In 2016, the newly created West Midlands Combined Authority revived the plans to restore local passenger services to the line, and declared it one of their priority transport schemes to be delivered by 2025.[10][11]
In 2019, the project to re-open the stations at Moseley, Kings Heath, and Hazelwell received £15 million in Government funding, with construction due to start in 2020 and aimed for completion in time for the 2022 Commonwealth Games.[12] In March 2021 it was announced that funding had been found for the project.[13] The reopening of the line has been hit by delays and the West Midlands Combined Authority is now aiming to reopen the line for passenger use by the end of 2024.[14]
A vote was held to determine the name of the station upon reopening, determined to be either 'Moseley' or 'Moseley Village'.[15] On 14 June 2022, it was announced that the reopened station would be called Moseley Village.[16]