Construction of the solar park began in October 2017.[1] The prime contractor for construction was RCR Tomlinson under an EPC arrangement. RCR went into administration in November 2018 just prior to facility completion and full production was delayed until February 2019. ENcome Energy Performance have been appointed as O&M contractor with RES Group as Asset Managers.
The project consists of 32 SMA supplied inverters, Solar modules were supplied by Canadian Solar mounted on Next Tracker solar tracking system. The project connects into the Ergon's 66 kV network.