ElecLink

ElecLink
Map
Map of ElecLink
Location
CountryUnited Kingdom, France
Coordinates51°5′54.2″N 1°8′40.9″E / 51.098389°N 1.144694°E / 51.098389; 1.144694 (Folkestone Converter Station)
50°55′12.7″N 1°46′50.2″E / 50.920194°N 1.780611°E / 50.920194; 1.780611 (Peuplingues Converter Station)
General directionNorth–South
FromFolkestone, United Kingdom
Passes throughEnglish Channel
ToPeuplingues, France
Ownership information
OwnerGetlink
Construction information
Manufacturer of conductor/cablePrysmian[1]
Manufacturer of substationsSiemens
ContractorsBalfour Beatty
Construction started2017
Construction cost£490 million[2]
Commissioned25 May 2022
Technical information
Typesubmarine cable
Type of currentHVDC
Total length51 km (32 mi)
Power rating1,000 MW
DC voltage±320 kV
No. of poles2
No. of circuits1
Websitewww.eleclink.co.uk

ElecLink is a 1,000 MW high-voltage direct current (HVDC) electrical interconnector between the United Kingdom and France, passing through the Channel Tunnel. ElecLink commenced operations on 25 May 2022.

Route

The 51-kilometre (32-mile) DC cable runs via the Channel Tunnel between HVDC converter stations at Peuplingues in France and Folkestone in the UK, with an additional 14.5 km (9.0 mi) of underground AC cable on the English side to Sellindge substation, and 3.5 km (2.2 mi) on the French side to Les Mandarins substation,[3] to link the converter stations to the existing transmission networks.[4]

Ownership

It is owned by a subsidiary of Getlink, which owns the tunnel itself.

ElecLink is the first UK interconnector to be entirely funded by private finance, without being underwritten by electricity consumers.[5]

Construction

The two convertor stations were constructed by Siemens and the Siemens FIT (Field Installation Team). The HVDC cables and the cable between the Folkstone convertor station and the National Grid substation at Sellindge were constructed by Prysmian and installed by Balfour Beatty, while RTE constructed the cable between the Peuplingues convertor station and the Les Mandarins substation.[3][1]

A specialized, 51-metre-long (167 ft), work train was manufactured by Clayton Equipment for the project to allow the HVDC cable to be installed[6][5] in 2021 and tested.[7] The train contained drilling modules, monorail modules, jointing platforms and hauling equipment, as well as staff accommodations and was entirely battery-powered.

In the entire length of the tunnel, a hexagonal monorail track was installed, as well as two, 7-metre-high (23 ft) high, 4-track helices (one on each end), that was straddled by a cable carrier which could carry sections of 2.5 km (1.6 mi) of HVDC cable into the tunnel. The actual cable pull happened between February and summer 2021, with cable sections then spliced in cleanrooms inside the tunnel.[3][8] The monorail was later removed.

Project history

Work commenced on the project in 2017.[2]

The foundation stone of the Folkestone converter station was laid in February 2017, by Jesse Norman MP, Minister for Industry and Energy.[9]

In 2019, the Anglo-French Channel Tunnel Intergovernmental Commission (IGC), which oversees the safety of the Channel Tunnel, suspended part of the project's consent due to concerns about safety of the HVDC cables within the tunnels.[10] This decision prevented the cables from being installed. The IGC was expected to make a final decision on whether the cables can be installed in April 2020, based on a recommendation from the Channel Tunnel Safety Authority,[11] however this approval was again delayed due to further safety concerns and the COVID-19 pandemic.[12]

In December 2020, the IGC announced its approval of the project, with the cable expected to be installed by summer 2021 and commercial operation expected to start in mid-2022.[12]

In February 2022, the IGC and national safety authorities announced their approval of ElecLink, which allowed final testing of the interconnector to commence, with entry into service still planned for mid-2022.[13]

ElecLink commenced operations on 25 May 2022.

See also

References

  1. ^ a b Sharpe, Lorna (24 February 2017). "ElecLink awards Channel Tunnel interconnector construction contract". E&T. Retrieved 22 February 2020.
  2. ^ a b Shrestha, Priyanka (24 February 2017). "Work begins on £490m UK-France power link". Energy Live News. Retrieved 22 February 2020.
  3. ^ a b c "The ElecLink Project" (PDF). Eleclink.
  4. ^ "What we do". ElecLink. Retrieved 22 February 2020.
  5. ^ a b "The ElecLink Project" (PDF). ElecLink. November 2019.
  6. ^ "Channel Tunnel interconnector installation train completed". Railway Gazette. 4 March 2018.
  7. ^ "1 GW ElecLink is ready for full operations now". 4c Offshore. 5 October 2021. Archived from the original on 8 October 2021.
  8. ^ "Putting power through the tunnel" (PDF). Rail Infrastructure. No. 38. NPT Publishing. Retrieved 12 March 2023.
  9. ^ "Eurotunnel Press Release 23 Feb 2017" (PDF). eleclink. Retrieved 7 April 2017.
  10. ^ Spero, Josh (24 March 2019). "'Eyebrows raised' over Eurotunnel cable finance disclosure". Financial Times.(subscription required)
  11. ^ "IGC Statement on ElecLink project". Channel Tunnel IGC. 9 January 2020. Retrieved 23 February 2020.
  12. ^ a b "UK-France Eleclink power interconnector approved". Argus Media. 21 December 2020.
  13. ^ "ElecLink: The Intergovernmental Commission and the national safety authorities give the go-ahead". Getlink Group. 17 February 2022. Retrieved 12 April 2022.