Alamitos Energy Center was originally built in the 1950s by Southern California Edison and consisted of seven natural gas-fired generating units that were cooled using a seawateronce-through cooling system. Units 1 and 2 generated 175 MW each, units 3 and 4 generated 320 MW each, and units 5 and 6 generate 480 MW each. Unit 7 generated an unknown amount of electricity and was decommissioned at an unknown date.[4][5][8] The AES Corporation purchased the power station from Southern California Edison in 1998.[9]
Block 1 was constructed between July 2019 and January 2020, and was commissioned on February 7, 2020. Block 2 is planned to be constructed between late 2020 and mid 2022. Construction of the battery energy storage system (BESS) began in June 2019,[2] and was complete in early 2021.[10][11][12]
Decommissioning Units 1-6
As part of the modernization project, all six operating units and the retired Unit 7 will be demolished. Units 1, 2, and 6 were decommissioned on December 31, 2019. Units 3-5 have a retirement date of December 31, 2020. However, in late 2019, AES submitted an application to the California Energy Commission to continue to operate units 3-5 for an additional 1 to 3 years. If approved, demolition of units 3-5 will be delayed for an additional 1 to 3 years.[1]
The water quality in the Alamitos Bay could be degraded by the decommissioning of the Alamitos Energy Center pumps. The City of Long Beach is assessing a replacement for these pumps to maintain the bay's water circulation.[13]
Battery Storage Project
A battery facility with a capacity of 400 megawatt-hours was completed in 2021.[14]