The project was awarded by the National Hydroelectric Power Corporation in October 1989 to a European consortium called Uri Civil led by Swedish Skanska and including Swedish NCC and ABB and British Kvaerner Boving.[4] It was partially funded by the Swedish and British governments.[5]
The workforce included about 200 foreigners and 4,000 Indians, many from the local area.[2][6][7] This together with shelling across the border and unrest related to the burning of Charari Sharief and the siege of Hazratbal Shrine led to an 18-month delay.[1]
The project cost about Rs. 33 billion (about 450 million EUR or US$660 million) and was completed in 1997.[1]
Operation
The station is operated by the NHPC. Plans to expand it with a 250 MW Uri-II plant were announced in 1998. The government of Pakistan has objected to this, saying it violates the Indus Waters Treaty.[8][9] On 4 July 2014 a 240 MW Uri-II power project which is a new project located just downstream of Uri I, was inaugurated.[10]
^Sveriges Radio P3 Dokumentär: Kidnappningen i Kashmir by Fredrik Johnsson and Kristofer Hansson. First broadcast on 7 December 2008. Radio documentary with interviews.