Hydropower station in Nepal
Dam
Tinau Hydropower Plant (Nepali: तिनाउ जलविद्युत आयोजना, Tinau Jalbidyut Ayojana) is a run-of-river hydro-electric plant located in Rupandehi District of Nepal. The flow from Tinau River is used to generate 1.024 MW electricity.[1]
The plant was constructed in the leadership of Odd Hoftun.[2][3] It was commissioned in 1978 with two 250-kW turbine-generators with total capacity of 500-kW. The project was later upgraded to 1.024 MW in assistance from ADB. The project has 2.462 km long tunnel, underground desilting chamber, and semi-underground powerhouse.[4] The weir is 10 m high and 63 m long.[5] The design flow is 2.5 m3/s.[6] The power plant was initially owned by Butwal Power Company, a private company that constructed the plant. After the expiry of licence, the ownership was transferred to Nepal Electricity Authority (NEA).[1]
The plant had suffered damage due to flood in 1983.[7]
Significance
The plant is considered instrumental to train Nepali Technicians/Engineers in various disciplines such as tunnelling, hydropower construction.[5]
Gallery
See also
List of power stations in Nepal
References