In January 2015 the multibillion-dollar construction contract for the bridge was awarded to Arkady Rotenberg's Stroygazmontazh. Construction began
in February 2016.[a] The road bridge was inaugurated by Russian President Vladimir Putin on 15 May 2018. It opened for cars on 16 May and for trucks on 1 October.[7][17] The rail bridge was inaugurated on 23 December 2019 and the first scheduled passenger train crossed the bridge two days later. The bridge was opened for freight trains on 30 June 2020. A record amount of traffic, totalling 36,393 cars, was recorded on 15 August 2020.[18]
The bridge was named the Crimean Bridge after an online vote in December 2017, whilst Kerch Bridge and Reunification Bridge were the second and third most popular choices respectively.[19]
During the Russian invasion of Ukraine, the bridge was attacked on multiple occasions. On 8 October 2022, an explosion occurred on the roadway leading from Russia to Crimea, causing parts of the road bridge to collapse and starting a large fire on the rail bridge. On 23 February 2023, the Russian government announced that the road bridge had been fully reopened to traffic, and on 5 May it announced that the rail bridge had been fully reopened. On 17 July 2023, another explosion occurred adjacent to the road bridge, causing a section to collapse, Ukraine claimed both attacks. On 12 August 2023, the bridge was the target of another attack. The bridge was fully reopened on 14 October.
During World War II the German Organisation Todt built a ropeway over the strait. Finished in June 1943, it had daily capacity of 1,000 tonnes. Construction of a combined road and railway bridge started in April 1943, but before it was finished, retreating German troops blew up the completed parts of the bridge and destroyed the ropeway.[20][21]
In late 1944–early 1945, the Soviet Union constructed a 4.5-kilometre (2+3⁄4 mi) railway bridge across the strait. This bridge, not designed as permanent, was marred by design and construction errors, and was destroyed by flowing ice in February 1945.[22] A proposal to repair it was quickly dismissed and the remnants of the bridge were dismantled, with permanent bridge designs envisaged instead.
Soviet proposals
In 1949 the Soviet government ordered the construction of a 5.969-kilometre (3 mi 1,248 yd) two-tier combined road-rail bridge (two road lanes on the upper tier and two rail tracks on the lower tier) with 40 m clearance below, connecting Yeni-Kale with Chushka Spit, but in 1950 construction was halted and a ferry line was set up instead.[21]
A different version of the fixed link, the Kerch waterworks project («Керченский гидроузел») was developed from the mid-1960s, proposing a system of dams and bridges across the strait. The project was not implemented due to a lack of funding[23] and the later collapse of the Soviet Union.[24][25]
Negotiations between the Ukrainian and Russian governments
Although the idea of an international bridge linking Ukraine and Russia survived the 1991 dissolution of the Soviet Union, the two countries failed to finalise the project.[26] Former Moscow mayor Yury Luzhkov was a vocal advocate for a highway bridge across the strait, expressing hope that it would bring the Crimean people closer to Russia, both economically and symbolically.[26] Similar hopes were expressed by pro-Russian authorities in Crimea, who hoped that the bridge would contribute to either a "revival of the Silk Road" or to a multinational road along the Black Sea coast.[23][f]
Construction of the bridge was reconsidered by the Cabinet of Ministers of Ukraine in 2006, and the Transport Minister of Ukraine Mykola Rudkovsky stated that he expected the bridge to be a "net positive for Crimea" as it would allow "every tourist visiting Russian Caucasus to visit Crimea as well".[28][29] The issue was discussed by prime ministers of both countries in 2008,[30] and a Transport Strategy of Russia, adopted in that year, envisaged the construction of the Kerch Strait bridge as a high priority issue for the development of the Southern Federal District's transport infrastructure in the period 2016–2030, with the design ready by 2015.[31]
Possible alignments of the proposed bridge as of 2002.[32]
("Tuzla" or "Southern") ultimately became the basis for the Crimean Bridge built by Russia
(Cape Fonar – Cape Maly Kut, also known as "Northern route") was preliminarily preferred by the Ukrainian government in 2011.
In 2010, Ukrainian PresidentViktor Yanukovych and Russian President Dmitry Medvedev signed the Kharkiv Pact, an agreement to build a bridge across the Kerch Strait,[33] and Russia and Ukraine signed a memorandum of understanding on the construction of the bridge on 26 November 2010.[34] A 2011 study by the Ukrainian government announced preliminary preference for a route between Cape Fonar and Cape Maly Kut. Had that project been carried out, it would have meant construction of a 10.92 km (6 mi 1,382 yd) bridge link, with 49 km (30+1⁄2 mi) of adjacent roads and 24 km (15 mi) of adjacent railroads.[35]
The shelving of the Ukraine–European Union Association Agreement in November 2013 led to increased interest in the construction of a bridge between Crimea and the Taman Peninsula of Russia,[36] and an agreement on the construction of that bridge was signed as a part of the 17 December 2013 Ukrainian–Russian action plan. In late January 2014, the Ukrainian and Russian governments decided that a new joint Ukrainian–Russian company would be commissioned to handle the construction of the bridge, while the Russian state enterprise Russian Highways (commonly known as Avtodor) would become responsible for the bridge in the long term.[36]
In the following months, as relations between Ukraine and Russia deteriorated, bilateral negotiations over the bridge collapsed,[37] yet Russia claimed that it expected the December 2013 deals to be honoured, and on 3 March prime minister Dmitry Medvedev signed a governmental decree to create a subsidiary of Avtodor to oversee the project.[38] A contest for the engineering survey of the bridge project was announced by that subsidiary on 18 March,[39] but by that time the premise of the contest, which still referred to 2013 agreements,[40] was already outdated. In April 2014, following the Russian annexation of Crimea the Ukrainian government gave Russia six months' notice of its withdrawal from the now-defunct bilateral Kerch Bridge agreement.[41]
Following the Russian annexation of Crimea in March 2014 amid a sharp deterioration in Ukrainian-Russian relations, Russia declared it would unilaterally build the Kerch Strait bridge to connect the Russian mainland with the annexed Ukrainian peninsula. The project was strategic, an instrumental part of Russian plans to integrate the newly annexed territory into Russia.[42] The project aimed to shift Crimean dependence on Ukraine and reduce Kyiv's leverage,[43] remove Moscow's reliance upon inadequate sea and air links for supplying the peninsula,[44][14] and allow Russia to independently supply Crimea, whose economy has become dependent upon significant subsidies from Moscow. The bridge has a symbolic purpose: it is meant to show Russia's resolve to hold Crimea,[42] and as a "physical" attachment of Crimea to Russian territory.
The announcement that Russia would build a road-rail bridge over the strait was made by the Russian PresidentVladimir Putin on 19 March 2014,[45][46] just one day after Russia formally claimed Crimea. In January 2015, the contract for construction of the bridge was awarded to the SGM Group, whose owner Arkady Rotenberg (reportedly a close personal friend of Putin) was internationally sanctioned in response to the Russian military's involvement in Ukraine. SGM typically constructed pipelines and had no experience building bridges, according to BBC News.[47]
The construction of the Kerch Bridge took place without Ukraine's consent.[41] The Ukrainian government has actively condemned Russian construction of the bridge[48] as illegal[49] because Ukraine, "as a coastal state with regard to the Crimean Peninsula", did not give its consent to such construction,[50] and called on Russia to demolish "those parts of that structure located within temporarily occupied Ukrainian territory".[51]Sanctions were introduced by the United States and the European Union against companies involved in the construction.[52][53]
Since December 2018 the United Nations General Assembly has repeatedly condemned the construction and opening of the bridge as "facilitating the further militarization of Crimea"[54][55] and "restricting the size of ships that can reach the Ukrainian ports on the Azov coast".[56] Russia, on the other hand, asserted that it "shall not ask for anybody's permission to build transport infrastructure for the sake of the population of Russian regions".[57]
During the invasion there were two large explosions, in October 2022 and July 2023, on the bridge. According to the BBC a source in Ukraine's security service said that the 2023 explosion was caused by a Ukrainian attack with unmanned surface vessels (aquatic drones). Russia attributed the attacks to "Ukrainian terrorism". A Ukrainian defence official also said that Ukraine had carried out the October 2022 attack; the BBC was unable to verify the claims independently.[61]
In a speech to the Aspen Security Forum in July 2023, Ukrainian President Volodymyr Zelenskyy called the bridge a legitimate military target for Ukraine that must be "neutralized" for "feeding the war with ammunition" and "militarizing the Crimean Peninsula."[62]
On 8 October 2022 a major explosion occurred on the bridge, causing portions of the Crimea-bound road segment to collapse and causing several oil tanker wagons on the rail section to catch fire. Vladimir Konstantinov, Chairman of the State Council of Crimea, attributed the explosion to a Ukrainian attack.[63] Limited traffic resumed on the remaining lines shortly afterwards.[64][65] Russian authorities ordered repairs to be complete by July 2023.[66]
On 6 January 2023, TASS reported that the first two spans of the left side of the Crimean Bridge's automobile part leading from the peninsula would be installed that month, with two more to be installed in February, the Federal Road Agency (Rosavtodor) said in a message.[67]
The road bridge was fully opened again to traffic on 23 February 2023 according to an announcement from Russian Deputy Prime Minister Marat Khusnullin.[68] On 5 May the deputy prime minister also announced that the rail bridge had been fully reopened.[69]
In the early morning of 17 July 2023 two explosions hit the Crimean Bridge. At least one section of the road bridge collapsed entirely,[70] and rail services were stopped. Two people, a couple who were in a car on the bridge, were killed, and their child injured.[71] The bridge was struck twice before 03:00 according to reports on social media;[72][73] Ukrainian and Russian sources indicated that the explosion was caused by a Ukrainian attack with unmanned surface vessels (aquatic drones).[61] The bridge was fully reopened on 14 October.[74]
August 2023 attack
On 12 August, Russia's Defence Ministry said that Ukraine tried to strike the bridge with three S-200 missiles but were unsuccessful due to interception by air defences. Footage released online appeared to show the bridge covered in smoke.[75][76] The bridge was temporarily closed, then both road and rail traffic resumed at a limited level.[76][77]
Design
After the annexation, Russian officials looked at various options for connecting Crimea to the Russian mainland, including a tunnel, but eventually settled on a bridge.[42]
The Russian government's draft resolution of 1 September 2014 required the bridge to have four lanes of vehicle traffic and a double-track railway.
An official video from October 2015 contained a CGI concept of the bridge design, annotated with various measurements. It showed a four-lane, flat deck highway bridge running parallel with the separate two-track railway. The main span over the Kerch Strait shipping channel would have a steel arch support, 227 m (745 ft) wide with a 35 m (115 ft) clearance above the water to allow ships to pass under. There would be three segments: from the Taman Peninsula to Tuzla Spit is 7 km (4 mi); across Tuzla Island is 6.5 km (4 mi); and from Tuzla Island to the Crimean Peninsula is 5.5 km (3+1⁄2 mi) (19 km or 12 mi total).
The final concept was a major change from the initial project considered in late 2014, which had envisaged construction of two bridge links (parallel road and rail bridges between the Taman Peninsula and the Tuzla Spit and a double deck road-rail bridge between Tuzla Island and the Kerch Peninsula) and a causeway on Tuzla Spit.[81] This design was scrapped, the causeway being deemed too risky to rely on given the instability of the Tuzla Spit.[82]
The official reason for abandonment of a double deck bridge in favor of two continuous parallel structures was that the latter solution allows for less massive spans and for simultaneous construction of both bridges (rather than having to construct one level of bridge first before starting the second one), an important consideration given demands by the Russian government that road and rail links be operational quickly.[83] The "Tuzla route" was preferred over shorter variants (starting at Chushka Spit), in particular because doing otherwise would have interfered with the still operational ferry line,[84] to the effect of worsening transport communications between Russia and Crimea.[85]
The bridge was built by Stroygazmontazh Ltd (SGM), which had never before built a major bridge. Because of the risk of sanctions, no international insurance company was willing to underwrite the potential $3 billion loss. It was insured instead by a small Crimean company.[86]
The geology of the Kerch Strait is difficult: it has a tectonic fault, and the bedrock is covered by a 60 m (197 ft) layer of silt.[86] About 70 mud volcanoes have been found in the area of the strait.[86] More than 7,000 piles support the bridges; these piles have been driven up to 90 m (300 ft) beneath the water surface.[86] Some of the piles are at an angle to make the structure more stable during earthquakes.[86] Some experts expressed doubts that the construction was safe, given the tectonic and sea current conditions in the strait.[86][87]
Construction
Preliminary work on the bridge began in May 2015. More than 200 bombs[88] and a few aeroplanes (including an Ilyushin Il-2[89] and a Curtiss P-40 Kittyhawk)[90] from the World WarII era were found in the area during pre-construction clearance. Three temporary bridges were built to facilitate access (independent of weather and currents) for main construction.[91] By October 2015, the first of the temporary bridges had been constructed, connecting Tuzla Island and Taman Peninsula.[92]
Main construction started in February 2016.[93] The first piles were installed in early 2016,[94] and in April 2016 the first pillar of the road bridge was constructed.[95] The foundations of the road bridge were completed in August 2017.[96] The two shipping channel arches (over the Kerch–Yenikale Canal) were lifted into position in August and October that year.[97]
In October 2017, National Guard of Russia Director Viktor Zolotov announced the formation of a new "maritime brigade", intended to protect the bridge as part of Russia's Southern Military District.[98] In December 2017 all road pillars and spans were completed,[99][100] by April 2018 asphalt concrete was laid onto the road bridge,[101] and after some examination the road bridge was deemed ready for operation.[102]
On 15 May 2018, the road bridge was officially unveiled. President Vladimir Putin led a convoy of trucks, driving one himself, across the bridge in an inauguration ceremony.[103] The bridge was opened for non-truck vehicle traffic on 16 May 2018[7] and for trucks on 1 October.[8]
The construction of the rail bridge continued. In June 2018 pile installation was finished,[104] and in July 2018 deployment of the rail tracks started.[105]
In October 2018, the Russian Taman Road Administration reported that as one of the railway spans was being lowered into place, it tilted and fell into the sea. This occurred in the sea section between Tuzla Spit and Tuzla Island.[106] In November 2018 the installation of the railway pillars was completed.[107]
On 24 March 2019 the bridge's press centre reported completion of construction of railway spans,[108] and on 18 July it reported completion of the bridge's rail tracks.[109] In October 2019, the opening for freight trains was postponed until 2020, the official cause was a delay in the construction of the connecting railroad caused by the discovery of an ancient site on the Kerch Peninsula.[110][111] Sale of train tickets across the Kerch Strait started in November 2019.[112] On 18 December 2019 the rail bridge was deemed ready for operation,[113][114] and President Putin formally opened the bridge on 23 December.[115] The first scheduled passenger train crossed the bridge on 25 December 2019,[116] while the bridge was opened for freight trains on 30 June 2020.[117]
The rail bridge design provides the ability to install an overheadrailway electrification system "whenever such decision will be made", requiring no rebuilding of the bridge's structures. Pending electrification, the rail bridge is served by diesel locomotives.[118]
Construction of supports and installation of the first spans of the railway bridge from the side of Kerch. At the same time, the construction site is backfilled and the assembly of the bridge arches begins.
Construction of the bridge pillars
Asphalting the finished section of the road bridge from the side of Taman. On the opposite side, construction work is underway to connect the temporary ramp with the bridge.
Concrete casting and asphalting of the overpass spans on Tuzla Island
Completing the assembly of arches on the slipway and preparing them for transportation and installation on fairway supports
The installation of the railway arch in August 2017
The installed arches of the bridge and the process of sliding the spans of the road bridge to the arch
The road bridge on 15 May 2018. The rail bridge – under construction at the time – is visible on the left.
Operation and impact
On Crimea and Russia
The road bridge, opened in 2018, quickly overtook the Kerch Strait ferry as a preferred route of communication between Crimea and Russia. In its first 12 hours of operation the bridge broke the traffic record of the ferry, which had been established in August 2017.[119] After the bridge was opened for trucks in October 2018, truck transportation via the ferry virtually ceased.[120] After the first full year of operation (May 2018 – May 2019) the road bridge had served three times more traffic than the Kerch Strait ferry had served in the whole of 2017.[121]
Since the road bridge is free of charge, in contrast to the ferry, it is claimed that users of the bridge saved more than 16 billion rubles.[122] The bridge is said to have contributed to an increase of the number of tourists visiting the Crimea,[123] with bridge traffic peaking in the summer months – on 5 August 2018 the bridge broke a single-day record for car traffic, with 32,000 vehicles crossing the span,[124] followed by over 33,000 vehicles on 12 August that year[125] and over 35,000 a year later.[126] The long roadway with few diversions occasionally becomes congested, with long traffic queues.[127]
A fall in the price of retail goods in Crimea, which was expected to occur after the opening of the road bridge, did not happen. According to the local Russian administration, this situation persists because large retail groups are not operating in Crimea due to either risk of being sanctioned or because they deem Crimea a "logistic dead end",[123] although there were expectations that the opening of the rail bridge would eventually contribute to a decrease in price of certain goods.[128]
On Ukraine
The Russian bridge crossed the sole access point for ships travelling to and from Ukraine's eastern port cities, including Mariupol and Berdiansk through which Ukraine exported steel and agricultural products.[129] Following completion of the bridge various restrictions were imposed on Ukrainian shipping which affect their operating costs, which Ukraine and others alleged was part of a creeping hybrid blockade of Ukrainian ports in the Azov Sea.[130][131][132]
These restrictions, including Russian inspections of ships, had risen sharply since the bridge opened in May 2018, some being forced to wait for three days before being allowed through.[130][131] Additionally, due to the height limits of the main span of the bridge (33 to 35 metres (108 to 115 ft) above sea level) the Ukrainian maritime authority said many ships are too big to pass safely under the bridge.[131][133] The bulk carrier Copan (deadweight tonnage 17,777 tons) solved this problem by cutting off the top of her mast.[133] On 26 October 2018, The Globe and Mail, citing Ukrainian sources, reported that the bridge had reduced Ukrainian shipping from its Sea of Azov ports by about 25%.[129]
In November 2018, the area near the bridge became the site of the Kerch Strait incident, in which the Russian navy claimed that three Ukrainian vessels entered Russian territorial waters. Russian forces seized the vessels and arrested their crews. During this time, passage through the Strait was blocked by a large cargo ship, placed under the bridge to prevent passage of other craft.[134][135] In response, Ukraine declared martial law in some regions of the country for 30 days.[134]
Archaeology
Part of a large Greek terracotta statue was found at the Crimean Bridge construction site, during underwater digging near the Ak-Burun Cape. According to archaeologists, this is a unique finding, since it is the first of its kind found in the northern Black Sea area.[136]
Gallery
The Crimean Bridge at night
Traffic on the Crimean Bridge, view in direction of Kerch
Train crossing the Crimean Bridge
The Crimean Bridge in May 2020. The infrastructure of the Port of Taman is visible in the background.
A ship passing under the Crimean Bridge
Aerial view of the Crimean Bridge
Explanatory notes
^ abPreliminary work started in May 2015, and the main construction (of the link itself) started in February 2016. See further.
^Opened on 16 May 2018 for non-truck traffic[7] and on 1 October for goods vehicles[8]
^Opened on 25 December 2019 for passenger traffic and on 30 June 2020 for freight trains
^Entire fixed link, including small causeways at the ends. The bridges themselves are 18.1 km (11+1⁄4 mi) (rail) and about 17 km (10+1⁄2 mi) (road) long.[12]
^It is also often considered to be the longest bridge in Russia,[14] but this applies only to de facto Russian territory, including Crimea, since most of the bridge is in the (Autonomous) Republic of Crimea. The Taman–Tuzla Spit part, in undisputed Russian territory, is only 4.5 kilometres (2+3⁄4 mi) long,[12] shorter than the President Bridge in Ulyanovsk Oblast (5.825 km or 3 mi 1,090 yd).
^After the 2014 annexation of Crimea, Russia continued to support the inclusion of the peninsula into that proposed road, claiming that such an option would be economically more feasible, but Ukraine, previously supportive of the project, now stridently opposed it.[27]
^ ab"Крыму начало везти". Коммерсантъ. Archived from the original on 24 October 2020. Retrieved 17 October 2019. Крымский мост 1 октября стал доступен для движения грузового транспорта.
^David M. Herszenhorn (19 March 2014). "Dependence on Russia Is Likely to Leave Region's Economy in a Precarious State". The New York Times. Archived from the original on 14 September 2021. Retrieved 26 July 2018. The process is also fraught with risks, including the possibility that the Ukrainian government could move to further isolate the geographically remote peninsula by shutting vital transportation lines. There is no overland transportation link between Russia and Crimea, and building a bridge across the shortest waterway, near the Crimean city of Kerch, would take years and cost an estimated $3 billion to $5 billion
^Roth, Andrew (15 May 2018). "Putin opens 12-mile bridge between Crimea and Russian mainland". The Guardian. Archived from the original on 22 September 2022. Retrieved 26 July 2018. The 12-mile (19km), $3.7bn (£2.7bn) bridge is Moscow's only direct road link to Crimea. Russia expects it will carry millions of cars and rail travellers and millions of tons of cargo each year. Previously, all car traffic passed over the Kerch strait by ferry or by passing through Ukraine
^Hodge, Nathan. "Russia's bridge to Crimea: A metaphor for the Putin era". CNN. Archived from the original on 13 August 2022. Retrieved 19 September 2018. The United States and most other countries have refused to recognize the annexation of Crimea, and sanctions on Russia don't seem likely to be lifted anytime soon.
^Kolyushev, Igor (August 2018). Технические особенности проектирования Крымского моста [Technical aspects of the designing of the Crimean Bridge] (PDF). Дороги. Инновации в строительстве (in Russian). Archived(PDF) from the original on 25 July 2021. Retrieved 29 November 2019.
^Построена первая опора Керченского моста [First pillar of the Kerch Bridge has been completed]. Interfax.ru (in Russian). Archived from the original on 31 January 2020. Retrieved 28 November 2019.
^Urcosta, Ridvan Bari (23 February 2018). "The Kerch Strait Bridge and Russia's A2/AD Zone around Crimean peninsula". The Ukrainian Weekly. Archived from the original on 10 July 2022. Retrieved 20 June 2022. The ongoing construction of the road-and-rail bridge reached a symbolic high point last year, when central arches were lifted into position in August and October, forcing the temporary closure of the narrow maritime channel to ship traffic...
^"Expert points to vulnerability of Kerch bridge from military perspective". unian.info. Archived from the original on 25 December 2019. Retrieved 28 November 2019. As UNIAN reported, on December 20, the occupiers completed the next stage of the Crimean bridge construction – assembling the span structures of the road section, having fully formed the bridge's sheet from Russia's Taman coast to the occupied Kerch.
^На Крымском мосту уложили первые рельсы [First tracks have been laid onto the Crimean Bridge]. Rossiyskaya Gazeta (in Russian). 25 July 2018. Archived from the original on 25 July 2018. Retrieved 28 November 2019.