The Act was the responsibility of the Ministry of Reconstruction, and came in response to the recommendations of the Burt Committee, which had been established in 1942.
The government aimed to provide enough homes for each family who required an individual dwelling, which it perceived had been the situation in 1939 prior to the outbreak of war. However, the Blitz had rendered some 450,000 homes either completely destroyed or uninhabitable. A secondary intention of the act was the completion of the pre-war slum clearance project.
The Act provided for a number of strategies to solve the housing crisis:
An increase in the labour force of the building industry to pre-war levels of over 1 million
The construction of at least 300,000 homes during the two-year period after the act, under the Emergency Factory Made programme
To prevent price inflation caused by high demand on building services