You can help expand this article with text translated from the corresponding article in Chinese. (June 2015) Click [show] for important translation instructions.
Machine translation, like DeepL or Google Translate, is a useful starting point for translations, but translators must revise errors as necessary and confirm that the translation is accurate, rather than simply copy-pasting machine-translated text into the English Wikipedia.
Do not translate text that appears unreliable or low-quality. If possible, verify the text with references provided in the foreign-language article.
You must provide copyright attribution in the edit summary accompanying your translation by providing an interlanguage link to the source of your translation. A model attribution edit summary is Content in this edit is translated from the existing Chinese Wikipedia article at [[:zh:屏東線]]; see its history for attribution.
You may also add the template {{Translated|zh|屏東線}} to the talk page.
It is 61.3 km (38.1 mi) long, of which 36.1 km (22.4 mi) is double track.[2]
The section between Nanzhou and Linbian railway stations will be upgraded from a single-track railway to a double-track railway in December 2019 while the section between Chaozhou and Nanzhou, and the section between Linbian and Fangliao is expected to remain in single-track.[3]
Taiwanese government stated in 2007 that it reserved the possibility to upgrade the entire section to dual-track railway when the number of travelers through Pingtung Line reaches a certain level [4]
History
The line was completed in 1941. The section between Kaohsiung and Pingtung was electrified on July 10, 1996.[5] The section between Pingtung and Chaozhou was electrified on August 23, 2015, when the elevated tracks between the two stations opened.[6]
Chaozhou–Fangliao upgrades
Immediately following the completion of the elevated tracks between Pingtung and Chaozhou, the TRA began planning for the electrification of the last section of the line between Chaozhou and Fangliao. The plan was approved by the Ministry of the Interior on June 3, 2013, and construction began on November 16, 2014.[7]
Aside from electrifying the tracks, the following upgrades were carried out simultaneously:[7]
Extending and raising platforms at all stations to cater to low-floor trains
The infrastructure was completed in October 2019, and beginning on November 8, test runs using electric trains were carried out on the line. The electrified tracks officially entered service on December 23, 2019.[7][8]