Pipe Pacific Cable
PIPE Pacific Cable (PPC-1) is a 6,900 km submarine cable laid by PIPE Networks. It runs from Cromer, New South Wales, in Australia, to Piti, Guam.[1] It resulted in huge international backhaul cost savings to Australian customers, for access to the US internet backbone,[2] quoting up to "50% savings" versus existing cable operators.[3] CapacityQuoting directly from PIPE International's PPC-1's Blog, substantial capacity will be available on the submarine cable network:[4]
During the official launch, PIPE Network's CEO Bevan Slattery said the new cable would now deliver speeds at an even greater capacity than originally planned, 2.56 terabits per second in total.[5] In September 2012, an upgrade was announced that would take the capacity available on the cable past the original design capacity of 2.56 terabits per second, to around 3 terabits per second.[6] ConstructionSubmarine cable laying commenced at the end of April 2009. The Guam to Papua New Guinea segment of the cable was completed in May 2009, with the ship Tyco Durable[7] commencing on the 4 segments from Sydney to Papua New Guinea. In June 2009, most cabling work south of Brisbane was completed,[8] leaving two cable segments—from BU2 (Branching Unit) near Brisbane up to BU4 near Madang[9] – to be laid before commissioning. On 23 August 2009 the first light signal was transmitted over the completed cable from Sydney to Guam.[10] This marked the completion of the submarine cabling work, and testing of the system began. On 22 September 2009, Internode released a press release claiming successful transmission of IP packets across the cable, making it the first commercial entity to make use of the cable.[11] The project was formally completed on 8 October 2009.[12] Cable landing pointsThe cable runs from Sydney to Guam. The cable landing points are:
Financial RealignmentOn 19 December 2008, it was reported that a "realignment of payments" was organised between PIPE, its PPC-1 customers, and Tyco Telecom, the primary contractor on the project. Some saw this as PPC-1 striking financial difficulties, however the timing of payments were realigned to allow Tyco to continue the work with respect to meeting the construction deadline of July 2009.[14] PIPE delivered a media release confirming this realignment, and the signing of a memorandum of understanding with Tyco Telecom, and a key customer, to secure the financial go-ahead for the project.[15] It confirmed that:
See also
References
External links
|