A raised floor (also raised flooring, access floor(ing), or raised-access computer floor) provides an elevated structural floor above a solid substrate (often a concrete slab) to create a hidden void for the passage of mechanical and electrical services. Raised floors are widely used in modern office buildings, and in specialized areas such as command centers, Information technology data centers and computer rooms, where there is a requirement to route mechanical services and cables, wiring, and electrical supply.[1] Such flooring can be installed at varying heights from 2 inches (51 mm) to heights above 4 feet (1.2 m) to suit services that may be accommodated beneath. Additional structural support and lighting are often provided when a floor is raised enough for a person to crawl or even walk beneath.

In the U.S., underfloor air distribution is becoming a more common way to cool a building by using the void below the raised floor as a plenum chamber to distribute conditioned air, which has been done in Europe since the 1970s.[2] In data centers, isolated air-conditioning zones are often associated with raised floors. Perforated tiles are traditionally placed beneath computer systems to direct conditioned air directly to them. In turn, the computing equipment is often designed to draw cooling air from below and exhaust into the room. An air conditioning unit then draws air from the room, cools it, and forces it beneath the raised floor, completing the cycle.

Above describes what has historically been perceived as raised floor and still serves the purpose for which it was originally designed. Decades later, an alternative approach to raised floor evolved to manage underfloor cable distribution for a wider range of applications where underfloor air distribution is not utilized. In 2009 a separate category of raised floor was established by Construction Specifications Institute (CSI) and Construction Specifications Canada (CSC) to separate the similar, but very different, approaches to raised flooring. In this case the term raised floor includes low-profile fixed-height access flooring.[3] Offices, classrooms, conference rooms, retail spaces, museums, studios, and more, have the primary need to quickly and easily accommodate changes of technology and floor plan configurations. Underfloor air distribution is not included in this approach since a plenum chamber is not created. The low-profile fixed-height distinction reflects the system's height ranges from as low as 1.6 to 2.75 inches (41 to 70 mm); and the floor panels are manufactured with integral support (not traditional pedestals and panels). Cabling channels are directly accessible under light-weight cover plates.

Design

The traditional type of floor consists of a gridded metal framework or substructure of adjustable-height supports (called "pedestals") that provide support for removable (liftable) floor panels, which are usually 2 by 2 feet (0.61 m × 0.61 m). The height of the legs/pedestals is dictated by the volume of cables and other services provided beneath, but typically arranged for a clearance of at least 6 inches (150 mm) with typical heights between 24 and 48 inches (610 and 1,220 mm).[citation needed]

The panels are normally made of steel-clad particleboard or a steel panel with a cementitious internal core, although some tiles have hollow cores. Panels may be covered with a variety of flooring finishes to suit the application, such as carpet tiles, high-pressure laminates, marble, stone, and antistatic finishes for use in computer rooms and laboratories. When using a panel with a cement top surface the panels are sometimes left bare and sealed or stained and sealed to create a tile appearance and save the customer money. This bare application is used most often in office area, hallways, lobbies, museums, casinos, etc.

Adaptive cable management

A contemporary low-profile fixed height type of cable management access floor differs from traditional access floor by requiring much less ramping floor space at floor height transitions, and can even be eliminated in new construction with slab depressions. The primary advantages are realized by much lighter weight panels for easier handling. No tools are required to make changes, and organized cable channel pathways are integral to the system. Time and expense is greatly reduced during installation and every time changes are made in the future during the life of the building. Since this type of access floor is not attached to the structure it is considered to be furnishings, fixtures, and equipment (FF&E) that can be a depreciated expense or leased. Since the underfloor cabling is not in a plenum, the expense of plenum rated cable is not required.

Computer centers

Many modern computer and equipment rooms employ an underfloor air distribution to ensure even cooling of the room with minimal wasted energy. Conditioned air is provided under the floor and dispersed upward into the room through regularly spaced diffuser tiles, blowers or through ducts directed into specific equipment. Automatic fire protection shutoffs may be required for underfloor ventilation, and additional suppression systems may be installed in case of underfloor fires.

Server cabinet aisle on raised floor with cooling panels

Office buildings

Many office buildings use access flooring to create more flexible and sustainable spaces. A large corporation can have over 20,000 miles (32,000 km) of cabling in a single facility.[4]

When underfloor air is designed into a building from the start of the project, the building can be less expensive to build and less expensive to operate over the life of the building. Underfloor air requires less space per floor, thereby reducing the overall height of the building, which in turn reduces the cost of the building facade. The blowers and air handlers required for underfloor air are much smaller and require less energy, since hot air rises naturally through the space as it comes in contact with people and equipment that warm the air and it rises to the ceiling. Additionally, when buildings are designed to combine modular electrical, modular walls, and access floor, the space within the building can be reconfigured in a few hours, as compared to historical means of demolishing walls and drilling holes in the floor to route electrical and other services. As more companies construct or renovate buildings to meet Leadership in Energy & Environmental Design (LEED) underfloor air and access floor usage will continue to grow. The U.S. Green Building Council (USGBC) states that 40–48 percent of new nonresidential construction is green.[5]

Common Applications: Raised access flooring is commonplace in office accommodation, retail spaces, computer and control rooms. There are two bench-marks for performance testing in the United Kingdom, These being the PSA MOB PF2 PS (spu) 1992 and the more recent, slightly less stringent BS/EN12825. These set out defined static loading criteria for the raised access floor to meet. The maximum for raised access flooring for general office accommodation (PSA medium grade) is 8 kilonewtons per square metre (kN/m2) uniformly distributed load (UDL) and a 3.0 kN point load. There is an additional 3 x safety factor applied to the loadings. Computer and control rooms including data centers generally have a higher requirement with regards to static loadings and PSA heavy grade should be employed. This provides 12 kN/m2 UDL and a 4.5 kN point load, again with a 3 x safety factor applied.

Residential use

While major wiring may not be the focus, residential use of raised floors and split levels in 12-foot-ceiling (3.7 m) Manhattan apartments provides "high-performance elements" and added functionality.[6]

Panel lifter

One-cup suction lifter

To remove panels, a tool with a suction cup on the end (referred to as a "floor puller", "tile lifter", or "suction lifter") is used. A hook-and-loop lifter may be used on carpeted panels. Low-profile fixed height access flooring is held in place by gravity without glue or fasteners and does not require any tools to make changes.

Structural problems

Beneath a raised floor

Structural problems, such as rocking panels and gaps between panels, can cause significant damage to equipment and injury to personnel. Regular inspections for the structural integrity of a raised floor system can help to identify and mitigate problems.

Equipment and floor damage can happen when using flooring that does not meet load demands. Load ratings range from 1,000 to 25,000 pounds (0.45–11.34 t). Higher panels can be used on heavier areas of a floor whereas lower panels can be used on lighter areas.

Many such problems can be attributed to sub-par installation. During installation, attention should be paid to the condition of the subfloor, which should be clean of debris and should be as level as possible. The walls surrounding the raised floor should be as square as possible to minimize the need for cutting raised floor panels and to minimize rocking panels and gaps.[citation needed]

Low-profile, fixed-height systems accommodate irregularly shaped rooms with adjustable border components that minimizes cutting of panels.

Other problems

Because the flooring tiles are rarely removed once equipment has been installed, the space below them is seldom cleaned, and fluff and other debris settles, making working on cabling underneath the flooring a dirty job. Smoke detectors under the raised floor can be triggered by workers disturbing the dust, resulting in false alarms.

Cooling load implications

Perforated cooling floor tile

The installation of a raised floor system can change the thermal behavior of the building by reducing the interaction between the heat gains and the thermally massive concrete slab.[7] The raised floor serves as a separation between the room and the slab. Energy simulations of an office building located in San Francisco showed that the mere presence of the raised floor affects the zone cooling load profile and tends to increase the peak cooling load. When carpeting is present the negative impact of the raised floor on zone peak cooling load may be reduced.[7]

Telecommunications data center applications

Raised floors available for general purpose use typically do not address the special requirements needed for telecommunications applications.[8]

The general types of raised floors in telecommunications data centers include: stringerless, stringered, and structural platforms; and, truss assemblies.

  • Stringerless raised floors: an array of pedestals that provide the necessary height for routing cables and also serve to support each corner of the floor panels.
  • Stringered raised floors: a vertical array of steel pedestal assemblies (steel base plate, tubular upright, and a head) uniformly spaced on 2-foot (0.61 m) centers and mechanically fastened to the concrete floor.
  • Structural platforms: members constructed of steel angles or channels that are welded or bolted together to form an integrated platform for supporting equipment.
  • Truss assemblies: utilizing attachment points to the subfloor to support a truss network on which the floor panels rest. The truss has high lateral strength and transfers lateral loads to the subfloor with less strain than possible with a vertical pedestal assembly.

A telecommunications facility may contain continuous lineups of equipment cabinets. The most densely populated installation configuration would consist of rows of continuous 2-foot-wide equipment cabinets with aisles that separate 2-foot-wide adjacent rows. This lineup configuration is considered to be the most densely populated in terms of square foot area and, therefore, the largest floor load anticipated for a raised floor system. Considering prorated aisle space, a single equipment cabinet will then occupy an 8-square-foot (0.74 m2) floor area (4 sq ft or 0.37 m2 for the cabinet and 4 sq ft of aisle).

The data center can be located in remote locations, and is subject to physical and electrical stresses from sources such as fires and from electrical faults.

The environment drives the installation methods for raised floors, including site preparation, cable and cable racking, bonding and grounding, and fire resistance. The actual installation should be in accordance with the customer's practices.[9][10]

Information technology data centers and computer rooms

Raised floors for Data centers, and in particular rooms, have a history and a set of specifications.

Telcordia GR-2930

Telcordia NEBS: Raised Floor Generic Requirements for Network and Data Centers,[11] GR-2930 presents generic engineering requirements for raised floors that fall within the strict NEBS guidelines.

There are many types of commercially available floors that offer a wide range of structural strength and loading capabilities, depending on component construction and the materials used. The general types of raised floors include stringer, stringerless, and structural platforms, all of which are discussed in detail in GR-2930.

This design permits equipment to be fastened directly to the platform without the need for toggle bars or supplemental bracing.[1] Structural platforms may or may not contain panels or stringers; they are not recommend in earthquake-prone locations.[1]

Data centers typically have raised flooring made up of 60 cm (2 ft) removable square tiles. The trend is towards 80–100 cm (31–39 in) void to cater for better and uniform air distribution. These provide a plenum for air to circulate below the floor, as part of the air conditioning system, as well as providing space for power cabling.

Metal whiskers

Raised floors and other metal structures such as cable trays and ventilation ducts have caused many problems with zinc whiskers in the past, and likely are still present in many data centers. This happens when microscopic metallic filaments form on metals such as zinc or tin that protect many metal structures and electronic components from corrosion. Maintenance on a raised floor or installing of cable etc. can dislodge the whiskers, which enter the airflow and may short circuit server components or power supplies, sometimes through a high current metal vapor plasma arc.[12]

This phenomenon is not unique to data centers, and has also caused catastrophic failures of satellites and military hardware.[13]

See also

References

  1. ^ a b c A. K. Tang; A. J. Schiff. "Selection and Installation of raised floors" (PDF).
  2. ^ Spinazzola, Steven (2005). "HVAC: The Challenge And Benefits of Under Floor Air Distribution Systems". Facilities Net.
  3. ^ MasterSpec (2009). "CSI MasterFormat Category 09.69.33 Low Profile Fixed Height Access Floor". FreeAxez.
  4. ^ Mark McCain (July 24, 1988). "COMMERCIAL PROPERTY: The New Priorities; Wiring and Power Now Dominate Office Concerns". The New York Times.
  5. ^ "Green Building Facts". USGBC. Retrieved 7 December 2015. This year it is estimated that 40-48 percent of new nonresidential construction will be green, equating to a $120-145 billion opportunity.
  6. ^ Joseph Giovannini (April 5, 1984). "Two Manhattan apartments turn architecture outside in". The New York Times.
  7. ^ a b Schiavon S, Lee KH, Bauman F, Webster T (2010). "Influence of raised floor on zone design cooling load in commercial buildings". Energy and Buildings. 42 (5): 1182–1191. doi:10.1016/j.enbuild.2010.02.009. S2CID 110507582.
  8. ^ "GR-2930, NEBS: Raised Floor Generic Requirements for Network and Data Centers" (2). July 2012. {{cite journal}}: Cite journal requires |journal= (help)
  9. ^ GR-1275-CORE, Central Office/Network Environment Equipment Installation/Removal Generic Requirements
  10. ^ GR-3160-CORE, NEBS Requirements for Telecommunications Data Center Equipment and Spaces
  11. ^ "GR-2930 - NEBS: Raised Floor Requirements - Telcordia". telecom-info.telcordia.com.
  12. ^ "Zinc Whiskers on Raised Floor Tile Structures". Retrieved February 5, 2019.
  13. ^ "NASA - metal whiskers research". NASA. Retrieved 2011-08-01.

Read other articles:

Scandinavian Airlines (SAS) IATA ICAO Kode panggil SK SAS SCANDINAVIAN Didirikan1 Agustus 1946PenghubungBandara KopenhagenBandara Arlanda StockholmBandara Gardermoen OsloProgram penumpang setiaEuroBonusLounge bandaraScandinavian Lounge & Business LoungeAliansiSkyTeamAnak perusahaan SAS Connect SAS Cargo Group SAS Ground Handling SAS Technical Services Armada132Tujuan168SloganService and simplicityPerusahaan indukSAS GroupKantor pusatSolna, Stockholm, SwediaTokoh utamaCarsten Dilling (Ketu...

 

Birmingham CityNama lengkapBirmingham City Football ClubJulukanBlues[1][2]Berdiri1875; 148 tahun lalu (1875) as Small Heath AllianceStadionSt Andrew's(Kapasitas: 29,409 (restricted to c. 21,000 pending completion of repairs)[3][4])PemilikBirmingham Sports Holdings 51.00%Shelby Companies Ltd 45.64%[5][6]KetuaTom Wagner [7]Wayne RooneySitus webSitus web resmi klub Kostum kandang Kostum tandang Musim ini Birmingham City Foot...

 

Benjamin Franklin BiografiKelahiran17 Januari 1706 Boston Kematian17 April 1790 (84 tahun)Philadelphia Penyebab kematianPleuritis Tempat pemakamanChrist Church, Philadelphia (en) Galat: Kedua parameter tahun harus terisi! President of the Supreme Executive Council of Pennsylvania (en) 18 Oktober 1785 – 5 November 1788 ← Farmer in Pennsylvania, – Thomas Mifflin → United States Ambassador to Sweden (en) 28 September 1782 – 3 April 1783 ← tanpa ni...

Danish professor and politician (1845–1918) Johan Henrik DeuntzerCouncil President of DenmarkIn office24 July 1901 – 14 January 1905MonarchChristian IXPreceded byHannibal SehestedSucceeded byJ. C. Christensen Personal detailsBorn(1845-05-20)20 May 1845CopenhagenDied16 November 1918(1918-11-16) (aged 73)CharlottenlundPolitical partyVenstre, Danish Social Liberal PartyAlma materUniversity of Copenhagen Johan Henrik Deuntzer (20 May 1845 – 16 November 1918) was a Danish p...

 

Cet article est une ébauche concernant un sculpteur américain. Vous pouvez partager vos connaissances en l’améliorant (comment ?) selon les recommandations des projets correspondants. Pour les articles homonymes, voir Fraser. James Earle FraserBiographieNaissance 4 novembre 1876WinonaDécès 11 octobre 1953 (à 76 ans)WestportSépulture Willowbrook Cemetery (en)Nationalité américaineFormation École de l'Institut d'art de ChicagoAcadémie JulianActivités Sculpteur, médaill...

 

For other uses, see Don't Give Up the Ship (disambiguation). 1959 American filmDon't Give Up the ShipTheatrical release posterDirected byNorman TaurogScreenplay byHerbert BakerEdmund BeloinHenry GarsonStory byEllis KadisonProduced byHal B. WallisStarringJerry LewisDina MerrillDiana SpencerClaude AkinsRobert MiddletonGale GordonMickey ShaughnessyCinematographyHaskell BoggsEdited byWarren LowMusic byWalter ScharfDistributed byParamount PicturesRelease date June 16, 1959 (1959-06-...

Ираклеониты — ученики гностика Ираклеона (II век). Упоминаются как особая секта Епифанием и Августином; при крещении и миропомазании они соблюдали обряд помазания елеем и при этом произносили воззвания на арамейском языке, которые должны были освободить душу от власт�...

 

Norwegian dialects of western Norway This article has multiple issues. Please help improve it or discuss these issues on the talk page. (Learn how and when to remove these template messages) This article may require cleanup to meet Wikipedia's quality standards. No cleanup reason has been specified. Please help improve this article if you can. (November 2011) (Learn how and when to remove this message) This article needs additional citations for verification. Please help improve this article ...

 

Artikel ini sebatang kara, artinya tidak ada artikel lain yang memiliki pranala balik ke halaman ini.Bantulah menambah pranala ke artikel ini dari artikel yang berhubungan atau coba peralatan pencari pranala.Tag ini diberikan pada Maret 2016. SD Negeri Kleco IInformasiJenisSekolah NegeriKepala SekolahGitono, S.Pd.Rentang kelasI - VIAlamatLokasiJl. Brigjen Slamet Riyadi No 554, Kota Surakarta, Jawa Tengah,  IndonesiaMoto SD Negeri Kleco I, merupakan salah satu Sekolah Dasar negeri ya...

Glassmaking company of Venice, Italy Barovier & TosoBarovier, Murano, Venice (right). Photo by Paolo Monti, 1968.Company typePrivateIndustryManufacturingFoundedItalyHeadquartersMurano, ItalyWebsitebarovier.com Barovier & Toso is an Italian company that specializes in Venetian glass.[1] History The company is one of the oldest family businesses in the world, founded in 1295 as Barovier.[2]The name Barovier derives from the term berroviere (highwayman/policeman[3]...

 

Australian filmmaker Rachel PerkinsPerkins at the 2012 AACTA Awards in SydneyBorn1970 (age 53–54)Canberra, Australian Capital Territory, AustraliaOccupation(s)Producer, director, writerYears active1998–presentSpouseRichard McGrath (divorced)Children1ParentCharles Perkins (father)RelativesHetty Perkins (grandmother)Hetti Perkins (sister)Madeleine Madden (niece) Rachel Perkins (born 1970[citation needed]) is an Australian film and television director, producer, and scr...

 

Part of a series onAnarchism History Outline Schools of thought Feminist Green Primitivist Social ecology Total liberation Individualist Egoist Free-market Naturist Philosophical Mutualism Postcolonial African Black Queer Religious Christian Jewish Social Collectivist Parecon Communist Magonism Without adjectives Methodology Agorism Illegalism Insurrectionary Communization Expropriative Pacifist Platformism Especifismo Relationship Syndicalist Synthesis Theory Practice Anarchy Anarchist Blac...

  「亳州」重定向至此。关于中国古代历史上的一个行政区划,请见「亳州 (古代)」。 亳州市亳地级市亳州火车站广场的曹操雕塑亳州市在安徽省的地理位置坐标:33°50′42″N 115°46′41″E / 33.845°N 115.778°E / 33.845; 115.778国家 中华人民共和国省安徽省設立2000年5月21日政府駐地谯城区下级行政区1市辖区、3县政府 • 市委書記杜延安 •...

 

Franziska GiffeyFranziska Giffey, 2018 Menteri Urusan Keluarga, Warga Senior, Wanita dan PemudaPetahanaMulai menjabat 14 Maret 2018KanselirAngela MerkelPendahuluKatarina BarleyPenggantiPetahanaWalikota NeuköllnMasa jabatan15 April 2015 – 14 Maret 2018PendahuluHeinz BuschkowskyPenggantiMartin Hikel Informasi pribadiLahirFranziska Süllke3 Mei 1978 (umur 46)Frankfurt (Oder), Jerman Timur(sekarang Jerman)KebangsaanJermanPartai politikPartai Sosial DemokratAlma materUniversit...

 

Politics of Canada Government (structure) The Crown Monarch (list): Charles III Governor General (list): Mary Simon Monarchy in the provinces Lieutenant governors Royal prerogative Executive King’s Privy Council Prime minister (List of prime ministers): Justin Trudeau Cabinet (List of Canadian ministries): 29th Canadian Ministry President of the Privy Council Clerk of the Privy Council Privy Council Office Public Service Provincial and territorial executive councils Premiers Legislative Fe...

Lucien-Victor Guirand de ScévolaGuirand de ScévolaLahir(1871-11-14)14 November 1871Sète, PrancisMeninggal29 Maret 1950(1950-03-29) (umur 78)Paris, PrancisKebangsaanPrancisPendidikanÉcole des Beaux-ArtsDikenal atasLukisan pastelGerakan politikSymbolismElectedLégion d'honneur Lucien-Victor Guirand de Scévola (14 November 1871 – 29 Maret 1950) adalah seorang pelukis asal Prancis. Ia dikenal karena kepemimpinan perintisnya Camoufleurs (Departemen Kamuflase Prancis) dal...

 

Opioid antagonist Methocinnamox Names IUPAC name (E)-N-[(4R,4aS,7aR,12bR)-3-(Cyclopropylmethyl)-9-hydroxy-7-oxo-2,4,5,6,7a,13-hexahydro-1H-4,12-methanobenzofuro[3,2-e]isoquinolin-4a-yl]-3-(4-methylphenyl)prop-2-enamide Identifiers CAS Number 117339-76-1 N 3D model (JSmol) Interactive image ChEMBL ChEMBL610884 ChemSpider 24673142 PubChem CID 46877713 InChI InChI=1S/C30H32N2O4/c1-18-2-4-19(5-3-18)8-11-25(35)31-30-13-12-23(34)28-29(30)14-15-32(17-20-6-7-20)24(30)16-21-9-10-22(33)27(36-28)26...

 

Mexican linguist Yolanda LastraLastra receiving a Science and Art National Prize in 2015Born1932 (age 91–92)NationalityMexicanAlma materCornell UniversityOccupationLinguistSpouseJorge A. Suárez Yolanda Lastra de Suárez (born 1932) is a Mexican linguist specializing in the descriptive linguistics of the indigenous languages of Mexico. She obtained her PhD degree in 1963 from Cornell University, her dissertation written under the guidance of Charles F. Hockett treating the syn...

La chaine numérique actuelle simplifiée Le STEP-NC (STEP compliant Numerical Control) est un standard d’échange de données pour la programmation de commande numérique. Il est basé sur le standard STEP (STandard for the Exchange of Product model data, Standard pour l'échange de données de produit) et permet d'intégrer complètement la chaîne numérique CAO-CFAO-CN. Il regroupe à la fois les propriétés du STEP (intégration des processus de conception, de développement, de fabri...

 

Place in Lower Carniola, SloveniaDobovecDobovecLocation in SloveniaCoordinates: 46°6′38.99″N 15°3′31.9″E / 46.1108306°N 15.058861°E / 46.1108306; 15.058861Country SloveniaTraditional regionLower CarniolaStatistical regionCentral SavaMunicipalityTrbovljeArea • Total5.75 km2 (2.22 sq mi)Elevation697.1 m (2,287.1 ft)Population (2002) • Total188[1] Dobovec (pronounced [dɔˈbɔːʋəts] or &#...