Nuclear power in Romania provides around 20% of its electricity, with two nuclear reactors commencing operations in 1996 and 2007. In 2020, Romania generated a total of 56.1 TWh of electricity. The generation mix was composed of hydro (28%), nuclear (20%), natural gas (15%), coal (17%), wind (12%), solar (3%), and biofuels & waste (less than 1%). The Romanian government strongly supports nuclear energy.[1]
Currently the plant has two fully operational reactors and another three reactors that are partially finished.
Unit One took 16 years to build, completed in 1996. It produces 705.6 MW[3] of electricity.
Unit Two took 27 years to build, achieving initial criticality in 2007[4] and produces 706 MW of electricity.
Unit Three and Unit Four were expected to be operational by the year 2015 (thirty-five years after the start of construction) and the total electricity production of the units was to be around 1,500 MW. The total cost of the units is expected to be around US$6 billion.
On 7 March 2008, Nuclearelectrica, ArcelorMittal, CEZ, Electrabel, Enel, Iberdrola and RWE agreed to set up a company dedicated to the completion, commissioning and operation of Units 3 and 4. The company is expected to be registered in May 2008.[5]
Expansion of Cernavodă nuclear plant
In 2002 and 2006, Romania made efforts to complete unit 3 and 4, respectively. The cost estimate put completion of both reactors at EUR 2.5 billion, with seven companies investing into the project, including the state run Societatea Nationala Nuclearelectrica. The six other companies include ArcelorMittal, CEZ, Electrabel, ENEL, Iberdrola, and RWE. With investment from all these companies, unit 3 would be completed in 2014 and unit 4 in 2015. In March 2008, the Romanian government suggested that it might build another four-unit power plant by 2020.[6]
The company that operates and maintains the power plant is Nuclearelectrica.
20 January 2011, GDF Suez, Iberdrola and RWE pulled out of the project, following ČEZ which had already left in 2010, citing "Economic and market-related uncertainties surrounding this project, related for the most part to the present financial crisis, are not reconcilable now with the capital requirements of a new nuclear power project".[7]
In February 2020 the prime minister announced that the country would no longer partner with CGN for the project. In October 2020 it was announced that the USA would finance the construction of Cernavoda 3&4, as well as the refurbishment programme of unit 1. In March 2021 Nuclearelectrica said it expects to commission unit 3 by 2031, starting construction in about 2024.The largely-new reactors will be updated versions of the Candu 6, but not the full EC6 version, since the concrete structures are already built. Unit 3 was reported to be 52% completed and 30% for unit 4, though in 2017 the reported figures were 15% and 14%. They would have an operating lifetime of 30 years with the possibility of a 25-year extension. Some 1000 tonnes of heavy water has been produced and is in storage.[9]
The partner for Nuclearelectrica in the construction will be from the USA, NuScale Power, rather than China, with a consortium of USA, Canada and France undertaking the construction.[10]
Nuclear waste
In Romania, spent nuclear fuel is first kept at reactor sites for 6-10 years. It's then transferred to Cernavoda's Dry Storage Facility (DICA), using AECL's Macstor system, designed for 50 years of storage. The country is also constructing a repository at Saligny for low- and intermediate-level waste and operates a national repository for industrial low-level waste at Baita Bihor since 1985. Established under the Nuclear Act of 1996, the National Commission for Nuclear Activities Control (CNCAN) regulates Romania's nuclear safety and operations, ensuring compliance with International Atomic Energy Agency (IAEA) standards and overseeing licensing and safeguards.[1]
Energy production
Nuclear electricity production in Romania (TWh).[11]