A railway was first planned in 1885. Investigations into the line were conducted in 1968, funding was agreed in 1973, and construction began the following year. The first section, from Owendo to Ndjolé, opened in 1978, with the remaining sections opening in stages until December 1986. Costs were well over budget and almost bankrupted the country.
Because the line was built well into the era of earthmoving machinery, the need to choose a narrow gauge to save costs was no longer important. As well, the choice of standard gauge (1,435 mm (4 ft 8+1⁄2 in)) took advantage of off-the-shelf equipment. It was constructed by a consortium of Impregilo, Astaldi, Philipp Holzmann, Constructions et entreprises industrielles and Entreprise de construction franco-africaine.[2]
The discovery of uranium helped to secure British interest in the project, and led to the injection of funds by the Conservative government under prime minister Margaret Thatcher. Many UK expatriates took the place of French workers and the building of the railway progressed rapidly from that point. About May 1983, CCI Eurotrag (a consortium of British, Italian and German interests) took over funding. British firms involved included Wimpey International, who seconded staff to Taylor Woodrow.
The building of the initial 182 kilometres of the line from Owendo to Ndjole took over 10 years to complete. The remaining 400-plus kilometres took only five years.
Recent history
In 2003 Hughes Network Systems (see Hughes Communications) installed a satellite-based telephony system into all the railway stations of the railway.[3]
In June 2006 a new line for iron ore from Belinga to port was announced. It is unclear if it will use part of the existing line. The track will be standard gauge.[4] This line was supposed to open in 2012, but in 2014 completion is still awaited.
Two EMD JT42CWR locomotives shipped September 2011.[5][6] A further 4 locomotives and 10 passenger coaches were also ordered.[7]
On 18 May 2019 three workers were killed in an accident on the line.[8]
In February 2023 Fortescue Metals Group inked in an agreement to develop iron ore at Belinga with a road and railway haulage to an existing port.
Network
There are no links with the adjacent states of Equatorial Guinea, Cameroon, or the Republic of the Congo.
The railway is important for transporting timber and uranium in addition to being the only important public transport route in the nation. In 1996, the railway carried freight and 190,000 passengers.[9]
The Trans-Gabon Railway, 669 km (416 mi) has 23 stations.
Trivia
The Trans-Gabon Railway crosses the Ogooué River five times, at Franceville, at Ndjolé, and three times around Booué, also at Lastoursville, where one girder bridge crosses the river to the east of Lastoursville. The Italians were responsible for the actual bridge building from Lastoursville heading East toward the Congo.
Minko Monique. 1983. Les communications Terrestres. in Geographie et Cartographie du Gabon, Atlas Illustré led by The Ministère de l'Education Nationale de la Republique Gabonaise. Pg 86-87. Paris, France: Edicef