opposition. Liberal MP Brad Rowswell criticised the Andrews government for a lack of community consultation and local feedback on the project and claimed that the government was out of touch with the community.[76] Shadow Minister for Transport Infrastructure David Davis criticised the project for its cost, arguing that “without a comprehensive business case, there is simply no proper economic justification for the Level Crossing Removal Program".[84] The ongoing disruption of roadworks for the project was also an issue in some suburbs.[85]

Media

The Guardian Australia has called the program "transformational" and "suburb moulding" in comments about the Andrews government's infrastructure projects.[86] Other local newspapers, such as The Age and Herald Sun, have been critical of the project and have highlighted local opposition in their reporting.[87][88][89][90]

Experts and lobby groups

The Public Transport Users Association has campaigned for level-crossing removals, and has welcomed the LXRP and its benefits to the public transport system, with spokesman Daniel Bowen highlighting how the projects "bring a lot of pluses to the wider community, and [how] it’s good to finally see progress on them."[91][92] The Royal Automobile Club of Victoria have also campaigned for level crossing removals, and have welcomed announcements of crossing removals.[93]

Academics Ian Woodcock and John Stone have highlighted the benefits from the LXRP, including its urban design opportunities and how it has contributed to the revitalisation of public transportation in Melbourne.[94][40] Other academics such as Monash University researcher Graham Currie have been critical of the project, arguing the travel time savings resulting from the project were low and did not justify the cost.[89]

Auditor-General

The main entrance to the lowered Chelsea railway station platforms.
The main entrance to the new Chelsea railway station platforms.

A report released in December 2017 by the Victorian Auditor-General's Office in the LXRP's original fifty level crossing removals found that the speed and cost of the project carried significant risks.[95] The report criticised the Level Crossing Removal Authority for its haste in delivering the program, and found that the rapid pace of the project had contributed to a failure to properly assess the merits of each grade separation. In 2017, the project's cost was found to have increased to $8.3 billion, the project is more than 38% more expensive than its initial $5–6 billion estimated price tag.[95]

The Auditor-General criticised the selection of crossings, stating that the value of the project was compromised by the apparent political motivation for some crossing removals at the expense of more dangerous or congested intersections.[96] In their report, the Auditor-General found that only 32 of the crossings chosen in the original 50 removals were featured in the top 50 of a 2008 list by the Department of Transport of the state's most dangerous level crossings. 28 of these were prioritised on a 2013 VicRoads removal list which was handed to the Napthine government.[95]

Since these findings, the LXRP has developed and applied a transparent process to select sites for the additional level crossing removals. In a follow-up 2020 report, the Auditor-General stated the new process has improved the project’s cost-effectiveness because it uses delivery efficiency as one of the criteria for site selection.[97] The Auditor-General noted the Department and the Major Transport Infrastructure Authority had fully addressed seven of its recommendations, partially addressed one and was working to address two more, but warned that the project had not completed a business case for its second batch of crossing removals so the economic benefits were unclear.[97]

Public

While the LXRP has been broadly popular, local opposition has attracted significant media attention. Elevated rail has been controversial among some local residents and businesses, with protests over the removal of crossings on the Upfield line calling for a rail trench to be used instead.[98][99] At the same time, polling has found a majority of Victorians supported the use of elevated rail to remove level crossings.[52] In other examples, such as the Caulfield to Dandenong elevated rail project, local media reported that many residents were supportive of the project's outcomes.[58][59]

List of crossing removals

Original 50 crossing removals: 2014–2022

Prior to the 2014 state election, the then Labor opposition announced a plan to remove 50 level crossings by 2022, including 20 by 2018.[100] Park Road, Cheltenham, Mascot Avenue, Bonbeach, and Lochiel Avenue, Edithvale were added to the original 50 level crossing removals after further community consultations.[101][102][103] This pushed the number of level crossing removals to 53. These removals were completed on the Glen Waverley, Frankston, Sunbury, Belgrave, Lilydale, Upfield, Pakenham, Cranbourne, Werribee, Craigieburn, and Mernda lines by May 2022.[104]

Line(s) Road Nearest station Solution Date of completion
Glen Waverley Burke Road Gardiner Rail under January 2016[105]
Frankston Centre Road Bentleigh Rail under August 2016[106]
Frankston McKinnon Road McKinnon Rail under August 2016[107]
Frankston North Road Ormond Rail under August 2016[108]
Sunbury Furlong Road Ginifer Rail under November 2016[109]
Sunbury Main Road St Albans Rail under November 2016[110]
Belgrave Mountain Highway Bayswater Hybrid December 2016[111]
Belgrave Scoresby Road Bayswater Rail under December 2016[112]
Belgrave, Lilydale Blackburn Road Blackburn Rail under January 2017[113]
Belgrave, Lilydale Heatherdale Road Heatherdale Rail under January 2017[114]
Upfield Camp Road Gowrie Rail under December 2017[115]
Sunbury Melton Highway Watergardens Road over January 2018[116]
Cranbourne, Pakenham Chandler Road Noble Park Rail over February 2018[117]
Cranbourne, Pakenham Corrigan Road Noble Park Rail over February 2018[118]
Cranbourne, Pakenham Heatherton Road Noble Park Rail over February 2018[119]
Cranbourne, Pakenham Centre Road Clayton Rail over April 2018[120]
Cranbourne, Pakenham Clayton Road Clayton Rail over April 2018[121]
Hurstbridge Grange Road Alphington Rail under May 2018[122]
Hurstbridge Lower Plenty Road Rosanna Rail over May 2018[123]
Cranbourne, Pakenham Grange Road Carnegie Rail over June 2018[124]
Cranbourne, Pakenham Koornang Road Carnegie Rail over June 2018[125]
Cranbourne, Pakenham Murrumbeena Road Murrumbeena Rail over June 2018[126]
Cranbourne, Pakenham Poath Road Hughesdale Rail over June 2018[127]
Frankston Skye/Overton Road Kananook Rail over June 2018[128]
Cranbourne Thompsons Road Merinda Park Road over June 2018[129]
Werribee Kororoit Creek Road Seaholme Rail over July 2018[130]
Cranbourne Abbotts Road Dandenong Rail over September 2018[131]
Craigieburn Buckley Street Essendon Road under September 2018[132]
Frankston Seaford Road Seaford Hybrid September 2018[133]
Werribee Aviation Road Aircraft Road over September 2019[134]
Mernda High Street Reservoir Rail over December 2019[135]
Frankston Eel Race Road Carrum Closed off February 2020[136]
Frankston Mascot Avenue Bonbeach Closed off February 2020[137]
Frankston Station Street Carrum Rail over February 2020[138]
Glen Waverley Toorak Road Tooronga Rail over April 2020[139]
Frankston Balcombe Road Mentone Rail under July 2020[140]
Frankston Charman Road Cheltenham Rail under August 2020[141]
Frankston Park Road Cheltenham Rail under August 2020[141]
Upfield Bell Street Coburg Rail over December 2020[142]
Upfield Moreland Road Moreland Rail over December 2020[143]
Werribee Werribee Street Werribee Rail over January 2021[144]
Werribee Cherry Street Werribee Road over March 2021[145]
Pakenham South Gippsland Highway Dandenong Road over August 2021[146]
Frankston Bondi Road Bonbeach Rail under November 2021[147]
Frankston Edithvale Road Edithvale Rail under November 2021[148]
Frankston Lochiel Avenue Edithvale Closed off November 2021[149]
Lilydale Manchester Road Mooroolbark Rail over November 2021[150]
Lilydale Maroondah Highway Lilydale Rail over November 2021[151]
Williamstown Ferguson Street North Williamstown Rail under December 2021[152]
Pakenham Clyde Road Berwick Road under February 2022[153]
Pakenham Hallam Road Hallam Rail over April 2022[154]
Mernda Bell Street Bell Rail over May 2022[155]
Craigieburn Glenroy Road Glenroy Rail under May 2022[156]

Additional 25 crossing removals: 2022–2025

During the lead up to the 2018 state election, an extra 25 level crossing removals were announced.[3] These removals will occur on the Cranbourne, Pakenham, Upfield, Frankston, Mernda, Ballarat, Geelong, Sunbury, Belgrave, Lilydale and Barinsdale lines. This announcement will result in the Cranbourne line being fully level crossing free, with these announcements pushing the number of level crossing removals to 75 by 2025.

Line(s) Road Nearest station Preferred solution Status Date of Completion
Cranbourne Evans Road Merinda Park Road over Completed October 2020[157]
Upfield Munro Street Coburg Rail over Completed November 2020[158]
Upfield Reynard Street Coburg Rail over Completed November 2020[159]
Pakenham Cardinia Road Cardinia Road Road over Completed December 2020[160]
Frankston Argyle Avenue Chelsea Rail under Completed November 2021[161]
Frankston Chelsea Road Chelsea Closed off Completed November 2021[162]
Frankston Swanpool Avenue Chelsea Closed off Completed November 2021[163]
Werribee Old Geelong Road Hoppers Crossing Road over Completed December 2021[164]
Cranbourne Greens Road Dandenong Rail over Completed February 2022[165]
Mernda Cramer Street Preston Rail over Completed May 2022[166]
Mernda Murray Road Preston Rail over Completed May 2022[167]
Mernda Oakover Road Bell Rail over Completed May 2022[168]
Ballarat, Geelong Fitzgerald Road Ardeer Road over Completed July 2022[169]
Ballarat, Geelong Robinsons Road Deer Park Road under Completed September 2022[170]
Sunbury Gap Road Sunbury Road under Completed September 2022[171]
Ballarat, Geelong Mt Derrimut Road Deer Park Rail over Completed April 2023[172]
Belgrave, Lilydale Union Road Surrey Hills Rail under Completed May 2023[173]
Belgrave, Lilydale Mont Albert Road Mont Albert Rail under Completed May 2023[81]
Frankston Neerim Road Glen Huntly Rail under Completed June 2023[174]
Frankston Glen Huntly Road Glen Huntly Rail under Completed July 2023[175]
Cranbourne Camms Road Cranbourne Road over Completed November 2023[176]
Pakenham Main Street Pakenham Rail over Completed June 2024[177]
Pakenham McGregor Road Pakenham Rail over Completed June 2024[178]
Gippsland Racecourse Road Pakenham Rail over Completed June 2024[179]
Cranbourne, Pakenham Webster Street Dandenong Closed off Planning 2025[a][180]

Additional 10 crossing removals: 2023–2025

Boosting the number of removals, the Andrews Labor government announced in July 2021 an extra 10 level crossing removals and 4 closures.[23] These removals will occur on the Pakenham, Frankston, Mernda, Sunbury, Belgrave and Lilydale lines. At the conclusion of these removals, the Pakenham and Lilydale lines will join the Cranbourne line in having no road level crossings for their entire length, with these announcements pushing the number of crossing removals to 85 by 2025.[23]

Line(s) Road Nearest station Preferred solution Status Date of Completion
Pakenham Webb Street Narre Warren Rail over Completed December 2023[181]
Lilydale Cave Hill Road Lilydale Closed off Completed January 2024[182]
Belgrave Bedford Road Ringwood Rail under Completed March 2024[183]
Pakenham Brunt Road Beaconsfield Road over Completed April 2024[184]
Mernda Keon Parade Keon Park Rail over Completed May 2024[185]
Pakenham Station Street Officer Closed off Completed May 2024[186]
Lilydale Dublin Road Ringwood East Rail under Completed June 2024[187]
Lilydale Coolstore Road Croydon Rail over Completed July 2024[188]
Frankston Warrigal Road Parkdale Rail over Completed August 2024[189]
Frankston Parkers Road Parkdale Rail over Completed August 2024[190]
Sunbury Calder Park Drive Watergardens Road over Under construction 2025[191]
Pakenham Progress Street Dandenong Closed off Under construction 2025[192][193]
Pakenham Station Street Beaconsfield Road over Under construction 2025[194]
Sunbury Holden Road Watergardens Closed off Planning 2025[195]

Additional 25 crossing removals: 2025–2030

Prior to the 2022 state election, the State Government announced an extra 25 level crossing removals by 2030. These removals will occur on the Upfield, Ballarat, Sunbury, Hurstbridge, Frankston and Werribee/Williamstown lines.[25] At the conclusion of these removals, the Frankston, Sunbury, and Werribee lines will have no road level crossings for their entire length, joining the Cranbourne, Pakenham and Lilydale lines, once projects on those lines are complete.[196] These series of announcements have pushed the number of crossing removals to 110.[24][197][29]

Line(s) Road Nearest station Preferred solution Status Date of Completion
Sunbury Old Calder Highway Diggers Rest Road over Under construction 2025[198][199]
Sunbury Watsons Road Diggers Rest Road over Under construction 2025[198][199]
Frankston Bear Street Mordialloc Closed off Planning 2026[200]
Werribee Champion Road Newport Closed off Planning 2026[201]
Ballarat Coburns Road Melton Rail over Planning 2026[202]
Ballarat Exford Road Melton Rail over Planning 2026[202]
Ballarat Ferris Road Cobblebank Road over Planning 2026[202]
Ballarat Hopkins Road Caroline Springs Road over Planning 2026[202]
Werribee Maddox Road Newport Rail over Planning 2026[201]
Frankston McDonald Street Mordialloc Rail over Planning 2026[200]
Frankston Station Street Mordialloc Rail over Planning 2026[200]
Werribee Maidstone Street Laverton[b] Road over Planning 2027[203]
Hurstbridge Ruthven Street Macleod Rail over Planning 2027[204]
Werribee, Williamstown Hudsons Road Spotswood Rail over Early planning 2028[205]
Frankston Armstrongs Road Seaford Rail over Early planning 2029[206]
Frankston Groves Street Aspendale Rail under Early planning 2029[207]
Frankston Highett Road Highett Rail over Early planning 2029[207]
Frankston Latrobe Street Mentone Closed off Early planning 2029[207]
Frankston Station Street Seaford Rail over Early planning 2029[206]
Frankston Wickham Road Highett Rail over Early planning 2029[207]
Upfield Albert Street Brunswick Rail over Early planning 2030[208]
Upfield Albion Street Anstey Rail over Early planning 2030[208]
Werribee, Williamstown Anderson Street Yarraville Closed off Early planning 2030[205]
Upfield Brunswick Road Jewell Rail over Early planning 2030[208]
Upfield Dawson Street Jewell Rail over Early planning 2030[208]
Upfield Hope Street Anstey Rail over Early planning 2030[208]
Upfield Union Street Jewell Rail over Early planning 2030[208]
Upfield Victoria Street Brunswick Rail over Early planning 2030[208]
Upfield Park Street Jewell Rail over Early planning 2030[208]

New and rebuilt stations

There will be 51 railway stations rebuilt as part of the LXRP. Four stations are being added to the metropolitan network as part of suburban rail extensions delivered by the LXRP. Three of these stations, Hawkstowe, Middle Gorge and Mernda were added as part of the Mernda rail extension, which extended the former South Morang line eight kilometres (5.0 mi) north to Mernda. The extension, announced by Labor at the 2014 state election, opened in 2018.[209][210] As part of the level crossing removals along the Pakenham line, a new station was added at East Pakenham along with a short rail extension.[211] The LXRP also delivered a new infill station at Southland on the Frankston line.[212] In one case, the nearby Mont Albert and Surrey Hills railway stations on the Belgrave and Lilydale lines were merged and replaced with a brand new Union station located between them.[213][214]

Line(s) Station Image Status Completion date
Glen Waverley Gardiner Open January 2016[215]
Frankston McKinnon Open August 2016[216]
Frankston Bentleigh Open August 2016[217]
Frankston Ormond Open August 2016[218]
Sunbury Ginifer Open November 2016[219]
Sunbury St Albans Open November 2016[220]
Belgrave Bayswater Open December 2016[221]
Belgrave, Lilydale Heatherdale Open February 2017[222]
Frankston Southland (new) Open November 2017[223]
Cranbourne, Pakenham Noble Park Open February 2018[224]
Cranbourne, Pakenham Clayton Elevated Clayton railway station Open April 2018[225]
Hurstbridge Rosanna Open May 2018[226]
Cranbourne, Pakenham Carnegie Open June 2018[227]
Frankston, Stony Point Frankston Open June 2018[228]
Cranbourne, Pakenham Murrumbeena Open June 2018[229]
Cranbourne, Pakenham Hughesdale Open August 2018[230]
Mernda Hawkstowe (new) Open August 2018[231]
Mernda Mernda (new) Open August 2018[231]
Mernda Middle Gorge (new) Open August 2018[231]
Mernda Reservoir Open December 2019[232]
Frankston Carrum Open February 2020[233]
Frankston Mentone Open July 2020[234]
Frankston Cheltenham Open August 2020[235]
Upfield Coburg Open December 2020[236]
Upfield Moreland Open December 2020[237]
Lilydale Lilydale Open November 2021[238]
Lilydale Mooroolbark Open November 2021[239]
Frankston Bonbeach Open November 2021[240]
Frankston Chelsea Open November 2021[241]
Frankston Edithvale Open November 2021[242]
Williamstown North Williamstown Open December 2021[243]
Cranbourne Merinda Park Open February 2022[244]
Pakenham Hallam Open May 2022[245]
Craigieburn Glenroy Open May 2022[246]
Mernda Bell Bell station Open September 2022[247]
Mernda Preston Preston station on the Mernda line Open September 2022[247]
Ballarat, Geelong Deer Park Open April 2023[248]
Hurstbridge Greensborough Open April 2023[249]
Hurstbridge Montmorency Open April 2023[250]
Belgrave, Lilydale Union (new) Open May 2023[251]
Frankston Glen Huntly Open July 2023[252]
Pakenham Narre Warren Open March 2024[181]
Pakenham East Pakenham (new) Open June 2024[179]
Pakenham Pakenham Open June 2024[177]
Mernda Keon Park Open June 2024[185]
Lilydale Ringwood East Open July 2024[187]
Frankston Parkdale Open August 2024[190]
Lilydale Croydon Open August 2024[188]
Ballarat Melton Planning 2026[202]
Frankston Mordialloc Planning 2026[200]
Werribee, Williamstown Spotswood Early planning 2028[205]
Frankston Aspendale Early planning 2029[207]
Frankston Highett Early planning 2029[207]
Frankston Seaford Early planning 2029[206]
Upfield Anstey Early planning 2030[208]
Upfield Brunswick Early planning 2030[208]
Upfield Jewell Early planning 2030[208]

See also

Notes

  1. ^ Webster Street will be closed to vehicle traffic at the level crossing in late 2025 with a new nearby road underpass completed by 2028.
  2. ^ Laverton station is the closest station on the Werribee line express route to the Maidstone Street level crossing. The closest station geographically is Westona station located south of the level crossing on the Altona Loop.

References

  1. ^ "Melbourne residents angry over new train station metres from their balconies".
  2. ^ "About – Level Crossing Removal Project". Level Crossing Removal Authority. Archived from the original on 12 December 2016. Retrieved 7 January 2017.
  3. ^ a b c "Andrews pledges 25 new level crossing removals in Melbourne". ABC News. 21 October 2018. Archived from the original on 31 October 2018. Retrieved 28 October 2018.
  4. ^ "Ten More Level Crossings To Go By 2025 | Premier of Victoria". www.premier.vic.gov.au. Archived from the original on 29 July 2021. Retrieved 9 August 2021.
  5. ^ a b Fowler, Michael (29 July 2021). "Big Build swells: Andrews adds $2.5b, five new stations and 10 level crossing removals". The Age. Archived from the original on 9 August 2021. Retrieved 9 August 2021.
  6. ^ Department of Transport (September 2019). "Annual Report 2018-19" (PDF). Archived (PDF) from the original on 9 November 2021. Retrieved 9 November 2021.
  7. ^ "Level Crossing Removal Project". Victoria’s Big Build. 26 October 2022. Archived from the original on 21 September 2022. Retrieved 6 December 2022.
  8. ^ "Abolition of Busy Level Crossings" Railway Gazette 13 August 1954 page 176
  9. ^ "Abolishing Level Crossings in Victoria" Railway Gazette 30 December 1955 pages 769–771
  10. ^ "Abolition of Level Crossings in Victoria" Railway Gazette 4 November 1960 pages 539–540
  11. ^ "DVN61: Crossing The Line: Boronia's forgotten killer intersection". DVN61. 7 July 2013. Archived from the original on 6 December 2022. Retrieved 6 December 2022.
  12. ^ "Infrastructure" Railway Gazette International July 2009 page 14
  13. ^ Springvale road and rail grade separation Archived 12 March 2017 at the Wayback Machine Arup
  14. ^ "Anderson rd level crossing in sunshine finally removed". 2014. Archived from the original on 6 December 2022. Retrieved 6 December 2022.
  15. ^ "Level crossings: Which are funded to be removed, which are promised? – Daniel Bowen". 16 March 2024. Archived from the original on 16 March 2024. Retrieved 29 April 2024.
  16. ^ "Melbourne Level Crossing Map". Google My Maps. Retrieved 29 April 2024.
  17. ^ Woodcock, Ian; Stone, John (2016). "The Benefits of Level Crossing Removal: lessons from Melbourne's historical experience". University of Melbourne/RMIT University: 13. Archived from the original on 6 December 2022. Retrieved 6 December 2022 – via RMIT Researchbank.
  18. ^ "Strategic framework for the prioritisation of level crossings in metropolitan Melbourne" (PDF). Parliament of Victoria. Archived from the original (PDF) on 13 March 2017. Retrieved 12 September 2022.
  19. ^ Carey, Adam (26 October 2015). "Level crossings: VicRoads list of Melbourne's worst overlooked by Labor". The Age. Archived from the original on 23 May 2017. Retrieved 7 January 2017.
  20. ^ Moorabbin Kingston Leader (6 September 2016). "Level Crossing Removal Authority releases plans for Frankston line". Archived from the original on 2 January 2017. Retrieved 22 November 2022.
  21. ^ Promise Delivered: Port Of Melbourne Leased To Remove Level Crossings And Create Thousands Of Jobs Archived 6 December 2022 at the Wayback Machine Premier of Victoria 19 September 2016
  22. ^ Towell, Craig Butt, Noel (21 October 2018). "Another 25 rail level crossings to go under Labor pledge". The Age. Archived from the original on 22 October 2018. Retrieved 28 October 2018.{{cite web}}: CS1 maint: multiple names: authors list (link)
  23. ^ a b c "10 more level crossings to go by 2025". levelcrossings.vic.gov.au. 29 July 2021. Archived from the original on 30 July 2021. Retrieved 30 July 2021.
  24. ^ a b c "Eight More Dangerous Level Crossings To Go By 2027 | Premier of Victoria". www.premier.vic.gov.au. Archived from the original on 19 September 2022. Retrieved 19 September 2022.
  25. ^ a b c Eddie, Rachael Dexter, Rachel (19 September 2022). "Eight level crossings to be removed in Melbourne's north". The Age. Archived from the original on 19 September 2022. Retrieved 19 September 2022.{{cite web}}: CS1 maint: multiple names: authors list (link)
  26. ^ "Making Melton level crossing-free". Victoria’s Big Build. 6 October 2022. Archived from the original on 6 October 2022. Retrieved 6 October 2022.
  27. ^ a b "Victorian opposition pledges to cap public transport fares at $2 a day". ABC News. 9 October 2022. Archived from the original on 9 October 2022. Retrieved 27 October 2022.
  28. ^ Tribune, The National (8 October 2022). "Making Frankston Line Level Crossing Free". The National Tribune. Archived from the original on 9 October 2022. Retrieved 9 October 2022.
  29. ^ a b "Making Macleod level crossing-free". Victoria’s Big Build. 25 October 2022. Archived from the original on 25 October 2022. Retrieved 25 October 2022.
  30. ^ "Making the Sunbury Line level crossing-free". Victoria’s Big Build. 21 October 2022. Archived from the original on 21 October 2022. Retrieved 21 October 2022.
  31. ^ Chan, Ray (26 October 2022). "All Werribee Line crossings set for removal". Rail Express. Archived from the original on 27 October 2022. Retrieved 27 October 2022.
  32. ^ a b "Werribee Line level crossing removals". Victoria’s Big Build. 26 October 2022. Archived from the original on 27 October 2022. Retrieved 27 October 2022.
  33. ^ a b c d "Making The Werribee Line Level Crossing Free | Premier of Victoria". www.premier.vic.gov.au. Archived from the original on 25 October 2022. Retrieved 26 October 2022.
  34. ^ "Victoria Government Gazette – No. G 18 Thursday 7 May 2015" (PDF). Victoria Government Gazette. 7 May 2015. p. 74. Archived (PDF) from the original on 23 October 2015. Retrieved 7 January 2017.
  35. ^ "Melbourne level crossing removal plan to be fast-tracked, Government says". ABC News. 15 February 2015. Archived from the original on 3 May 2017. Retrieved 7 January 2017.
  36. ^ "About the authority". Level Crossing Removal Authority. Archived from the original on 27 December 2016. Retrieved 7 January 2017.
  37. ^ "Wyndham Vale Train Stabling – Mcconnell Dowell". www.mcconnelldowell.com. Archived from the original on 12 December 2022. Retrieved 12 December 2022.
  38. ^ Bayside News (18 May 2020). "Train stabling facility finished". Bayside News. Archived from the original on 12 December 2022. Retrieved 12 December 2022.
  39. ^ "About the Major Transport Infrastructure Authority". Victoria’s Big Build. 28 April 2021. Archived from the original on 31 October 2022. Retrieved 31 October 2022.
  40. ^ a b c d e Woodcock, Ian (January 2020). "On track: Level Crossing Removal Project". Architecture Australia. Archived from the original on 22 December 2022. Retrieved 20 September 2022.
  41. ^ Rothenbury, Camryn (10 April 2018). "Level-crossing removals: learning from Melbourne's experience". Melbourne School of Design. Archived from the original on 20 September 2022. Retrieved 20 September 2022.
  42. ^ Browne, Geoffrey; Lowe, Melanie (22 January 2021). "Level-crossing removals: a case study in why major projects must also be investments in health". The Conversation. Archived from the original on 22 September 2022. Retrieved 20 September 2022.
  43. ^ Browne, Geoffrey R.; Lowe, Melanie (1 March 2021). "Liveability as determinant of health: Testing a new approach for health impact assessment of major infrastructure". Environmental Impact Assessment Review. 87: 106546. Bibcode:2021EIARv..8706546B. doi:10.1016/j.eiar.2020.106546. ISSN 0195-9255. S2CID 233784494.
  44. ^ "2021 Passenger Stations". Prix Versailles. Archived from the original on 13 December 2022. Retrieved 13 December 2022.
  45. ^ "Fantastique Reservoir – world architecture and rail sustainability winner". Victoria’s Big Build. 31 December 2021. Archived from the original on 31 October 2022. Retrieved 31 October 2022.
  46. ^ a b "Level crossings top landscape architecture awards". Victoria’s Big Build. 19 July 2022. Archived from the original on 30 October 2022. Retrieved 31 October 2022.
  47. ^ "2022 AILA Landscape Architecture Award Winners | Ace Contractors Group Pty Ltd". 11 July 2022. Archived from the original on 31 October 2022. Retrieved 31 October 2022.
  48. ^ Chan, Ray (13 June 2022). "Sustainability award for Bell-Moreland level crossing removal project". Rail Express. Archived from the original on 31 October 2022. Retrieved 31 October 2022.
  49. ^ a b Carey, Adam (8 February 2016). "Melbourne sky rail: Many questions remain about Andrews government plan". The Age. Archived from the original on 20 September 2022. Retrieved 20 September 2022.
  50. ^ a b Woodcock, Ian; Stone, John (22 February 2016). "The 'sky rail' saga: can big new transport projects ever run smoothly?". The Conversation. Archived from the original on 21 September 2022. Retrieved 20 September 2022.
  51. ^ Willingham, Richard (16 February 2016). "Sky rail: Premier Andrews stands by consultation process in face of anger". The Age. Archived from the original on 20 September 2022. Retrieved 20 September 2022.
  52. ^ a b Willingham, Richard (4 September 2016). "Sky rail gets strong backing from voters". The Courier. Archived from the original on 4 December 2016. Retrieved 20 September 2022.
  53. ^ Szego, Julie (10 February 2016). "Sky rail more an eye opener than an eyesore". The Age. Archived from the original on 20 September 2022. Retrieved 20 September 2022.
  54. ^ Preiss, Benjamin (1 November 2018). "Andrews targets key marginal with latest sky rail announcement". The Age. Archived from the original on 20 September 2022. Retrieved 20 September 2022.
  55. ^ "Rail lines over roads can help with more than just traffic jams". ArchitectureAU. Archived from the original on 2 December 2021. Retrieved 20 September 2022.
  56. ^ Landezine International Landscape Award LILA (2019). "Caulfield to Dandenong Level Crossing Removal Project". Archived from the original on 20 September 2022. Retrieved 20 September 2022.
  57. ^ Jacks, Timna (13 November 2017). "Life under the viaduct: Melbourne's south-east Skyrail will get a 'green up'". The Age. Archived from the original on 20 September 2022. Retrieved 20 September 2022.
  58. ^ a b Sakkal, Paul (12 May 2019). "More than a year on, has 'sky rail' turned suburbs into ghettos?". The Age. Archived from the original on 20 September 2022. Retrieved 20 September 2022.
  59. ^ a b Cowie, Tom (16 April 2018). "New sky rail station opens – and residents are happy about it". The Age. Archived from the original on 20 September 2022. Retrieved 20 September 2022.
  60. ^ a b c d e Lucas, Clay (3 January 2021). "Anger grows as thousands of trees axed in transport building blitz". The Age. Archived from the original on 23 October 2022. Retrieved 23 October 2022.
  61. ^ "Why are trees dying at this Melbourne train station?". ABC News. 2 September 2021. Archived from the original on 24 October 2022. Retrieved 23 October 2022.
  62. ^ "Level crossing removals: 600 trees to go for Glen Huntly trench". Herald Sun. 8 February 2022. Archived from the original on 24 October 2022. Retrieved 24 October 2022.
  63. ^ "Works notice – vegetation removal in Glen Huntly". Victoria’s Big Build. 20 June 2022. Archived from the original on 24 October 2022. Retrieved 24 October 2022.
  64. ^ Carey, Adam (28 September 2016). "Hundreds of red gums at risk if trench is built at Rosanna rail crossing". The Age. Archived from the original on 24 October 2022. Retrieved 24 October 2022.
  65. ^ Koenig, Rick (7 February 2017). "Design finalised for Lower Plenty Rd level crossing removal". Herald Sun. Archived from the original on 24 October 2022. Retrieved 24 October 2022.
  66. ^ "Station serves up a slice of history". Bayside News. 2 February 2022. Archived from the original on 24 October 2022. Retrieved 24 October 2022.
  67. ^ "TAFE class assist with Clayton Station restoration". Victoria’s Big Build. 14 June 2022. Archived from the original on 24 October 2022. Retrieved 24 October 2022.
  68. ^ "Council's call for Parkdale Train Station heritage protection refused". Mirage News. 16 September 2022. Archived from the original on 24 January 2023. Retrieved 24 October 2022.
  69. ^ Cowburn, Brodie (21 September 2022). "Heritage hopes for train station dashed". Bayside News. Archived from the original on 24 October 2022. Retrieved 24 October 2022.
  70. ^ "New design features old station building". Bayside News. 12 October 2022. Archived from the original on 24 October 2022. Retrieved 24 October 2022.
  71. ^ "Updated designs released for Parkdale level crossings". Victoria’s Big Build. 1 October 2022. Archived from the original on 24 October 2022. Retrieved 24 October 2022.
  72. ^ "Bell to Moreland comes out on top!". Victoria’s Big Build. 8 June 2022. Archived from the original on 24 October 2022. Retrieved 24 October 2022.
  73. ^ "Ferguson Street, Williamstown". Victoria’s Big Build. 21 June 2022. Archived from the original on 24 October 2022. Retrieved 24 October 2022.
  74. ^ "Burke Road, Glen Iris". Victoria’s Big Build. 22 June 2022. Archived from the original on 24 October 2022. Retrieved 24 October 2022.
  75. ^ "'It would divide our community': Newport locals slam level crossing removal". ABC Melbourne. 27 October 2022. Archived from the original on 12 November 2022. Retrieved 12 November 2022.
  76. ^ a b Staszewska, Ewa (4 November 2022). "'Dictate from their ivory tower': Andrews upsets marginal Melbourne seat". Sky News. Archived from the original on 6 November 2022. Retrieved 6 November 2022.
  77. ^ "Murrumbeena Rail Station LXRP". Mascot Engineering. Retrieved 25 March 2024.
  78. ^ Victoria’s Big Build (15 June 2022). "Union Road, Surrey Hills and Mont Albert Road, Mont Albert – selecting the best design". Victoria’s Big Build. Retrieved 13 April 2024.
  79. ^ "Union Road, Surrey Hills and Mont Albert Road, Mont Albert". Engage Victoria. Retrieved 25 March 2024.
  80. ^ "Union Road, Surrey Hills and Mont Albert Road, Mont Albert level crossing removals Submission from Boroondara City Council". Boroondara City Council. Retrieved 25 March 2024.
  81. ^ a b "Mont Albert Road, Mont Albert". Victoria’s Big Build. 3 August 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  82. ^ a b Kolovos, Benita (1 April 2022). "Analysis: Australia's busiest state government goes into hibernation". the Guardian. Archived from the original on 12 November 2022. Retrieved 12 November 2022.
  83. ^ Andrews, Daniel (29 July 2021). "Premier of Victoria: Ten More Level Crossings To Go By 2025". Archived from the original on 24 October 2022. Retrieved 12 November 2022.
  84. ^ Davis, Davis (14 October 2020). "Press release: Allan and level crossing cowboys oversee a billion dollar blowout". vic.liberal.org.au. Archived from the original on 6 November 2022. Retrieved 6 November 2022.
  85. ^ Wahlquist, Calla; Bowers, Mike (2018). "Victorian election 2018: On the ground in Cranbourne part 1". The Guardian. Archived from the original on 12 November 2022. Retrieved 12 November 2022.
  86. ^ "The Daniel Andrews paradox: the enduring appeal of Australia's most divisive premier". the Guardian. 29 October 2022. Archived from the original on 2 November 2022. Retrieved 2 November 2022.
  87. ^ Carey, Adam (14 December 2017). "Level crossing removal program poor value for money: Auditor-General Andrew Greaves". The Age. Archived from the original on 12 November 2022. Retrieved 12 November 2022.
  88. ^ Abbott, Lachlan (17 August 2022). "Barred from their own street, residents fume at handling of level crossing works". The Age. Archived from the original on 20 September 2022. Retrieved 12 November 2022.
  89. ^ a b Jacks, Timna (23 January 2018). "Just a minute: Level crossing project resulting in small time savings, data shows". The Age. Archived from the original on 12 November 2022. Retrieved 12 November 2022.
  90. ^ Masanauskas, John (17 August 2022). "Melbourne's leafy east set for level crossing removal mayhem". Herald Sun. Archived from the original on 12 November 2022. Retrieved 12 November 2022.
  91. ^ "Benefits to non-motorists from level crossing removals". Daniel Bowen. 15 December 2015. Archived from the original on 6 November 2022. Retrieved 6 November 2022.
  92. ^ "Level crossing removal – all options must be on the table | Public Transport Users Association (Victoria, Australia)". Public Transport Users Association. 11 January 2016. Archived from the original on 12 November 2022. Retrieved 12 November 2022.
  93. ^ AAP (19 August 2014). "Do more on Victorian transport: RACV". Retrieved 6 November 2022.
  94. ^ Woodcock, Ian; Stone, John (2016). "The Benefits of Level Crossing Removal: lessons from Melbourne's historical experience". University of Melbourne, RMIT University. Archived from the original on 12 November 2022. Retrieved 12 November 2022.
  95. ^ a b c "Managing the Level Crossing Removal Program". Victorian Auditor-General's Office. Archived from the original on 1 November 2022. Retrieved 1 November 2022.
  96. ^ Carey, Adam (14 December 2017). "Level crossing removal program poor value for money: Auditor-General Andrew Greaves". The Age. Archived from the original on 14 December 2017. Retrieved 14 December 2017.
  97. ^ a b Victorian auditor-general. "Follow-up level crossing removal report" (PDF). Archived (PDF) from the original on 1 November 2022. Retrieved 1 November 2022.
  98. ^ "Skyrail protest in Coburg | Hundreds of angry residents marched through Coburg to protest a Skyrail on the Upfield line through the northern suburbs. www.7plus.com.au/news #7News | By 7NEWS Melbourne | Facebook". www.facebook.com. Archived from the original on 6 November 2022. Retrieved 6 November 2022.
  99. ^ "Hundreds march down Melbourne highway in protest of Sky Rail construction". www.9news.com.au. 18 September 2016. Archived from the original on 6 November 2022. Retrieved 6 November 2022.
  100. ^ Landy, Sam; Johnston, Matt (20 October 2014). "Victorian state election 2014: Labor's key promises in detail". Herald Sun. Archived from the original on 14 November 2022. Retrieved 14 November 2022.
  101. ^ "Charman Road, Cheltenham". Victoria’s Big Build. 22 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  102. ^ "Lochiel Avenue, Edithvale". Victoria's Big Build. 21 June 2022. Archived from the original on 3 December 2022. Retrieved 11 December 2022.
  103. ^ "Mascot Avenue, Bonbeach". Victoria’s Big Build. 21 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  104. ^ Willingham, Richard (23 June 2015). "Three suburban train stations to be rebuilt underground: St Albans, Ginifer and Heatherdale". The Age. Archived from the original on 14 November 2022. Retrieved 14 November 2022.
  105. ^ Victoria’s Big Build (22 June 2022). "Burke Road, Glen Iris". Victoria’s Big Build. Archived from the original on 24 October 2022. Retrieved 12 December 2023.
  106. ^ Victoria’s Big Build (21 June 2022). "Centre Road, Bentleigh". Victoria’s Big Build. Archived from the original on 25 February 2023. Retrieved 12 December 2023.
  107. ^ Victoria’s Big Build (21 June 2022). "North Road, Ormond". Victoria’s Big Build. Archived from the original on 25 February 2023. Retrieved 12 December 2023.
  108. ^ Victoria’s Big Build (21 June 2022). "McKinnon Road, McKinnon". Victoria’s Big Build. Archived from the original on 25 February 2023. Retrieved 12 December 2023.
  109. ^ Victoria’s Big Build (21 June 2022). "Furlong Road, St Albans". Victoria’s Big Build. Archived from the original on 17 April 2023. Retrieved 12 December 2023.
  110. ^ Victoria’s Big Build (21 June 2022). "Main Road, St Albans". Victoria’s Big Build. Archived from the original on 17 April 2023. Retrieved 12 December 2023.
  111. ^ Victoria’s Big Build (21 June 2022). "Mountain Highway, Bayswater". Victoria’s Big Build. Archived from the original on 24 February 2023. Retrieved 12 December 2023.
  112. ^ Victoria’s Big Build (21 June 2022). "Scoresby Road, Bayswater". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 12 December 2023.
  113. ^ "Blackburn Road, Blackburn". Victoria’s Big Build. 21 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  114. ^ "Heatherdale Road, Mitcham". Victoria’s Big Build. 21 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  115. ^ "Camp Road, Campbellfield". Victoria’s Big Build. 21 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  116. ^ Victoria’s Big Build (21 June 2022). "Melton Highway, Sydenham". Victoria’s Big Build. Archived from the original on 7 April 2023. Retrieved 12 December 2023.
  117. ^ Victoria’s Big Build (21 June 2022). "Chandler Road, Noble Park". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 12 December 2023.
  118. ^ Victoria’s Big Build (21 June 2022). "Corrigan Road, Noble Park". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 12 December 2023.
  119. ^ Victoria’s Big Build (21 June 2022). "Heatherton Road, Noble Park". Victoria’s Big Build. Archived from the original on 7 April 2023. Retrieved 12 December 2023.
  120. ^ Victoria’s Big Build (21 June 2022). "Centre Road, Clayton". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 12 December 2023.
  121. ^ Victoria’s Big Build (21 June 2022). "Clayton Road, Clayton". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 12 December 2023.
  122. ^ Victoria’s Big Build (21 June 2022). "Grange Road, Alphington". Victoria’s Big Build. Archived from the original on 25 March 2023. Retrieved 12 December 2023.
  123. ^ Victoria’s Big Build (21 June 2022). "Lower Plenty Road, Rosanna". Victoria’s Big Build. Archived from the original on 25 March 2023. Retrieved 12 December 2023.
  124. ^ Victoria’s Big Build (21 June 2022). "Grange Road, Carnegie". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 12 December 2023.
  125. ^ Victoria’s Big Build (21 June 2022). "Koornang Road, Carnegie". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 12 December 2023.
  126. ^ Victoria’s Big Build (21 June 2022). "Murrumbeena Road, Murrumbeena". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 12 December 2023.
  127. ^ Victoria’s Big Build (21 June 2022). "Poath Road, Hughesdale". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 12 December 2023.
  128. ^ Victoria’s Big Build (21 June 2022). "Skye/Overton Road, Frankston". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 12 December 2023.
  129. ^ Victoria’s Big Build (21 June 2022). "Thompsons Road, Lyndhurst". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 12 December 2023.
  130. ^ Victoria’s Big Build (21 June 2022). "Kororoit Creek Road, Williamstown North". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 12 December 2023.
  131. ^ Victoria’s Big Build (22 June 2022). "Abbotts Road, Dandenong South". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 12 December 2023.
  132. ^ "Buckley Street, Essendon". Victoria’s Big Build. 21 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  133. ^ Victoria’s Big Build (21 June 2022). "Seaford Road, Seaford". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 12 December 2023.
  134. ^ Victoria’s Big Build (21 June 2022). "Aviation Road, Laverton". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 12 December 2023.
  135. ^ "High Street, Reservoir". engage.vic.gov.au. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  136. ^ "Eel Race Road, Carrum". Victoria’s Big Build. 21 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  137. ^ "Mascot Avenue, Bonbeach". Victoria’s Big Build. 21 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  138. ^ "Station Street, Carrum". Victoria’s Big Build. 21 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  139. ^ "Toorak Road, Kooyong". Victoria’s Big Build. 21 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  140. ^ Victoria’s Big Build (22 June 2022). "Balcombe Road, Mentone". Victoria’s Big Build. Archived from the original on 1 March 2023. Retrieved 12 December 2023.
  141. ^ a b Victoria’s Big Build (22 June 2022). "Charman Road, Cheltenham". Victoria’s Big Build. Archived from the original on 20 September 2022. Retrieved 12 December 2023.
  142. ^ Victoria’s Big Build (22 June 2022). "Bell Street, Coburg". Victoria’s Big Build. Archived from the original on 9 April 2023. Retrieved 12 December 2023.
  143. ^ Victoria’s Big Build (22 June 2022). "Moreland Road, Brunswick". Victoria’s Big Build. Archived from the original on 9 April 2023. Retrieved 12 December 2023.
  144. ^ Victoria’s Big Build (24 May 2023). "Werribee Street, Werribee". Victoria’s Big Build. Archived from the original on 28 October 2023. Retrieved 12 December 2023.
  145. ^ Victoria’s Big Build (22 June 2022). "Cherry Street, Werribee". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 12 December 2023.
  146. ^ Victoria’s Big Build (24 February 2023). "South Gippsland Highway, Dandenong South". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 12 December 2023.
  147. ^ Victoria’s Big Build (21 June 2022). "Bondi Road, Bonbeach". Victoria’s Big Build. Archived from the original on 2 December 2023. Retrieved 12 December 2023.
  148. ^ Victoria’s Big Build (21 June 2022). "Edithvale Road, Edithvale". Victoria’s Big Build. Archived from the original on 25 February 2023. Retrieved 12 December 2023.
  149. ^ Victoria’s Big Build (21 June 2022). "Lochiel Avenue, Edithvale". Victoria’s Big Build. Archived from the original on 3 December 2022. Retrieved 12 December 2023.
  150. ^ Victoria’s Big Build (24 February 2023). "Manchester Road, Mooroolbark". Victoria’s Big Build. Archived from the original on 2 December 2023. Retrieved 12 December 2023.
  151. ^ Victoria’s Big Build (24 February 2023). "Maroondah Highway, Lilydale". Victoria’s Big Build. Archived from the original on 1 March 2023. Retrieved 12 December 2023.
  152. ^ Victoria’s Big Build (24 February 2023). "Ferguson Street, Williamstown". Victoria’s Big Build. Archived from the original on 24 October 2022. Retrieved 12 December 2023.
  153. ^ Victoria’s Big Build (16 May 2023). "Clyde Road, Berwick". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 12 December 2023.
  154. ^ "Hallam Road, Hallam". Victoria’s Big Build. 12 July 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  155. ^ "Bell Street, Preston". Victoria's Big Build. 15 September 2022. Archived from the original on 11 January 2023. Retrieved 11 December 2022.
  156. ^ Victoria’s Big Build (12 April 2023). "Glenroy Road, Glenroy". Victoria’s Big Build. Archived from the original on 11 April 2023. Retrieved 12 December 2023.
  157. ^ "Evans Road, Lyndhurst". Victoria’s Big Build. 22 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  158. ^ Victoria’s Big Build (22 June 2022). "Munro Street, Coburg". Victoria’s Big Build. Archived from the original on 9 April 2023. Retrieved 12 December 2023.
  159. ^ Victoria’s Big Build (22 June 2022). "Reynard Street, Coburg". Victoria’s Big Build. Archived from the original on 9 April 2023. Retrieved 12 December 2023.
  160. ^ "Cardinia Road, Pakenham". Victoria’s Big Build. 22 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  161. ^ Victoria’s Big Build (21 June 2022). "Argyle Avenue, Chelsea". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 12 December 2023.
  162. ^ Victoria’s Big Build (21 June 2022). "Chelsea Road, Chelsea". Victoria’s Big Build. Archived from the original on 25 February 2023. Retrieved 12 December 2023.
  163. ^ Victoria’s Big Build (21 June 2022). "Swanpool Avenue, Chelsea". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 12 December 2023.
  164. ^ Victoria’s Big Build (24 February 2023). "Old Geelong Road, Hoppers Crossing". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 12 December 2023.
  165. ^ Victoria’s Big Build (21 June 2022). "Greens Road, Dandenong South". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 12 December 2023.
  166. ^ "Cramer Street, Preston". Victoria’s Big Build. 6 September 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  167. ^ "Murray Road, Preston". Victoria’s Big Build. 6 September 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  168. ^ Victoria’s Big Build (14 April 2023). "Oakover Road, Preston". Victoria’s Big Build. Archived from the original on 1 April 2023. Retrieved 12 December 2023.
  169. ^ Victoria’s Big Build (7 July 2023). "Fitzgerald Road, Ardeer". Victoria’s Big Build. Archived from the original on 10 July 2023. Retrieved 12 December 2023.
  170. ^ Victoria’s Big Build (7 July 2023). "Robinsons Road, Deer Park". Victoria’s Big Build. Archived from the original on 10 July 2023. Retrieved 12 December 2023.
  171. ^ Victoria’s Big Build (12 April 2023). "Gap Road, Sunbury". Victoria’s Big Build. Archived from the original on 21 March 2023. Retrieved 12 December 2023.
  172. ^ Victoria’s Big Build (26 July 2023). "Mt Derrimut Road, Deer Park". Victoria’s Big Build. Archived from the original on 10 July 2023. Retrieved 12 December 2023.
  173. ^ "Mont Albert Road, Mont Albert". Victoria’s Big Build. 3 August 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  174. ^ "Neerim Road, Glen Huntly". Victoria’s Big Build. 28 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  175. ^ "Glen Huntly Road, Glen Huntly". Victoria’s Big Build. 28 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  176. ^ Victoria’s Big Build (11 December 2023). "Camms Road, Cranbourne". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 12 December 2023.
  177. ^ a b "Main Street, Pakenham". Victoria’s Big Build. 22 June 2022. Archived from the original on 9 December 2022. Retrieved 19 September 2022.
  178. ^ "McGregor Road, Pakenham". Victoria’s Big Build. 22 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  179. ^ a b "Racecourse Road, Pakenham". Victoria’s Big Build. 22 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  180. ^ "Webster Street, Dandenong". Victoria’s Big Build. 21 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  181. ^ a b "Webb Street, Narre Warren". Victoria’s Big Build. 7 September 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  182. ^ "Cave Hill Road, Lilydale". Victoria’s Big Build. 21 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  183. ^ "Bedford Road, Ringwood". Victoria’s Big Build. 29 August 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  184. ^ "Brunt Road, Beaconsfield". Victoria’s Big Build. 21 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  185. ^ a b "Keon Parade, Reservoir". Victoria’s Big Build. 9 September 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  186. ^ "Station Street, Officer". Victoria’s Big Build. 21 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  187. ^ a b "Dublin Road, Ringwood East". Victoria’s Big Build. 29 August 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  188. ^ a b "Coolstore Road, Croydon". Victoria’s Big Build. 7 September 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  189. ^ Victoria’s Big Build (22 November 2023). "Warrigal Road, Mentone". Victoria’s Big Build. Archived from the original on 20 September 2022. Retrieved 13 December 2023.
  190. ^ a b "Parkers Road, Parkdale". Victoria’s Big Build. 21 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  191. ^ "Calder Park Drive, Calder Park". Victoria’s Big Build. 21 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  192. ^ "Progress Street, Dandenong South". Victoria’s Big Build. 21 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  193. ^ Victoria’s Big Build (3 May 2024). "Piling works underway at Progress Street". Victoria’s Big Build. Retrieved 3 May 2024.
  194. ^ "Station Street, Beaconsfield". Victoria’s Big Build. 21 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  195. ^ "Holden Road, Calder Park". Victoria’s Big Build. 21 June 2022. Archived from the original on 20 September 2022. Retrieved 19 September 2022.
  196. ^ "Victorian opposition pledges to cap public transport fares at $2 a day". ABC News. 9 October 2022. Archived from the original on 9 October 2022. Retrieved 9 October 2022.
  197. ^ "Level Crossing Removal Project". Victoria’s Big Build. 19 September 2022. Archived from the original on 21 September 2022. Retrieved 9 October 2022.
  198. ^ a b Victoria’s Big Build (10 October 2023). "Old Calder Highway, Diggers Rest". Victoria’s Big Build. Archived from the original on 17 April 2023. Retrieved 1 December 2023.
  199. ^ a b "Site establishment works continue in Diggers Rest". levelcrossingremovalproject.cmail20.com. Retrieved 31 May 2024.
  200. ^ a b c d Victoria’s Big Build (14 November 2023). "Mordialloc level crossings". Victoria’s Big Build. Archived from the original on 4 December 2023. Retrieved 1 December 2023.
  201. ^ a b Victoria’s Big Build (2 October 2023). "Maddox Road and Champion Road, Newport". Victoria’s Big Build. Archived from the original on 4 December 2023. Retrieved 1 December 2023.
  202. ^ a b c d e Victoria’s Big Build (27 November 2023). "Melton level crossing removals". Victoria’s Big Build. Archived from the original on 5 December 2023. Retrieved 1 December 2023.
  203. ^ Victoria’s Big Build (2 August 2023). "Maidstone Street, Altona". Victoria’s Big Build. Archived from the original on 4 December 2023. Retrieved 1 December 2023.
  204. ^ Victoria’s Big Build (24 February 2023). "Ruthven Street, Macleod". Victoria’s Big Build. Archived from the original on 25 March 2023. Retrieved 1 December 2023.
  205. ^ a b c Victoria’s Big Build (24 February 2023). "Werribee Line level crossing removals". Victoria’s Big Build. Archived from the original on 27 October 2022. Retrieved 1 December 2023.
  206. ^ a b c Victoria’s Big Build (7 March 2023). "Seaford level crossings". Victoria’s Big Build. Archived from the original on 4 December 2023. Retrieved 1 December 2023.
  207. ^ a b c d e f Victoria’s Big Build (7 September 2023). "Frankston Line level crossing removals". Victoria’s Big Build. Archived from the original on 4 December 2023. Retrieved 1 December 2023.
  208. ^ a b c d e f g h i j k Victoria’s Big Build (4 October 2023). "Brunswick and Parkville". Victoria’s Big Build. Archived from the original on 8 April 2023. Retrieved 1 December 2023.
  209. ^ Carey, Adam (15 November 2016). "Hawkstowe is go: Third train station announced for Mernda rail extension". The Age. Archived from the original on 20 September 2022. Retrieved 20 September 2022.
  210. ^ Boseley, Matilda (1 April 2018). "Mernda train line ahead of schedule". The Age. Archived from the original on 20 September 2022. Retrieved 20 September 2022.
  211. ^ "Pakenham East Station location fact sheet". Victoria’s Big Build. 19 June 2022. Archived from the original on 20 September 2022. Retrieved 20 September 2022.
  212. ^ Carton, Donna (24 November 2017). "Southland Station finally ready to open this Sunday". Herald Sun Leader.
  213. ^ "A 'Union' of 2 communities and more open space in the heart of Union Road". Victoria’s Big Build. 28 March 2022. Archived from the original on 20 September 2022. Retrieved 20 September 2022.
  214. ^ Abbott, Lachlan (17 August 2022). "Barred from their own street, residents fume at handling of level crossing works". The Age. Archived from the original on 20 September 2022. Retrieved 20 September 2022.
  215. ^ Victoria’s Big Build (22 June 2022). "Burke Road, Glen Iris". Victoria’s Big Build. Archived from the original on 24 October 2022. Retrieved 2 December 2023.
  216. ^ Victoria’s Big Build (21 June 2022). "McKinnon Road, McKinnon". Victoria’s Big Build. Archived from the original on 25 February 2023. Retrieved 2 December 2023.
  217. ^ Victoria’s Big Build (21 June 2022). "Centre Road, Bentleigh". Victoria’s Big Build. Archived from the original on 25 February 2023. Retrieved 2 December 2023.
  218. ^ Victoria’s Big Build (21 June 2022). "North Road, Ormond". Victoria’s Big Build. Archived from the original on 25 February 2023. Retrieved 2 December 2023.
  219. ^ Victoria’s Big Build (21 June 2022). "Furlong Road, St Albans". Victoria’s Big Build. Archived from the original on 17 April 2023. Retrieved 2 December 2023.
  220. ^ Victoria’s Big Build (21 June 2022). "Main Road, St Albans". Victoria’s Big Build. Archived from the original on 17 April 2023. Retrieved 2 December 2023.
  221. ^ Victoria’s Big Build (21 June 2022). "Mountain Highway, Bayswater". Victoria’s Big Build. Archived from the original on 24 February 2023. Retrieved 2 December 2023.
  222. ^ Victoria’s Big Build (21 June 2022). "Heatherdale Road, Mitcham". Victoria’s Big Build. Archived from the original on 20 September 2022. Retrieved 2 December 2023.
  223. ^ "Southland Station Set For A Festive Opening". Premier of Victoria. 22 October 2017. Archived from the original on 7 November 2017. Retrieved 31 October 2017.
  224. ^ Victoria’s Big Build (21 June 2022). "Heatherton Road, Noble Park". Victoria’s Big Build. Archived from the original on 7 April 2023. Retrieved 2 December 2023.
  225. ^ Victoria’s Big Build (21 June 2022). "Clayton Road, Clayton". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 2 December 2023.
  226. ^ Victoria’s Big Build (21 June 2022). "Lower Plenty Road, Rosanna". Victoria’s Big Build. Archived from the original on 25 March 2023. Retrieved 2 December 2023.
  227. ^ Victoria’s Big Build (21 June 2022). "Koornang Road, Carnegie". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 2 December 2023.
  228. ^ "Frankston Station Precinct Redevelopment". economicdevelopment.vic.gov.au. Archived from the original on 11 November 2017. Retrieved 5 January 2018.
  229. ^ Victoria’s Big Build (21 June 2022). "Murrumbeena Road, Murrumbeena". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 2 December 2023.
  230. ^ Victoria’s Big Build (21 June 2022). "Poath Road, Hughesdale". Victoria’s Big Build. Archived from the original on 24 October 2023. Retrieved 2 December 2023.
  231. ^ a b c Victoria’s Big Build (25 January 2021). "Mernda Rail Extension". Victoria’s Big Build. Archived from the original on 27 February 2021. Retrieved 2 December 2023.
  232. ^ Victoria’s Big Build (14 April 2023). "High Street, Reservoir". Victoria’s Big Build. Archived from the original on 1 April 2023. Retrieved 2 December 2023.
  233. ^ Victoria’s Big Build (21 June 2022). "Station Street, Carrum". Victoria’s Big Build. Archived from the original on 20 September 2022. Retrieved 2 December 2023.
  234. ^ Victoria's Big Build (21 June 2022). "Balcombe Road, Mentone". Victoria's Big Build. Archived from the original on 1 March 2023. Retrieved 2 December 2023.
  235. ^ Victoria’s Big Build (22 June 2022). "Charman Road, Cheltenham". Victoria’s Big Build. Archived from the original on 20 September 2022. Retrieved 2 December 2023.
  236. ^ Victoria’s Big Build (22 June 2022). "Bell Street, Coburg". Victoria’s Big Build. Archived from the original on 9 April 2023. Retrieved 2 December 2023.
  237. ^ Victoria’s Big Build (22 June 2022). "Moreland Road, Brunswick". Victoria’s Big Build. Archived from the original on 9 April 2023. Retrieved 2 December 2023.
  238. ^ Victoria’s Big Build (16 June 2022). "Your new Lilydale Station". Victoria’s Big Build. Archived from the original on 2 December 2023. Retrieved 2 December 2023.
  239. ^ Victoria’s Big Build (24 February 2023). "Manchester Road, Mooroolbark". Victoria’s Big Build. Archived from the original on 2 December 2023. Retrieved 2 December 2023.
  240. ^ Victoria’s Big Build (21 June 2022). "Bondi Road, Bonbeach". Victoria’s Big Build. Archived from the original on 2 December 2023. Retrieved 2 December 2023.
  241. ^ Victoria’s Big Build (21 June 2022). "Chelsea Road, Chelsea". Victoria’s Big Build. Archived from the original on 25 February 2023. Retrieved 2 December 2023.
  242. ^ Victoria’s Big Build (21 June 2022). "Edithvale Road, Edithvale". Victoria’s Big Build. Archived from the original on 25 February 2023. Retrieved 2 December 2023.
  243. ^ Victoria’s Big Build (24 February 2023). "Ferguson Street, Williamstown". Victoria’s Big Build. Archived from the original on 24 October 2022. Retrieved 2 December 2023.
  244. ^ "Merinda Park Station Precinct | Cranbourne Line Upgrade". Engage Victoria. Archived from the original on 1 March 2023. Retrieved 2 December 2023.
  245. ^ Victoria’s Big Build (26 October 2022). "Hallam Road, Hallam". Victoria’s Big Build. Archived from the original on 20 September 2022. Retrieved 2 December 2023.
  246. ^ Victoria’s Big Build (12 April 2023). "Glenroy Road, Glenroy". Victoria’s Big Build. Archived from the original on 11 April 2023. Retrieved 2 December 2023.
  247. ^ a b Victoria’s Big Build (6 September 2023). "Happy 1st birthday to the new Preston and Bell stations". Victoria’s Big Build. Archived from the original on 2 December 2023. Retrieved 2 December 2023.
  248. ^ Victoria’s Big Build (26 July 2023). "Mt Derrimut Road, Deer Park". Victoria’s Big Build. Archived from the original on 10 July 2023. Retrieved 2 December 2023.
  249. ^ Victoria’s Big Build (16 March 2023). "Montmorency upcoming major works in March and April". Victoria’s Big Build. Archived from the original on 2 December 2023. Retrieved 2 December 2023.
  250. ^ Victoria’s Big Build (29 May 2023). "Union Road, Surrey Hills". Victoria’s Big Build. Archived from the original on 18 February 2023. Retrieved 2 December 2023.
  251. ^ Victoria’s Big Build (29 May 2023). "Union Road, Surrey Hills". Victoria’s Big Build. Archived from the original on 18 February 2023. Retrieved 2 December 2023.
  252. ^ Victoria’s Big Build (25 September 2023). "Glen Huntly Road, Glen Huntly". Victoria’s Big Build. Archived from the original on 20 September 2022. Retrieved 2 December 2023.