Spit Bridge

The Spit Bridge
The Spit Bridge with its bascule deck opened
Coordinates33°48′09″S 151°14′46″E / 33.8025°S 151.2462°E / -33.8025; 151.2462
CarriesThe Spit Road
CrossesMiddle Harbour
LocaleThe Spit, Sydney, New South Wales, Australia
BeginsMosman (south)
EndsSeaforth (north)
OwnerTransport for NSW
Heritage statusRoads & Maritime Services
heritage and conservation register
Preceded byRoseville Bridge
Characteristics
DesignGirder bridge with a bascule lift span
MaterialSteel and concrete
Trough constructionComposite concrete
Total length745 feet 6 inches (227.23 m)
Width54 feet (16 m)
No. of spans7
No. of lanes4
History
DesignerNSW Department of Main Roads
Constructed byCleveland Bridge & Engineering Company
Construction start1952 (1952)
Construction end1958 (1958)
Construction cost1,110,000
Opened19 November 1958 (1958-11-19)
ReplacesThe Spit Bridge (1924–1958)
Statistics
Daily traffic~33,000 (2012)
Location
Map
References
[1][2][3]

The Spit Bridge, a steel and concrete girder bridge with a bascule lift span across the Middle Harbour, is located 10 kilometres (6.2 mi) north-east of the central business district in Sydney, Australia. The bridge carries The Spit Road (A8) from a point called The Spit, and connects the suburbs of Mosman, on the south bank and Seaforth, on the north bank.

History

Construction of the (first) Spit Bridge in 1924. The punt may be seen in bottom left foreground.

Sydney's Lower North Shore and Northern Beaches were serviced initially by a rowing boat from as early as 1829. A hand-operated punt service began in 1850 and continued until 1889, when it was replaced by a steam punt.[4]

The inhabitants of the Manly area first requested a bridge in the 1870s and the first plans for one were made in the following decade.[5] In 1912, Member of Parliament Richard Arthur lobbied the State Government to build a bridge, but was told that the planned construction of the Sydney Harbour Bridge made this unlikely.[6] World War I pushed the issue aside but more calls for a bridge were made in 1919.[6]

In 1922, the cost of a bridge was estimated at £150,000 by the Public Works Committee, a price that Manly Council said would cover a 205-metre-long concrete bridge, resting on 18 arches of varying lengths, with two sets of tram lines, two roadways and two footpaths.[6] Eventually, in late 1923, the Council decided to build a bridge itself on a cost of £40,000 to £60,000 with a low height design made from timber that was 213m long, with a roadway 5.5m wide and room for one covered footpath, but no tram lines.[6]

In 1924, The (first) Spit Bridge was completed and opened. By 1927 the timber low–level bridge saw a 60% growth over that of the punt for the year prior to the bridge opening. The amount of traffic using the bridge was higher than expected and the subsequent revenue from tolls providing a financial boon for the government.

Various plans were considered to reduce congestion including a high-level bridge and a bridge further upstream, leaving the existing bridge for local traffic; however none were enacted until after World War II. The NSW Government decided to build another low–level bridge at the same site.[1]

Description

The Spit Bridge from Ellery's Punt Reserve.

Construction of the current bridge by Cleveland Bridge & Engineering Company[7] had commenced in 1952 and after delays was completed in 1958; and opened on 19 November 1958.[1][8]

The Spit Bridge over Middle Harbour can be described as a steel and concrete girder bridge with a bascule lift span. The Spit Bridge comprises 7 spans of a total length of 745 feet 6 inches (227.23 m), has four traffic lanes with a width of 44 feet (13 m) and a pedestrian walkway of 5 feet (1.5 m) on either side. There are three spans at either end of the opening span. Each of the six fixed spans have four welded plate girders as the main members, with cross girders, but without stringers or horizontal bracing. The concrete deck is dowelled to the steelwork. The opening span (Span 4) is a single-leaf bascule. It has two main girders, with cross girders and stringers, covered by an open mesh steel deck.[1]

The two footways are of concrete on the fixed spans, and steel on the bascule span. The piers either side of the opening span are flanked by fenders, and when the bridge is in the open position a navigation channel of 80 feet (24 m) wide is created. At the Mosman end the slab and two column piers rest on concrete piles driven into the sands of the harbour bed at a depth of between 40 and 50 feet (12 and 15 m). At the Manly end the harbour bottom slopes up steeply to outcropping rock on which the northern abutment sits. Piers 5 and 6 are double cylinder piers sitting on bedrock below the harbour bed. The main pier which supports the bascule span is Pier 4. It rests on four cylinders taken down to sandstone bedrock at a depth of between 45 and 75 feet (14 and 23 m) which is 75 and 105 feet (23 and 32 m) below mean sea level. The pier is box-like and supports all machinery for the operation of the bascule, including the operator's cabin. The approaches and abutments at each end are varied due to the nature of the topography. The southern abutment is built up from the sandy beach level and has a retaining wall faced with stone on either side. The northern abutment is resting directly on the rock on the western side and is built up on the eastern side with a retaining wall. Due to the variation in ground level on each shore there is a grade of 2.68% from south to north. Traffic across the bridge is regulated by traffic lights at either end (located at the end of Spans 2 and 6) and by roadway gates which operate as the bridge is about to open.[1]

The bridge has two traffic lanes in each direction, with a tidal flow system established, while the approaches to it have three lanes in each direction. In 2007, the Roads & Traffic Authority found that traffic either side of the bridge doesn't return to normal for 15 minutes after the bridge is opened[9] and reduced the number of bridge opening times.

Grade-separated shared pedestrian footpaths and cycleways are located on the bridge's western (upriver) and eastern (downriver) sides.

Heritage listing

The Spit Bridge was listed on the Roads & Traffic Authority heritage and conservation register on 24 November 2003:[1]

Congestion and bypassing project

The Spit Bridge forms part of the route from the Sydney central business district and Lower North Shore suburbs to Manly and the Northern Beaches. The next crossing of Middle Harbour is some distance upstream (north-west) at Roseville Bridge. The Roads & Traffic Authority announced in August 2006 that tenders had been called for widening of the bridge to six lanes, with two extra traffic lanes and a pedestrian/cycleway being added on the western side, and upgrades to the lifting mechanism. Construction was to have begun in 2007,[10] however, the project was scrapped in May of that year. According to the government this was due to technical and engineering difficulties, according to the opposition it was because of political considerations. The increased cost estimates to $115 million were deemed to be not justifiable by the Minister for Roads Eric Roozendaal and the five–year plan was abandoned.[11]

Traffic delays either side of The Spit Bridge have been a problem for many years, not only on the approaches to the bridge itself, but also far up the hills on either side. Proposals to ameliorate delays have included widening the bridge, a tunnel linking the Warringah Expressway and the Burnt Bridge Creek Deviation, and a high-level bridge in place of the existing one. David Barr, the member for Manly, claimed in 2002 that the latter two were too expensive with $200 million estimated for a high-level bridge, and $1 billion for the tunnel.[12] In 2009 it was reported that the Labor Government was reviewing a proposal for a tunnel from Cammeray to The Spit, linked to a new, higher bridge that would be able to let boats through without the need to be opened.[13]

In 2014, Premier Mike Baird, also the member for Manly, announced plans to bypass Mosman and The Spit Bridge by constructing a $2–3 billion tunnel from Seaforth to Neutral Bay that would run underground beneath Military Road.[14] In 2017, NSW Premier Gladys Berejiklian announced that the NSW Government will provide $77 million towards the construction of a tunnel to bypass The Spit Bridge as part of the Beaches Link project. The tunnel, which is expected to take five years to build, will connect the Warringah Freeway from Cammeray and cross underneath Middle Harbour to meet up with the Burnt Bridge Creek deviation at Balgowlah. The proposed tunnel will be located west of The Spit Bridge.[15][16] However, in June 2022, the NSW Government announced that the Beaches Link section of the project would be shelved indefinitely, due to market constraints and labour shortages.[17]

See also

References

  1. ^ a b c d e f "Spit Bridge, The". Heritage and conservation register, Roads & Traffic Authority. Government of New South Wales. 24 November 2003. Retrieved 26 October 2006.
  2. ^ "Average Daily Traffic Volumes" (PDF). Roads & Maritime Services (PDF). Government of New South Wales. 2012. p. 18. Retrieved 16 January 2015.
  3. ^ "The Spite: Historical Overview" (PDF). Local Studies Service: Mosman Library. Mosman Council. n.d. Retrieved 17 April 2020.
  4. ^ "Bridging the Spit". Heritage Plaques in Manly. Manly Council. 2002. Retrieved 17 April 2020.
  5. ^ "Spit Bridge | The Dictionary of Sydney". dictionaryofsydney.org. Retrieved 9 October 2021.
  6. ^ a b c d Morcombe, John (21 March 2014). "90 years of bridging The Spit". Daily Telegraph. Retrieved 9 October 2021.
  7. ^ "Model of Spit Bridge in Sydney". Museum of Applied Arts & Sciences. Retrieved 18 September 2021.
  8. ^ New Bridge at The Spit. Middle Harbour, Sydney Main Roads March 1959 pages 80/81
  9. ^ "Spit spat leaves yachties fearing harbour crush". Sydney Morning Herald. 21 January 2007.
  10. ^ "Spit Bridge widening". Roads & Traffic Authority. Government of New South Wales. Retrieved 26 October 2006.
  11. ^ "Working group to mull Spit Bridge ideas". Sydney Morning Herald. 1 May 2007.
  12. ^ Barr, David; Stewart, Tony (4 September 2002). "Spit Bridge Widening". Hansard, Legislative Assembly of New South Wales. Parliament of New South Wales. Retrieved 16 January 2015.
  13. ^ Robins, Brian (26 January 2009). "$1b plan for tunnel and new Spit Bridge". St George & Sutherland Shire Leader. Australia. Retrieved 17 April 2020.
  14. ^ Westbrook, Tom (26 November 2014). "Beaches Link tunnel to bypass Mosman and cut cross-Sydney travel time". Manly Daily. Retrieved 16 January 2015.
  15. ^ Spicer, David (16 March 2017). "Spit Bridge Tunnel: $77m earmarked ahead of key by-elections". ABC News. Australia. Retrieved 17 April 2020.
  16. ^ O'Keefe, Chris (15 February 2017). Moves to finally fix Sydney's Spit Bridge once and for all (streaming video). Nine News. Sydney. Retrieved 17 April 2020.
  17. ^ "NSW government puts Beaches Link and Blue Mountains tunnel on ice". ABC News Australia. 1 June 2022. Retrieved 6 February 2023.