The Western Harbour Tunnel is an under construction tunnel in Sydney, New South Wales, Australia. The six lane, 6.5 kilometre twin tunnels will run from Cammeray to Rozelle, passing beneath Sydney Harbour. It is scheduled for completion in 2028.
The tunnel will form part of the M8 Motorway when it opens. It is expected to cost $14 billion.[1]
The Western Harbour Tunnel was introduced as a single project with the Beaches Link, aimed at reducing the level of traffic congestion in the greater Sydney area. The Sydney Harbour Bridge and Sydney Harbour Tunnel corridor currently carry 80 percent of all vehicles crossing Sydney Harbour and the Parramatta River, greatly increasing traffic congestion.[3] The Government of New South Wales pledged $77 million in funding to evaluate the design and construction feasibility of the project. The design phase began in April 2017.[3][4]
Community engagement and the environment assessment for both components were undertaken during 2020 and 2021.[5] Planning approval was received in January 2021.[6]
Tenders
In December 2020, three potential development partners to assist with the procurement and delivery of the project were shortlisted:[7]
By September 2021, the search for a development partner had been scrapped.[8]
In September 2021 the design and construction contract for the Warringah Freeway upgrade was awarded to a CPB Contractors and Downer Groupjoint venture.[9] In January 2022, the tunnelling contract for stage one of the tunnel between Rozelle and Birchgrove was awarded to a John Holland / CPB Contractors joint venture.[10]
Three bidders were shortlisted for the stage two between Cammeray and Birchgrove:[11]
John Holland / CPB Contractors / UGL joint venture
In December 2022, the contract was awarded to Acciona.[12]
Construction
Early work activities commenced in March 2021, while major construction of the Warringah Freeway upgrade and the Western Harbour Tunnel began in late 2021 and 2022 respectively.[13][14] Construction of stage two commenced in November 2023.[15]
Originally it was planned to sink immersed tubes into the harbour bed. In November 2022 it was decided to instead use tunnel boring machines to bore out tunnels below the harbour floor.[16]
The construction of stub tunnels at the Western Harbour Tunnel portals in Cammeray reserve a future connection to Beaches Link, should it be built by a future government.[17]
Operations and maintenance
In April 2022, the state government signed a 15-year contract with Ventia for the asset management, operations and maintenance of the Sydney Harbour Tunnel and the future Western Harbour Tunnel.[18] Tolling arrangements of both tunnels were unrelated to the new agreement.