Swanbank Power Station

Swanbank Power Station
Swanbank Power Station
Map
CountryAustralia
LocationIpswich, Queensland
Coordinates27°39′35″S 152°48′48″E / 27.659783°S 152.813446°E / -27.659783; 152.813446
StatusOperational
Commission date
  • 1967 (Swanbank A)
  • 1971 (Swanbank B)
  • 1969 (Swanbank C)
  • 2000 (Swanbank D)
  • 2002 (Swanbank E)
Decommission date
  • 2005 (Swanbank A)
  • 2012 (Swanbank B)
  • 2002 (Swanbank C)
  • 2004 (Swanbank D)
OwnerCleanCo Queensland
Thermal power station
Primary fuelNatural gas
Secondary fuelLandfill gas
Combined cycle?Yes
Power generation
Units operational385 MW (Swanbank E)
Make and modelAlstom GT26 (Swanbank E)
Nameplate capacity385 MW
External links
CommonsRelated media on Commons

The Swanbank Power Stations are located in Swanbank within South East Queensland, Australia. The original power station was coal fired, but the site has since moved to gas. By 2007 the site had consisted of the highly efficient 385 megawatts (516,000 hp) gas-fired Swanbank E Power Station and the smaller 28 megawatts (38,000 hp) gas-fired Swanbank C Power Station. Swanbank E was written off by the Queensland Audit Office as having no value, as it is uneconomical to run in 2021.[1]

Components

Swanbank A was commissioned in 1967 and decommissioned in August 2005.[2] It had six 66 megawatts (89,000 hp) steam turbines, and was powered by coal. The three 133-metre (436 ft) high, 7,000-tonne (6,900-long-ton; 7,700-short-ton) concrete smoke stacks were collapsed on 20 August 2006.[2] All three were collapsed on the same day with a 10 second delay between each stack. The deconstruction and demolition project, undertaken by Trio Industries, was scheduled to be completed in February 2007.

Swanbank B was commissioned in 1971 with four 120 megawatts (160,000 hp) steam turbines, powered by coal. Four units of Swanbank B were decommissioned in April 2010, June 2010, 2011, and May 2012, due to the plant reaching the end of its operational life.[2][3] The coal for Swanbank B came from coalfields in South-East Queensland, including New Acland Mine, by road. Water is supplied from Lake Moogerah and the Western Corridor Recycled Water Scheme began to supply the power station with water in August 2007.[4]

Swanbank C was a small gas turbine generating plant, rated at 28 megawatts (38,000 hp). It had two Rolls-Royce Avon gas generators discharging into a power turbine which drove the generator. Middle Ridge Power Station was a similar design, with four gas generators discharging into two power turbines, one on each end of the 56 megawatts (75,000 hp) electrical generator. It was commissioned in 1969,[5] and, in 2002, was expected to be decommissioned in December 2002.[6]

Swanbank D was a small open cycle gas turbine. Delivering only 37 megawatts (50,000 hp), it was installed in 1999[7] but was sold by CS Energy in 2003/2004[7] and was decommissioned by 2004.[8]

The much larger and more efficient Swanbank E was commissioned in 2002 with a single 385 megawatts (516,000 hp) combined cycle gas turbine.[9] The gas turbine of Swanbank E was the largest of its type at the time of its commissioning.[10] In 2011, Swanbank E set a world record for the continuous operation of an Alstom GT26 gas turbine.[10] It had been running for 254 days when it was shut down on 9 July 2011 for planned maintenance.

In 2021, its owner, CleanCo Queensland, wrote down the entire value of the power station to zero, and expects to receive net losses until its expected retirement in 2036.[11]

In February 2024, construction started for a 250 MW / 500 MWh grid battery at the B site,[12] and a further 500 MW / 1000 MWh battery is planned.[13]

Protest

On 11 July 2008, four activists from Greenpeace Australia Pacific occupied the top of a 140-metre high Swanbank B smokestack for 33 hours. They descended over two hours on the next day, leaving a message for Australia's leaders – "Go Solar"- painted on the side of the smoke stack.[14]

See also

References

  1. ^ Mazengarb, Michael (4 February 2021). "More than $1 billion wiped off value of Queensland coal and gas power stations". RenewEconomy. Retrieved 4 February 2021.
  2. ^ a b c "Ipswich Heritage Trails" (PDF). p. 15. Retrieved 2 November 2021.
  3. ^ "Stanwell Corporation – Final coal delivered to Swanbank B Power Station". Power Engineering. PennWell Corporation. 7 May 2012. Retrieved 22 May 2012.
  4. ^ "Bundamba plant begins to produce recycled water". WaterWorld. PennWell Corporation. 31 August 2007. Retrieved 4 July 2014.
  5. ^ "Electricity Industry Chronology". Chronology of Engineering works in Queensland. Engineers Australia. Retrieved 2 March 2014.
  6. ^ "annual planning report 2002" (PDF). Retrieved 1 November 2021.
  7. ^ a b "Annual Report 2003_2004". Retrieved 1 November 2021.
  8. ^ "Annual Planning Report 2004" (PDF). p. 98. Retrieved 1 November 2021.
  9. ^ "Swanbank E Power Station" (PDF). Fact Sheet. Stanwell. September 2013. Retrieved 28 April 2014.
  10. ^ a b "Swanbank E sets world record for continuous operation" (PDF). Media Release. Stanwell Corporation. 14 July 2011. Retrieved 7 September 2011.
  11. ^ "Queensland writes off Swanbank E gas-fired power plant | Argus Media". www.argusmedia.com. 8 February 2021. Retrieved 1 November 2021.
  12. ^ "Works begin on giant Queensland Tesla battery at site of former coal plant". RenewEconomy. 19 February 2024.
  13. ^ "Local council approves gigawatt-scale battery near old coal plant". RenewEconomy. 9 July 2024.
  14. ^ "Greenpeace protesters scale Swanbank smoke stacks". Australian Broadcasting Corporation.

YouTube videos of chimney demolition