Champlain Bridge (Montreal, 1962–2019)

Champlain Bridge

Pont Champlain (French)
Champlain Bridge in October 2010
Coordinates45°28′07″N 73°31′03″W / 45.46861°N 73.51750°W / 45.46861; -73.51750
CarriedSix lanes of Autoroute 10, 15, 20
CrossedSt. Lawrence River and
Saint Lawrence Seaway
LocaleBrossard and Montreal, Quebec, Canada
OwnerThe Jacques Cartier and Champlain Bridges Inc.
Maintained byThe Jacques Cartier and Champlain Bridges Inc.
Websitejacquescartierchamplain.ca?lang=en
Characteristics
DesignSteel truss Cantilever bridge
MaterialSteel, Concrete
Total length3,440 m (11,286 ft)
7,412 m (24,318 ft) (including approaches)[1]
Longest span215.5 m (707.02 ft)[1]
Clearance below36.6 m (120 ft) at mid-span[1]
No. of lanes6
History
DesignerPhilip Louis Pratley
Henry Hugh Lewis Pratley
Engineering design byPhilippe Ewart
Lalonde and Valois
Constructed byAtlas Construction Company Limited
McNamara (Quebec) Limited
The Key Construction Inc.
Deschamps & Bélanger Limitée
Dominion Bridge Company
Construction start1957
Construction costC$35 million
C$52 million (including approaches and Bonaventure Expressway)
OpenedJune 28, 1962 (1962-06-28)
ClosedJune 28, 2019 (2019-06-28)
Demolishedc. 2024
Statistics
Daily traffic159,000[2]
TollCollected until 1990
Location
Map

The Champlain Bridge (French: Pont Champlain) was a steel truss cantilever bridge with approach viaducts constructed of prestressed concrete beams supporting a prestressed concrete deck paved with asphalt. Opened in 1962, the bridge crossed the Saint Lawrence River, connecting the Island of Montreal to its South Shore suburbs.[3]

Together with the Jacques Cartier Bridge, it was administered by the Jacques Cartier and Champlain Bridges Incorporated (JCCBI), a Canadian Crown Corporation which reports to Housing, Infrastructure and Communities Canada. Since December 21, 1978, JCCBI was responsible for the management, maintenance and monitoring of the Champlain Bridge.[4]

The bridge saw about 50 million crossings per year, of which 200,000 were buses. On an average weekday, 66% of users were commuters. It was one of the busiest bridges in Canada until its closure in 2019.[5]

Towards the end of its life, the Champlain Bridge was well known to be in an advanced state of decay. Long-discussed plans to construct a replacement bridge finally came to fruition when construction commenced in 2015. In 2019, upon the opening of the new bridge (formally known as the Samuel-De Champlain Bridge), the original Champlain Bridge was closed and promptly demolished, concluding 57 years of service.[3][6][7]

Specifications

The Champlain Bridge project was undertaken in 1955 and construction proceeded between 1957 and 1962. The bridge carried six lanes of vehicle traffic; three in each direction. During rush hour one lane of those heading off the island in the morning, and onto the island in the evening, was used as a reserved bus lane for buses to be able to head in the opposite direction. The bridge was opened to traffic in stages as the approaches were completed between June 1962 and September 1964. It was subsequently connected to the Bonaventure Expressway, which was part of the north approach to the bridge. The expressway was opened to traffic on April 21, 1967. It was one of North America's busiest highways with almost 59 million crossings annually.

  • Total length of crossing complex: 14.5 km (9 mi)
  • Total bridge length including approaches: 7,412 m (24,318 ft)
    • Length: abutment to abutment: 3,440 m (11,290 ft)
    • Link of viaduct to Section 1: 2,195 m (7,201 ft)
    • Center main cantilevered span: 215 m (705 ft)
    • Wellington Street approach: 365 m (1,198 ft)
  • Bonaventure Expressway: 4,573 m (15,003 ft)

Just upstream from the bridge there is an ice boom, the Champlain Bridge Ice Control Structure.[8]

Construction history

View from the east side of the Saint Lawrence River, July 2011
The upstream ice control structure

On August 17, 1955, Federal Transport Minister George Marler announced the planned construction of a new bridge connecting Montreal to the South Shore via Nun's Island. The city's existing bridges (Victoria, Cartier, and Mercier) had become inadequate to support the amount of traffic that carried residents from the growing South Shore suburbs into Montreal.

The project was initially called the Nuns' Island Bridge because it crosses Nuns' Island. In 1958, it was named the Champlain Bridge in honour of the explorer Samuel de Champlain.

The National Harbours Board was placed in charge of the project. Through several lengthy meetings and consultations in the fall of 1955, the location for the bridge and its approaches were selected. Originally, the plan had been to build the bridge with only 4 lanes, with room for further expansion to 6 lanes. During the design phase, however, it was decided to go with an initial 6-lane design.

It was opened on June 28, 1962 at 4 p.m. with only one approach from Montreal, via Wellington Street. A section including approaches to and from Atwater Street and La Vérendrye Boulevard were opened two years later.

In 1967, the final approach to the bridge on the Montréal side was completed when the Bonaventure Expressway was opened to traffic.[9]

A $0.25 toll ($0.08 if paid with tokens) was charged to finance the $35 million cost of the Champlain Bridge. The toll was collected until 1990, when the Jacques Cartier and Champlain Bridges Incorporated (JCCBI), which took over jurisdiction of the bridge a dozen years earlier, removed the toll plaza.[10]

In 1992, the concrete deck of the cantilever metal part was replaced by an orthotropic steel deck. Gutters to channel the corrosive runoff to the river appeared in 1994. The pressure exerted by the reinforced beams on the ends of the trimmers then required the reinforcement of the latter by steel rods under tension.

In November 2013, a crack was discovered in a critical part of the superstructure. One lane was closed immediately, and emergency repair plans were put in place. During preparation, the crack enlarged and a second lane was closed.[11] On November 29, 2013, a temporary external beam of 75 tons, named "super-beam" by the media, was urgently installed to reinforce the structure. In June 2014, JCCBI replaced the super-beam with a modular truss that was designed and manufactured in Quebec.

As part of a 2014–2017 Edge girder reinforcement program, 94 modular trusses and six shoring systems were installed to stabilize the condition of the bridge girders.[3]

Problems and replacement

Montreal's climate subjected the Champlain Bridge to wintry cold, snowfall, and windy conditions, as well as contrasting hot and humid summer conditions, all of which accelerated damage to the bridge. Because of the potential danger from ice accumulation during winter, the bridge was salted every season for decades. Salt attacks both the concrete and steel rebar used in girders, pylons, and other parts. The problems associated with the design and maintenance of the Champlain Bridge thus exceeded the useful life of several structural components. The design and construction of the structure prevented the isolation of outdated elements and their replacement with new ones, as could be done on other structures. Given the advanced deterioration of the bridge, it was constantly monitored by 300 sensors.

Several reinforcement measures and rehabilitation programs were deployed over time by JCCBI. However, none of these were effective in the long term.

In 2009, the Government of Canada announced in its 2009 Economic Action Plan that it would be allocating $212 million to renew the bridge. In March 2011, the Government of Canada announced $158 million were to be spent on a major repair and maintenance program as concerns mounted that it was at risk of collapse. Montreal's La Presse newspaper cited two leaked engineering reports prepared for a federal bridge agency that suggested sections of the structure were in a severe state of deterioration. The report concluded that a partial or complete collapse of the span could not be ruled out.[12]

Starting in 2009, JCCBI — the Federal agency that managed the structure — began conducting a major repair program to extend the useful life of the Champlain Bridge. In 2010, JCCBI retained international engineering firm Delcan to carry out an expert study of the bridge's structural health. The firm returned a report entitled "The Future of the Champlain Bridge Crossing". In the Executive Summary, the bridge was said to be "functionally deficient" for both current and long-term traffic demands, and showing "significant deterioration".[13] One finding suggested that the Champlain Bridge was in "very much poorer condition than would be typical" for comparable bridges. Delcan concluded that the bridge had "many deficiencies" and, even in light of the methodical inspection and rehabilitation of the structure undertaken by its owners, that continued operation "entails some risks that cannot altogether be quantified".

In September 2007, faced with rising costs for the maintenance of the Champlain Bridge, then Canadian Minister of Transport Lawrence Cannon confirmed that his department was seriously considering the construction of a replacement structure. In August 2008, Transport Canada announced that it was exploring different scenarios for a new bridge. In October 2011, then Minister of Transport Denis Lebel officially announced that construction on the new bridge would begin within 10 years.

In April 2015, the federal government selected the JV consortium: Signature on the St. Lawrence Group to build the new bridge. The consortium mainly included SNC-Lavalin, the Spanish ACS Infrastructure, and Dragados Canada. T.Y. Lin International served as the Lead Designer.[14]

Construction on the new bridge officially began on June 16, 2015. On December 19, 2018, Minister of Infrastructure and Communities François-Philippe Champagne announced that the official name of the new bridge would be the Samuel-de-Champlain Bridge.[15] The bridge opened to northbound/westbound traffic on June 24, 2019 (St-Jean-Baptiste Day), with the official opening ceremony being held on June 28, 2019, and southbound/eastbound traffic opening on 1 July 2019 (Canada Day). The multi-purpose runway was opened in November 2019 followed by the REM train tracks on July 31, 2023.[16][17]

As soon as the new bridge was opened to traffic, the old bridge was closed and demolition work began immediately.

The cable-stayed Samuel de Champlain bridge (background) illuminated at night, with the old truss cantilever bridge (foreground) being dismantled, May 2022.

See also

References

  1. ^ a b c "Champlain Bridge: Technical Data". Bridges & Structures. The Jacques Cartier and Champlain Bridges Incorporated. Archived from the original on December 11, 2013. Retrieved December 6, 2013.
  2. ^ Sources disagree on the actual figure:
  3. ^ a b c "Original Champlain Bridge ⋆ PJCCI". PJCCI. Retrieved March 12, 2018.
  4. ^ "About ⋆ PJCCI". PJCCI. Retrieved March 12, 2018.
  5. ^ "New Champlain Bridge - Frequently Asked Questions". Infrastructure Canada. February 21, 2012. Retrieved August 26, 2016.
  6. ^ "Montreal's Samuel De Champlain Bridge is now open | CBC News".
  7. ^ "Demolition of old Champlain Bridge to cost $400". CBC. April 5, 2017.
  8. ^ "Technical Data Sheet - Champlain Bridge Sector" (PDF). PJCCI.com. Archived from the original (PDF) on June 26, 2017.
  9. ^ "The Champlain Bridge and the Bonaventure Expressway" (PDF). Archived from the original (PDF) on June 25, 2008. Retrieved July 1, 2008.
  10. ^ "The Champlain Bridge:Historic overview". Retrieved April 29, 2009.
  11. ^ "Champlain Bridge: The Support Beam operation is underway - two lanes per direction during the next few days - Pont Champlain Bridge". Archived from the original on December 2, 2013. Retrieved November 24, 2013.
  12. ^ "Montreal bridge gets $158M in repair funds". CBC News. March 18, 2011. Retrieved March 18, 2011.
  13. ^ Delcan, Inc (March 28, 2011). "Future of the Champlain Bridge Crossing" (PDF). pjcci.ca. Archived from the original (PDF) on July 23, 2011. Retrieved April 11, 2011.
  14. ^ "New Champlain Bridge Corridor Project". Road-Traffic Technology.com. Retrieved November 8, 2017.
  15. ^ Magder, Jason (December 19, 2019). "The new Champlain Bridge is finished — mostly". Montreal Gazette. Retrieved July 7, 2019.
  16. ^ "Work schedule 2021". REM. Retrieved November 22, 2021.
  17. ^ Nerestant, Antoni (July 31, 2023). "Stuck railway switch on Montreal's new REM to blame for bumpy start to 1st official day". CBC News. Retrieved July 31, 2023.

Media related to Champlain bridge at Wikimedia Commons

Read other articles:

ReturnPoster promosiHangul리턴 GenreMisteriThrillerDrama hukumDitulis olehChoi Kyung-miSutradaraJoo Dong-minPemeranGo Hyun-jung (Ep. 1–15)Park Jin-hee (Ep. 16–34)Lee Jin-wookShin Sung-rokBong Tae-gyuPark Ki-woongJung Eun-chaeYoon Jong-hoonNegara asalKorea SelatanBahasa asliKoreaJmlh. episode34[a]ProduksiPengaturan kameraSingle-cameraDurasi35 menit[a]Rumah produksiThe Story WorksDistributorSeoul Broadcasting SystemRilis asliFormat gambar1080i (HDTV)Format audioDolby Digi...

 

العلاقات الإكوادورية التشادية الإكوادور تشاد   الإكوادور   تشاد تعديل مصدري - تعديل   العلاقات الإكوادورية التشادية هي العلاقات الثنائية التي تجمع بين الإكوادور وتشاد.[1][2][3][4][5] مقارنة بين البلدين هذه مقارنة عامة ومرجعية للدولتين: وجه الم...

 

South Carolinian election for State Treasurer 2022 South Carolina Treasurer election ← 2018 November 8, 2020 (2020-11-08) 2026 → Turnout50.86%   Candidate Curtis Loftis Sarah E. Work Party Republican Alliance Popular vote 1,129,961 281,695 Percentage 79.67% 19.86% Treasurer before election Curtis Loftis Republican Elected Treasurer Curtis Loftis Republican Elections in South Carolina Federal government U.S. President 1788-89 1792 1796 1800 1804 1...

Kualifikasi Piala Dunia FIFA 2022Informasi turnamenJadwalpenyelenggaraan6 Juni 2019 – 14 Juni 2022Jumlahtim peserta207[cat. 1] (dari 6 konfederasi)Statistik turnamenJumlahpertandingan784Jumlah gol2.236 (2,85 per pertandingan)Jumlahpenonton6.789.008 (8.659 per pertandingan)Pencetak golterbanyak Abu Makhbout(14 gol)← 2018 2026 → Seluruh statistik akurat per 30 Januari 2022. Kualifikasi Piala Dunia FIFA 2022 akan menentukan 31 dari 32 tim nasional sepak bola ...

 

Socially and economically organized region in Colombia Location of the Aburrá Valley region within the Antioquia Department. The Metropolitan Area of the Aburrá Valley (Spanish: Área Metropolitana del Valle de Aburrá) is the second most important and populated metropolitan area in Colombia. The region is made up of ten municipalities, Medellín being the most important, largest and the capital city of the Antioquia Department. History The Metropolitan Area of the Aburrá Valley was the fi...

 

Chemical compound AM-4030Identifiers IUPAC name (6S,6aR,9R,10aR)-9-(hydroxymethyl)-6-[(E)-3-hydroxyprop-1-enyl]-6-methyl-3-(2-methyloctan-2-yl)-6a,7,8,9,10,10a-hexahydrobenzo[c]chromen-1-ol CAS Number587023-54-9 YPubChem CID10550598ChemSpider8725989 YUNIICGYGFRRXKKChemical and physical dataFormulaC27H42O4Molar mass430.629 g·mol−13D model (JSmol)Interactive image SMILES OCC=CC3(C)C1CCC(CO)CC1c2c(O3)cc(cc2O)C(C)(C)CCCCCC InChI InChI=1S/C27H42O4/c1-5-6-7-8-12-26(2,3)20-16-23(30...

Elliptical galaxy in the constellation Aries NGC 904legacy surveys image of NGC 903 and NGC 904 (left)Observation data (J2000 epoch)ConstellationAriesRight ascension02h 24m 05.546s[1]Declination+27° 20′ 32.97″[1]Redshift0.017956[2]Heliocentric radial velocity5335 km/s[2]Distance234.9 Mly (72.02 Mpc)[3]Apparent magnitude (B)14.98[4]CharacteristicsTypecE[4]Other designationsUGC 1852, MCG +04-06-024...

 

Italian businessman Francesco Gaetano CaltagironeCaltagirone with Giorgio Napolitano, President of the Italian RepublicBorn (1943-03-02) 2 March 1943 (age 81)[1]Rome, ItalyOther namesFrancesco Caltagirone, Franco CaltagironeOccupationBusinessmanKnown forOwns more than 50% of Caltagirone S.p.A.[2]SpouseLuisa FarinonChildren3 Francesco Gaetano Caltagirone (Italian pronunciation: [franˈtʃesko ɡa.eˈtaːno kaltadʒiˈroːne]; born 2 March 1943) is an Ital...

 

Endangered Alacalufan language of Chile KawésqarAlacalufKawésqar, QawasqarNative toChileRegionChannel Region, western Patagonia, Wellington Island off south Chilean coast, 49° south, with centre in Puerto Edén.Ethnicity2,600 Alacaluf people (2002 census)[1]Native speakers10 (2019)[2]Language familyAlacalufan KawésqarLanguage codesISO 639-3alcGlottologqawa1238ELPKawésqarKawésqar is classified as Critically Endangered by the UNESCO Atlas of the World's Languages...

Railway line in Osaka & Nara, Japan For the West Japan Railway Company (JR West) Nara Line, see Nara Line. This article needs additional citations for verification. Please help improve this article by adding citations to reliable sources. Unsourced material may be challenged and removed.Find sources: Nara Line Kintetsu – news · newspapers · books · scholar · JSTOR (January 2022) (Learn how and when to remove this message) Nara LineA Kintetsu 8...

 

يفتقر محتوى هذه المقالة إلى الاستشهاد بمصادر. فضلاً، ساهم في تطوير هذه المقالة من خلال إضافة مصادر موثوق بها. أي معلومات غير موثقة يمكن التشكيك بها وإزالتها. (يوليو 2019) الملعب البلدي الهادي بن رمضان برادسمعلومات عامةالبلد  تونس الاستعمالالمستضيف النجم الرياضي الرادسيال...

 

1918 silent film Midnight MadnessDirected byRupert JulianWritten byElliott J. ClawsonStarringRuth Clifford Kenneth Harlan Harry von MeterCinematographyEdward A. KullProductioncompanyUniversal PicturesDistributed byUniversal PicturesRelease date June 8, 1918 (1918-06-08) Running time50 minutesCountryUnited StatesLanguagesSilent English intertitles Midnight Madness is a 1918 American silent mystery film directed by Rupert Julian and starring Ruth Clifford, Kenneth Harlan and Harr...

Study of finance of an enterprise This article relies largely or entirely on a single source. Relevant discussion may be found on the talk page. Please help improve this article by introducing citations to additional sources.Find sources: Strategic financial management – news · newspapers · books · scholar · JSTOR (January 2011) Corporate finance Financial management Asset and liability management Business plan Clawback Corporate action Enterprise risk...

 

Questa voce o sezione sull'argomento videogiochi sportivi non cita le fonti necessarie o quelle presenti sono insufficienti. Puoi migliorare questa voce aggiungendo citazioni da fonti attendibili secondo le linee guida sull'uso delle fonti. Harry Potter e la Coppa del Mondo di QuidditchvideogiocoPiattaformaMicrosoft Windows, Game Boy Advance, Xbox, GameCube, PlayStation 2 Data di pubblicazione28 ottobre 2003 GenereSport OrigineStati Uniti SviluppoElectronic Arts Pubblica...

 

Bridge between New Jersey and New York Bayonne BridgeCoordinates40°38′31″N 74°08′31″W / 40.642°N 74.142°W / 40.642; -74.142Carries4 lanes of NY 440 (NY side) / Route 440 / CR 501 (NJ side)CrossesKill Van KullLocaleStaten Island, New York and Bayonne, New JerseyMaintained byPort Authority of New York and New JerseyCharacteristicsDesignSteel arch bridgeTotal length5,780 feet (1,762 m)Width85 feet (26 m)Longest span1,675 feet (510.54 m)Clea...

1 Tawarikh 6Kitab Tawarikh (Kitab 1 & 2 Tawarikh) lengkap pada Kodeks Leningrad, dibuat tahun 1008.KitabKitab 1 TawarikhKategoriKetuvimBagian Alkitab KristenPerjanjian LamaUrutan dalamKitab Kristen13← pasal 5 pasal 7 → 1 Tawarikh 6 (atau I Tawarikh 6, disingkat 1Taw 6) adalah pasal keenam Kitab 1 Tawarikh dalam Alkitab Ibrani dan Perjanjian Lama di Alkitab Kristen. Dalam Alkitab Ibrani termasuk dalam bagian Ketuvim (כְּתוּבִים, tulisan).[1] Pasal ini berisi d...

 

Rumah Tambi Rumah Tambi adalah rumah adat atau rumah tradisional dari Tampo Lore, Kabupaten Poso, provinsi Sulawesi Tengah, Indonesia. Rumah adat ini berbentuk panggung yang atapnya sekaligus berguna sebagai dinding. Rumah Tambi merupakan rumah bagi suku Pekurehua (Napu), Bada dan Behoa di Lemba Lore yang umumnya merupakan rumah penduduk setempat serta beberapa wilayah di Sulawesi Tengah menjadikan rumah ini sebagai rumah bagi kepala adat.[1] Yang membedakannya adalah jumlah anak tang...

 

Besatecomune LocalizzazioneStato Italia Regione Lombardia Città metropolitana Milano AmministrazioneSindacoPasini Ottorino (facente funzioni, Sindaco deceduto il 26-07-2023 (Per Besate insieme) dal 26-7-2023 TerritorioCoordinate45°19′N 8°58′E45°19′N, 8°58′E (Besate) Altitudine104 m s.l.m. Superficie12,74 km² Abitanti2 031[1] (31-12-2021) Densità159,42 ab./km² FrazioniCascina Caremma, Cascina Cantarana, Cascina Molinotto, C...

Jalan Tol Aceh–BinjaiInformasi ruteDikelola oleh PT Hutama Karya (Persero)Panjang:137 km (85 mi)Sejarah:14 Desember 2018Persimpangan besarUjung utara:Banda AcehUjung selatan:BinjaiLetakKota besar:Banda AcehSigliBireunLhokseumaweLangsaSistem jalan bebas hambatanAH 25 Sistem Jalan di Indonesia Jalan Tol Jalan raya Jalan Tol Aceh–Binjai adalah jalan tol bagian dari Jalan Tol Trans Sumatra yang menghubungkan Provinsi Aceh dengan Provinsi Sumatera Utara. Tahap pertama pembangunannya...

 

خياطةصنف فرعي من عملية — Textiles Fügen (de) — عمل في ورشة جزء من فنون النسيج — clothmaking (en) يمتهنه seamstress (en) تعديل - تعديل مصدري - تعديل ويكي بيانات صندوق خياطة فولاذ مقاوم للصدأ مخيط على أنبوب تأين. كشتبان. تطريز خياطة،وسادة مطرزة يدوي من خيوط الحرير الخياطة هي عملية ربط الملابس أو الج...