Greater Winnipeg Water District Aqueduct

Greater Winnipeg Water District Aqueduct
Coordinates49°37′21″N 95°11′44″W / 49.62250°N 95.19556°W / 49.62250; -95.19556 (GWWD Aqueduct)
LocaleShoal Lake 40 First Nation
BeginsShoal Lake, Ontario
EndsDeacon Reservoir, Winnipeg, Manitoba
OwnerCity of Winnipeg
Characteristics
Total length154 km (96 mi)
Capacity85 million imp gal (390 million L)
History
Engineering design byHering, Fuertes and Stearns
Built1913-1919
Opened1919
Location
Map

The Greater Winnipeg Water District Aqueduct (GWWDA) is an aqueduct that supplies the city of Winnipeg, Manitoba, with water from Shoal Lake, Kenora District, Ontario. Winnipeg has relied on the lake as its source for safe drinking water since the aqueduct was put in service in 1919 at a cost of nearly CDN $16 million.[1][2]

It has a capacity of 85 million imp gal (390 million L) per day (4.4 cubic metres per second), a capacity that was planned for a city of one million inhabitants; peak water usage by the city was in 1988 and the capacity of the aqueduct has never been entirely used.

The aqueduct extends approximately 154 kilometres (96 mi) from an intake structure on Shoal Lake to the Deacon Reservoir on the east side of the Winnipeg floodway, a few kilometres south of Highway 15.[3] Water flows by gravity from the lake, since the aqueduct drops about 91 metres (300 ft) over its length.[4]

Access by maintenance staff to the aqueduct has been provided by the Greater Winnipeg Water District Railway, also operated by the City, since 1916. The Railway formerly provided passenger and freight rail services to the public, from Winnipeg to the rail station at the Shoal Lake aqueduct intake.[1]

Overflow tank for Winnipeg aqueduct prevents pressure rise if water demand is low. Tache Ave. Winnipeg near 49°53′52.04″N 97°07′43.10″W / 49.8977889°N 97.1286389°W / 49.8977889; -97.1286389

History

Background

The first water supply system in Winnipeg was installed and operated by the private Winnipeg Water Works Company, which obtained its charter on 30 December 1880. The charter was for a 20-year period and the works were put into operation in 1882. The source of supply was the Assiniboine River, the intake and pumping station being located at Armstrong's Point on the north bank of the river immediately downstream from the Maryland Street Bridge.[5]

In April 1899, the City of Winnipeg purchased the plant of the Water Works Company for $237,650, making it a municipally-owned and operated utility. At this time, the source of supply was changed from the Assiniboine River to artesian wells. In October 1900, the well supply was placed in operation.

Between 1900 and 1908, a group of seven wells were dug. These averaged about 5.5 metres (18 ft) in diameter and varied in depth from 14 to 31 metres (46 to 102 ft). In some years, their yield was not consistent and it was evident that a more adequate supply was needed for the rapidly increasing city population.

Creating the Greater Winnipeg Water District

On 23 July 1906, a commission was appointed to investigate the best available source of water supply. The commission engaged the services of a group of engineers which, on 29 August 1907, submitted a report that recommended the City to go to the Winnipeg River for its future water supply. The commission endorsed this recommendation and forwarded it to the Winnipeg City Council on 30 October 1907. At this time, the City was undertaking the building of a hydro electric generating station at Pointe du Bois and was committed to the expenditure of a large sum of money. Consequently, the water supply project was postponed until 1912.

In 1912, the Public Utilities Commissioner, at the request of the City of Winnipeg, caused an investigation to be made and obtained an engineering report that recommended Shoal Lake, Kenora District, Ontario—the western tributary of the Lake of the Woods watershed—as the source of water supply.[6] Winnipeg Mayor Thomas R. Deacon spearheaded making Shoal Lake the city's water source, a project he had supported long before becoming mayor in 1913.[7] The engineer's report also recommended sinking of additional wells to maintain a supply until the larger system could be completed.

In January 1913, a series of meetings was held between Winnipeg and several municipalities in the surrounding region, who reached an agreement on draft legislation to form a metropolitan water district.[7][6]

This resulted in the creation of the Greater Winnipeg Water District (GWWD), incorporated by an Act of the Manitoba Legislature, assented to on 15 February 1913. The Act was passed contingent on the plan being approved by Winnipeg voters. The matter was submitted to vote on 1 May 1913 with 2,226 people in favour and 369 against.[1][6] The areas included in the district were the City of Winnipeg, City of St. Boniface, Town of Transcona, and Rural Municipality of St. Vital, as well as a part of the Rural Municipality of Fort Garry, the Rural Municipality of Assiniboia, and the Rural Municipality of Kildonan.[7]

Planning and construction

On 7 April 1913, the Winnipeg City Council appointed a Board of Consulting Engineers to estimate the cost and general plan of the project to supply the Greater Winnipeg Water District with water from Shoal Lake. This report was submitted on 20 August 1913 and contained the following recommendations:

  • That Shoal Lake water is of excellent quality for domestic and for manufacturing purposes;
  • That Shoal Lake can be depended on to furnish all the water required for the Greater Winnipeg Water District until the population shall have reached about 850,000 and with the help of the Lake of the Woods can furnish a practically inexhaustible supply;
  • That this water be brought from Shoal Lake through a covered concrete aqueduct 136 kilometres (85 mi) in length under open flow conditions to within about eight miles from St. Boniface, thence through a 1.7-metre (5.6 ft) reinforced concrete circular pipe under pressure to the eastern bank of the Red River, thence through a 1.5-metre (5 ft) diameter cast iron pipe in tunnel under the river, and thence through a 1.2-metre (4 ft) diameter reinforced concrete pipe to the reservoirs at McPhillips Street.

The aqueduct between Shoal Lake and the Deacon Reservoir was to have a capacity of 390 million L (85 million imp gal) per day and the pressure portion to be capable of delivering to the McPhillips Street reservoirs about 140 million L (30 million imp gal) per day. The engineers estimated the total cost of the intake, diversion works, concrete aqueduct, pressure portion, and tunnel to be CA$13,045,600, excluding costs for land acquisition and for interest charges during construction.

The engineering report was adopted by the Administration Board of the Greater Winnipeg Water District on 6 September 1913. A by-law was passed to raise the sum of $13,500,000 for the project by the issue and sale of debentures. The plan was put to Winnipeg voters on 1 October 1913 and was approved by a vote of 2,951 in favour and 90 against.

As Shoal Lake is connected with, and is part of, the trans-boundary Lake of the Woods watershed, approval was required from the International Joint Commission which administered the 1909 Boundary Waters Treaty between the United States and Canada.[8]

The project was carried out as outlined in the engineering report with the addition of a 250 million gallon reservoir at Deacon (about eight miles east of St. Boniface), a second 5-foot 6-inch pressure pipe from Deacon to the Red River, and a booster pumping station on the east bank of the Red River capable of delivering 50 million gallons per day to the reservoirs at McPhillips Street.

Surveying along the route of the aqueduct began in 1913 and construction commenced on 1 March 1914. The first work to be undertaken was the building of a 110-mile (180 km) railway, including siding and spurs, a telephone line, clearing and fencing of the right-of-way, and completion of the Falcon River diversion. Construction of the aqueduct began in May 1915 and was virtually completed by the end of 1918.

The Falcon River dam was constructed to divert discoloured water from the Falcon River through the newly-created lake at the west end of Indian Bay and a channel was dug to convey this water to Snowshoe Bay, away from the aqueduct inlet.

Opening and beyond

On 29 March 1919, water from Shoal Lake arrived at the McPhillips Street reservoir and distribution to the City of Winnipeg began on 5 April 1919. The opening ceremony for the aqueduct was performed by Edward, Prince of Wales on 9 September 1919.[9]

As a result of steadily increasing demand for water, construction of a booster pumping station adjacent to the Greater Winnipeg Water District's surge tank in St. Boniface was completed in 1950. This station allowed the District to fully develop the capacity of the existing works and to increase the flow to the City of Winnipeg from 30 to 42 million gallons per day. The station was equipped with three 20 million gallons per day pumping units with electrically controlled switchgear and electrically operated discharge valves. This was the first major addition to the District's aqueduct since the original works were completed in 1919.

In 1954, the District completed a direct 41-centimetre (16 in) diameter pipe connection between the aqueduct and the Municipality of St. Vital, the cost being borne between the District and St. Vital. A pumping station was paid for and operated by St. Vital.

Equipment to fluoridate the water supply was installed at the aqueduct intake and operations commenced on 28 December 1956.

In June 2019, a road to serve the Shoal Lake 40 reserve was completed and officially opened. Residents of Shoal Lake 40 living on the peninsula between Indian and Snowshoe Bays were initially land-locked by the channel conveying water to Snowshoe Bay, and the water in Snowshoe Bay was often not potable.[10]

The Shoal Lake 40 First Nation community had proposed developments but they were cancelled in the interest of protecting the watershed. In lieu of these cancelled developments, a trust fund for the First Nation was set up, to which both the City of Winnipeg and the Province of Manitoba both contribute to.[1]

Description

The entry structure is located at Indian Bay, Shoal Lake, Ontario. On its way to Winnipeg the aqueduct and railway pass through East Braintree, McMunn, Hadashville, Spruce, Larkhill, Monominto, Millbrook and Deacon stations.[11]

The system consists of about 83-mile (134 km) of buried concrete unpressurized conduit and 9.9-mile (16 km) of buried pressurized inverted siphons. Over its length the aqueduct crosses eight rivers. The conduit was built using the "cut and cover" method with an unreinforced concrete arch resting on a cast in place base invert. Sections at road and rail crossings had reinforcing steel. Siphon crossings of rivers were made as reinforced round concrete tubes. The interior dimensions of the aqueduct were selected so that no internal pressure was developed by the water flow; nineteen different interior sections were required. For inspection and maintenance, manholes were provided at approximately 1 mile intervals, which allow insertion of a small boat for inspections. Vent pipes in the manholes allowed controlled entry of air.

Structural design was complicated by the widely varying ground conditions, ranging from rock to soft peat soil. In some places, gravel fill was brought in to replace unsuitable material excavated. The depth of backfill was intended to protect the aqueduct from freezing.

To allow surface water to drain freely across the path of the aqueduct, inverted siphons were installed at fifty-six locations. Freezing was prevented by ensuring the outlet level was always below water level, preventing cold air from entering the siphon.

Since the Falcon River entering Shoal Lake drains a considerable area of muskeg, a dike was built in the lake to prevent brown, organics-laden water from being drawn into the aqueduct. The intake structure included dual intake chambers to allow for maintenance of one while the other was in use. Again, to prevent cold air from entering, the intake level was well below the lake level.

Initially the aqueduct terminated at a reservoir built on McPhillips Street, which had been the center of the city's original water system. The design of the project included provisions for an additional reservoir approximately 13-mile (21 km) east of the McPhillips reservoir. This would allow for peak loads to be served in excess of the aqueduct's nominal capacity and allow for maintenance shutdowns of the aqueduct without interrupting the city's water supply.

Deacon Reservoir

The McPhillips reservoir in the north-west part of the city holds 227 megalitres. The Wilkes reservoir in the southern part holds 251 megalitres. The McLean reservoir in the eastern part of the city holds 205 megalitres. The Deacon reservoir near 49°50′57.29″N 96°56′07.63″W / 49.8492472°N 96.9354528°W / 49.8492472; -96.9354528, built in 1972 with eight open cells, holds 8800 megalitres, equal to a 20-day supply for the city. It is named after Thomas Russ Deacon, who as Mayor of the city drove efforts to secure the Shoal Lake water supply.

Greater Winnipeg Water District

The Greater Winnipeg Water District (GWWD) was a water district serving the Greater Winnipeg area.[8]

The GWWD covered an area of 166.8 km2 (64.42 sq mi) and included the City of Winnipeg (65 km2); parts of the Cities of St. Boniface (17.7 km2), St. James (18.8 km2), and East Kildonan (9 km2); parts of the Towns of Transcona (12.8 km2) and Tuxedo (1.9 km2); and parts of the Municipalities of Fort Garry (20.8 km2), St. Vital (14.3 km2), and West Kildonan (6.2 km2).[8]

It was established in 1913 as a collaboration between the City of Winnipeg and its neighbouring municipalities, who decided to invest CA$13.5 million to access Shoal Lake. Winnipeg Mayor Thomas R. Deacon spearheaded making Shoal Lake the city's water source, a project he had supported long before becoming mayor in 1913. In January 1913, a series of meetings was held between Winnipeg and the municipalities, who reached an agreement on draft legislation to form a water district. On February 15 that year, An Act to incorporate the ‘Greater Winnipeg Water District,’ was assented to in the Manitoba Legislature.[8]

The District was administered by a Board composed of the Mayor of Winnipeg and four other members of City Council; the Mayor of St. Boniface and one other member of its City Council; and the Mayors of St. James, East Kildonan, Transcona, Fort Garry, St. Vital, West Kildonan, and Tuxedo. The Mayor of Winnipeg was the ex officio Chairman, and the work of the corporation was managed by a Board of Commissioners consisting of one to three persons.

The District sold water in bulk—without pressure—and at the same price, to the several participating municipalities. This price was at first based on the cost of maintenance, operation, and management; the Greater Winnipeg Water District Act provided that interest and sinking fund charges should be levied on land only. The GWWD Act was amended in 1927 to allow a maximum price of five cents per thousand gallons to be charged, which became effective on 1 January 1938. Any surplus from sales was used to reduce the annual level based on the findings on an equalization board

The District also operated a railway service between St. Boniface and Shoal Lake, and a sand and gravel business.

The GWWD was eventually succeeded by the City of Winnipeg Water and Waste Department.[8]

Commemoration

Plaque on aqueduct monument, Stephen Juba Park, Waterfront Drive, shows shape of much of the buried conduit, near 49°53′54.37″N 97°07′57.72″W / 49.8984361°N 97.1327000°W / 49.8984361; -97.1327000

A stone monument was unveiled at the foot of James Avenue in Stephen Juba Park in Winnipeg to commemorate the aqueduct. The monument includes a Historic Sites Advisory Board of Manitoba plaque designed in the shape of the aqueduct pipe, a Canadian Water Landmark plaque by the American Water Works Association, and a National Historic Civil Engineering Site plaque unveiled in 1994 by the Canadian Society for Civil Engineering.[9]

On 17 October 1960, the Second Branch Aqueduct was opened as a branch line built to secure the maximum capacity of the GWWD Aqueduct. At the branch's official opening, a plaque and stone & metal sculpture were also unveiled. Originally located on the west side of Pembina Highway, it was moved in 1988 when Bishop Grandin Boulevard was extended west from River Road to Waverley Street and the underpass at Pembina Highway had to be built.[12]

See also

References

  1. ^ a b c d Water and Waste Department. "Shoal Lake and Winnipeg's Drinking Water". legacy.winnipeg.ca. City of Winnipeg. Retrieved 2023-05-21.
  2. ^ http://www.mhs.mb.ca/docs/pageant/24/winnipegaqueduct.shtml The Building of the Winnipeg Aqueduct, retrieved 2014 July 25
  3. ^ Water and Waste Department. "Treatment Plant Background - Water Treatment Program". legacy.winnipeg.ca. City of Winnipeg. Retrieved 2023-05-21.
  4. ^ http://www.winnipegrealtors.ca/Resources/Article/?sysid=936 90th anniversary of Shoal Lake aqueduct, retrieved 2014 July 25
  5. ^ City of Winnipeg Municipal Manual, 1959. City of Winnipeg Archives.
  6. ^ a b c "Greater Winnipeg Water District". www.canadiana.ca. 1918. Archived from the original on 2020-03-24. Retrieved 2020-03-24 – via Canadiana Online.
  7. ^ a b c "Manitoba History: Pressure to Act: The Shoal Lake Aqueduct and the Greater Winnipeg Water District". www.mhs.mb.ca. Retrieved 2023-05-21.
  8. ^ a b c d e "Manitoba History: Pressure to Act: The Shoal Lake Aqueduct and the Greater Winnipeg Water District". www.mhs.mb.ca. Retrieved 2023-03-26.
  9. ^ a b "Historic Sites of Manitoba: Winnipeg Aqueduct Monument (James Avenue, Winnipeg)". www.mhs.mb.ca. Retrieved 2023-05-21.
  10. ^ "Shoal Lake Aqueduct – CSCE / SCGC". Retrieved 2023-05-21.
  11. ^ http://www.ryerson.ca/~amackenz/history/national/w.html Shoal Lake Aqueduct, retrieved 2014 08 30
  12. ^ "Historic Sites of Manitoba: Greater Winnipeg Water District Second Branch Aqueduct Plaque (Bishop Grandin Boulevard, Winnipeg)". www.mhs.mb.ca. Retrieved 2023-05-21.

Further reading

Read other articles:

Ebiet G. AdeLahirAbid Ghoffar(1954-04-21)21 April 1954Wanadadi, Banjarnegara, Jawa Tengah, IndonesiaKebangsaanIndonesiaPekerjaanPenyanyi-penulis lagugitarisfilantropisproduser rekamanTahun aktif1970-an–sekarangSuami/istriKoespudji Rahayu Sugianto ​ ​(m. 1982)​Anak4, termasuk Adera, SegaraOrang tuaAboe Dja'far (bapak)Saodah (ibu)Karier musikAsalBanjarnegara, IndonesiaGenrePopfolk popcountrysoft rockInstrumenVokalgitar akustikLabelJacksonEGATrinityBMG ...

 

Public university in Kingston, Rhode Island, U.S. Not to be confused with Rhode Island College. University of Rhode IslandFormer namesRhode Island College of Agriculture and the Mechanic Arts (1892–1909)Rhode Island State College (1909–1951)MottoHopeTypePublic land-grant research universityEstablishedMay 19, 1892; 131 years ago (1892-05-19)AccreditationNECHEAcademic affiliationsSea-grantSpace-grantEndowment$203 million (2022)[1]PresidentMarc ParlangeProvostBarbar...

 

Cet article est une ébauche concernant les neurosciences. Vous pouvez partager vos connaissances en l’améliorant (comment ?) selon les recommandations des projets correspondants. Pour les veines, voir artère fémorale. Nerf fémoralDétailsBranche de Partie postérieure du plexus lombal (d)Ramification Rameau cutané antérieur du nerf fémoral, rameau musculaire du nerf fémoral (d), nerf saphène, nerf du quadriceps (d), rameau du muscle pectiné du nerf fémoral (d), rameau du m...

Crayon Shin-chan: Mononoke Ninja ChinpūdenPoster rilis teatrikalNama lainNama JepangKanji クレヨンしんちゃん もののけニンジャ珍風伝 TranskripsiRevised HepburnKureyon Shinchan: Mononoke Ninja Chinpūden SutradaraMasakazu HashimotoSkenarioMasakazu HashimotoKimiko UenoBerdasarkanCrayon Shin-chanoleh Yoshito UsuiPemeran Yumiko Kobayashi Miki Narahashi Toshiyuki Morikawa Satomi Kōrogi Mari Mashiba Penata musikToshiyuki ArakawaShinji MiyazakiPerusahaanproduksiShin-...

 

FC Baník OstravaCalcio Baníček Segni distintivi Uniformi di gara Casa Trasferta Colori sociali Blu, rosso Dati societari Città Ostrava Nazione  Rep. Ceca Confederazione UEFA Federazione FAČR Campionato 1. liga Fondazione 1922 Presidente Václav Brabec Allenatore Pavel Hapal Stadio Městský stadion Vítkovice / Bazaly(15 123 / 17 400 posti) Sito web www.fcb.cz Palmarès Titoli nazionali 3 Campionati cecoslovacchi1 Campionato ceco Trofei nazionali 3 Coppe di Cecoslovacchia1 Cop...

 

Canadian ice hockey player (b. 1949) This article is about the ice hockey player. For the footballer, see Bobby Clarke (footballer). For the rock drummer, see Bobbie Clarke. Bob Clarke redirects here. For other people with a similar name, see Robert Clarke (disambiguation). Ice hockey player Bobby ClarkeOC Hockey Hall of Fame, 1987 Clarke in 2017Born (1949-08-13) August 13, 1949 (age 74)Flin Flon, Manitoba, CanadaHeight 5 ft 10 in (178 cm)Weight 176 lb (80 kg; 12...

Le proteste in Palestina del 2011 sono state una serie di proteste in seno all'Autorità Nazionale Palestinese (ANP) e Hamas nella Striscia di Gaza, messo in scena da diversi gruppi palestinesi come parte della più ampia primavera araba. Le proteste erano dirette al governo palestinese, oltre a sostenere le rivolte popolari in Tunisia, Egitto e Siria. Il fine delle proteste era unificare i due principali partiti Fatah e Hamas. Altre ragioni erano la disoccupazione, l'inflazione e la mancanza...

 

Coppa Italia Primavera 1995-1996 Competizione Coppa Italia Primavera Sport Calcio Edizione 24ª Organizzatore Lega Serie A Luogo  Italia Partecipanti 48 Risultati Vincitore  Fiorentina(2º titolo) Secondo  Torino Semi-finalisti  Como Bari Cronologia della competizione 1994-1995 1996-1997 Manuale La Coppa Italia Primavera 1995-1996 è la ventiquattresima edizione del torneo riservato alle squadre giovanili iscritte al Campionato Primavera. Indice 1 Primo turno 2 Ottav...

 

Державний комітет телебачення і радіомовлення України (Держкомтелерадіо) Приміщення комітетуЗагальна інформаціяКраїна  УкраїнаДата створення 2003Керівне відомство Кабінет Міністрів УкраїниРічний бюджет 1 964 898 500 ₴[1]Голова Олег НаливайкоПідвідомчі ор...

Croatian footballer and manager Branko Ivanković Ivanković as Persepolis manager in 2019Personal informationDate of birth (1954-02-28) 28 February 1954 (age 70)Place of birth Varaždin, PR Croatia, YugoslaviaHeight 1.81 m (5 ft 11 in)Position(s) Attacking midfielderTeam informationCurrent team China (manager)Senior career*Years Team Apps (Gls)1979–1990 Varteks 269 (83)Managerial career1991–1995 Varteks1995–1996 Segesta1996–1998 Rijeka1998–1999 Croatia (assistan...

 

Passport of the Commonwealth of Australia issued to Australian citizens Australian passportThe front cover of a current Australian biometric passport The polycarbonate photo page of a current R series Australian passportTypePassportIssued byAustralian Passport Office (DFAT)First issued1901 (first version following federation)1984 (machine-readable passport)24 October 2005 (biometric passport)September 2022 (current version)In circulation14.2 million (2023)[1]PurposeIdentific...

 

The inland and intercoastal waterways, with the Upper Mississippi highlighted in red. The first bridge (and only log bridge) over the Mississippi, about 25 feet south of its source at Lake Itasca This is a list of all current and notable former bridges or other crossings of the Upper Mississippi River which begins at the Mississippi River's source and extends to its confluence with the Ohio River at Cairo, Illinois. This transport-related list is incomplete; you can help by adding missing it...

مارتن كرامر (بالإنجليزية: Martin Kramer)‏    معلومات شخصية الميلاد 9 سبتمبر 1954 (70 سنة)  واشنطن العاصمة  مواطنة الولايات المتحدة إسرائيل  الحياة العملية المدرسة الأم جامعة برينستونجامعة كولومبيا  المهنة عالم سياسة،  وصحفي،  ومستشرق  اللغات الإنجليزية،  و�...

 

German–American philosopher, sociologist, and political theorist (1898–1979) Marcuse redirects here. For other uses, see Marcuse (disambiguation). Herbert MarcuseMarcuse in 1955Born(1898-07-19)July 19, 1898Berlin, German EmpireDiedJuly 29, 1979(1979-07-29) (aged 81)Starnberg, West GermanyNationalityGermanAmericanAlma materUniversity of BerlinUniversity of FreiburgNotable workEros and Civilization (1955)One-Dimensional Man (1964)Spouses Sophie Wertheim ​ ​(m.&...

 

Historical territory in South Germany and North Switzerland For other uses, see Baden (disambiguation). Grand Duchy of Baden with the Margraviate (red) and gains after 1803 Hohenbaden Castle on the Battert above Baden-Baden Monument to Charles Frederick, Grand Duke of Baden in front of Karlsruhe Palace Baden (/ˈbɑːdən/; German: [ˈbaːdən]) is a historical territory in South Germany. In earlier times it was considered to be on both sides of the Upper Rhine, but since the Napoleon...

Shopping mall in Texas, USAThe Shops at La CanteraLocationLa Cantera, San Antonio, Texas, USAOpening date2005 (phase I)2008 (phase II)DeveloperThe Rouse CompanyManagementBrookfield PropertiesOwnerBrookfield Properties[1]ArchitectAlamo ArchitectsNo. of stores and services194No. of anchor tenants6Total retail floor area1,246,938 sq ft (115,844.3 m2)No. of floors2Websitetheshopsatlacantera.com The Shops at La Cantera is an open-air regional shopping mall located in La Cant...

 

Polish football club Football clubJKS 1909 JarosławFull nameJarosławski Klub Sportowy 1909 JarosławFounded5 July 1909; 115 years ago (1909-07-05) (as Pogoń Jarosław)GroundJKS StadiumCapacity2,074ChairmanGracjan DziukiewiczManagerBogdan ZającLeagueIV liga Subcarpathia2023–24IV liga Subcarpathia, 11th of 18WebsiteClub website Home colours JKS 1909 Jarosław is a Polish football club based in Jarosław. They currently play in the IV liga Subcarpathia, the fifth tier of ...

 

1955 picture book by John Langstaff This article needs additional citations for verification. Please help improve this article by adding citations to reliable sources. Unsourced material may be challenged and removed.Find sources: Frog Went A-Courtin' book – news · newspapers · books · scholar · JSTOR (October 2015) (Learn how and when to remove this message) Frog Went A-Courtin' First editionAuthorJohn LangstaffIllustratorFeodor RojankovskyGenreC...

Battle of the War of the First Coalition Not to be confused with the earlier Battle of Limburg (1792). Battle of LimburgPart of the War of the First CoalitionMarker indicating the location of the Austrian lineDate16–19 September 1796LocationLimburg an der Lahn, GermanyResult Austrian victoryBelligerents Republican France Habsburg AustriaCommanders and leaders Jean-Baptiste Jourdan Archduke CharlesUnits involved Army of Sambre-et-Meuse Army of the Lower RhineStrength 45,000 20,000 vteRhi...

 

Regulations for flying an aircraft in clear weather conditions In aviation, visual flight rules (VFR) are a set of regulations under which a pilot operates an aircraft in weather conditions generally clear enough to allow the pilot to see where the aircraft is going. Specifically, the weather must be better than basic VFR weather minima, i.e., in visual meteorological conditions (VMC), as specified in the rules of the relevant aviation authority. The pilot must be able to operate the aircraft...