Construction started in Autumn 2011, followed by a series of missteps delaying the completion of the project. In October 2012, after a year of work on the site, an investigation was started on the assignment of the call for tenders for construction.[4] At the end of March 2016, a new investigation was launched, delaying the final stages of construction. The windows installed on the building were faulty, and roughly 300 of the 3,600 already-installed windows needed to be replaced.[5]
Work did not resume until the summer of 2017.[6][7]
After years of delays, the headquarters was inaugurated on October 14, 2022, with regional president Alberto Cirio and his staff being the first to move in.[8] Other employees were transferred to the building gradually over the spring of 2023.