As per latest reports, the Yellow Line is slated to be operational between 2nd & 4th weeks of January 2025[1] due to lack of train sets which are needed for commencement of commercial operations.[2][3][4][5][6]
History
In December 2016, the Bangalore Metro Rail Corporation Limited (BMRCL) issued a call for bids to construct the Electronic City metro station along the 6.418 km Reach 5 – Package 1 section (Bommasandra - Hosa Road) of the 18.825 km Yellow Line of Namma Metro. On 25 March 2017, ITD-ITD Cementation JV was selected as the lowest bidder for this stretch, with their bid closely aligning with the original cost estimates.[7] Consequently, the contract was successfully awarded to the company, which then commenced construction of the metro station in accordance with the agreements.