Piran Dam is a stone and concrete hydroelectric dam on the Piran stream located about 6.2 km (3.9 mi) east of Piran in Sarpol-e Zahab County, Kermanshah Province, Iran. The project started in 1989 with the preliminary studies. All studies were carried out by 2000. The main contractor was selected in 2007.[1] Construction of the dam started in 2008 and the dam was inaugurated on 24 November 2011.[2] It cost more than US$15 million.[2]
The dam is 7.5 metres (25 ft) high and 25 metres (82 ft) long. It creates a reservoir with capacity of 15,000 cubic metres (12 acre⋅ft) and surface of 10,000 square metres (110,000 sq ft). The projects includes a 212 metres (696 ft) transfer channel, 1,572 metres (5,157 ft) of siphon pipes, and 800 metres (2,600 ft) outlet channel.[3]
The power plant has installed capacity of 8.4 MW. It has two Pelton turbines manufactured by Ghet Hydro Energy and two generators manufactured by WEG.[3]