The stadium was the westernmost location of the 2018 World Cup.[2] In April 2012, the regional government chose the French architectural bureau Wilmotte & Associes, SA stadium construction project. NPO Mostovik & Mersfor Rus OOO were project partners and the Kaliningrad Region and Russian Federation were the project managers.[5] The project itself is worth $280 million.[6]
In June 2014 the Omsk Arbitration Court declared "Mostovik" bankrupt and, in March 2015, termination of the contract with the company began. On 1 April 2014 a government order published by the government declared the appointment of ZAO "Crocus International" as the sole executor of the Ministry of Sports of the Russian Federation for the works on the construction.[7] The state contract was signed between the Government of the Kaliningrad Oblast and Crocus International "to develop the project and working documentation on the design of the stadium".[8]
On 10 June 2015 it was reported that the stadium project was sent to the state examination. On 20 July, the layout of the stadium was presented.[9]
At first, regional authorities considered the option with the construction of new sports facilities in the city center, on the place of the current Baltika Stadium. Finally, in December 2014 it was announced that Oktyabrsky Island will be the location of the new stadium, even though it is often under threat of flooding. and work on it requires additional financial investments.[10]
On 10 August 2015, it became known that the stadium would be named "Stadium Kaliningrad" or in the English version, Kaliningrad Stadium.[11]
Construction
The project was based on the concept of the Allianz Arena Munich, which hosted matches of the 2006 World Cup in Germany. The project cost was anticipated as 11 billion rubles but was exceeded by far. Soil compaction work was completed in December 2014. Preparation work for construction of the infrastructure started in January 2015. In addition, a new bridge was built over the river to provide better connections to the surrounding area.[5] Testing for the stadium piles and foundation began in July 2014. As a multiple-purpose arena, Kaliningrad Stadium can be used for football matches and other sporting events, conferences and concerts.[2][5]
Safety and security
This is a two-tier stadium with a VIP section, equipped with ultramodern security systems and CCTV.[12][13] The stadium is equipped with more than 700 security cameras.[13]
Work on consolidation and drainage of Oktyabrsky Island
During excavation, some pre-war buildings' infrastructure was found which was not marked on the topographic survey. These issues have been dealt with. The project includes construction of the overpass East from Oktyabrsky island and from the street.[14]
The seating capacity of 35,000 seats was to be reduced to 25,000 before the stadium was handed over to the football club Baltika, which had 4,000 spectators to matches in 2017.[6] In March 2019 the federal government allocated 40 million rubles to renovate the stadium.[20]