The Harris Nuclear Plant is a nuclear power plant with a single Westinghouse designed pressurized-waternuclear reactor operated by Duke Energy. It was named in honor of W. Shearon Harris, former president of Carolina Power & Light (predecessor of Progress Energy Inc.).[2] Located in New Hill, North Carolina, in the United States, about 20 miles (30 km) southwest of Raleigh, it generates 900 MWe, uses a 523-foot (160 m) natural draft cooling tower for cooling, and uses Harris Lake for cooling tower makeup, shutdown and emergency cooling. The reactor achieved criticality in January 1987 and began providing power commercially on May 2 of that year.
The Shearon Harris site was originally designed for four reactors (and still has the space available for them), but only one was built. The final cost approached $3.9B, including safety upgrades mandated after the Three Mile Island accident.
On November 16, 2006, the operator applied to the Nuclear Regulatory Commission (NRC) for a renewal and extension of the plant's operating license.[3]
The NRC granted the renewal on December 17, 2008, extending the license from forty years to sixty.[4]
Refurbished generator from Three Mile Island
On January 22, 2010, officials at the Nuclear Regulatory Commission announced the electrical generator from the damaged Unit 2 reactor at Three Mile Island would be used at Shearon Harris.[5] The generator was refurbished and installed during a refueling outage in November, 2010.
Units 2 & 3
On February 19, 2008 Progress filed an application with the Nuclear Regulatory Commission (NRC) for a Combined Construction and Operating License (COL). It seeks to build two 1,100 MWe Westinghouse AP1000 pressurized water reactors. Although the NRC had already certified the AP1000 design, the application review was expected to take about 36 months. The new reactors would not be operational before 2018.[6]
Expansion of the plant would require raising the water level of Harris Lake by 20 feet,[7] decreasing the size of Wake County's largest park, with the Cape Fear River as a backup water source.
On May 2, 2013, Duke submitted a request to the NRC to suspend review of the Harris Units 2 and 3 Combined License Application (COLA), effectively halting further development of this project.[8] Duke has determined the forecast operating dates of the proposed reactors falls outside the fifteen-year planning horizon utilized by state regulators in their demonstration of need evaluation. The COLA remains docketed, however, leaving the door open for Duke to restart activities.[9]
Electricity Production
Generation (MWh) of Shearon Harris Nuclear Power Plant[10]
Year
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Annual (Total)
2001
651,550
587,897
650,961
600,053
641,046
612,514
633,035
632,278
392,127
-7,612
-7,423
-17,930
5,368,496
2002
596,616
605,885
692,186
664,354
685,426
656,254
587,765
633,905
657,210
687,635
670,898
696,922
7,835,056
2003
697,798
628,360
692,040
550,040
200,220
585,862
675,487
566,282
586,953
690,227
668,416
695,419
7,237,104
2004
696,104
651,056
691,524
640,461
378,332
655,523
674,118
676,491
658,386
324,248
268,635
693,550
7,008,428
2005
691,938
627,883
693,146
663,595
577,180
654,438
670,675
671,369
652,216
669,072
664,739
694,577
7,930,828
2006
691,473
624,282
689,215
144,735
256,719
651,468
665,897
665,520
588,819
689,625
669,468
692,047
7,029,268
2007
691,771
626,054
685,273
660,878
678,022
648,431
666,547
661,605
600,239
137,065
667,641
679,524
7,403,050
2008
692,158
644,233
684,058
661,179
679,592
648,293
672,513
436,426
656,281
686,147
668,900
691,631
7,821,411
2009
693,809
624,890
688,165
342,241
441,456
659,020
680,311
678,090
657,569
689,492
551,057
697,061
7,403,161
2010
690,254
632,140
695,980
666,054
685,081
654,660
677,181
677,639
653,802
11,904
336,596
699,324
7,080,615
2011
695,889
622,800
697,118
668,969
685,747
657,595
676,763
678,847
661,806
693,847
675,050
697,696
8,112,127
2012
700,273
654,589
692,354
421,429
-7,575
461,809
691,734
698,837
681,896
711,705
692,239
715,075
7,114,365
2013
716,430
638,321
692,542
683,333
324,651
512,112
696,829
645,140
656,853
708,893
175,051
438,208
6,888,363
2014
606,998
645,639
714,360
684,365
535,765
670,317
696,617
698,502
678,978
709,000
692,342
715,692
8,048,575
2015
716,758
650,304
712,106
15,096
333,847
671,653
695,019
696,555
677,127
706,975
692,525
704,212
7,272,177
2016
716,122
673,699
712,660
687,985
706,362
676,975
695,043
696,569
672,401
136,077
416,053
723,105
7,513,051
2017
721,046
643,988
717,641
688,333
709,239
680,788
698,805
701,133
674,279
556,960
697,080
719,281
8,208,573
2018
593,388
643,338
715,370
128,815
459,520
701,420
724,583
723,583
701,214
733,607
721,164
741,912
7,587,914
2019
744,045
669,919
737,793
704,407
720,979
691,860
708,692
710,988
687,739
221,209
268,342
744,621
7,610,594
2020
743,483
694,486
677,007
716,207
735,529
621,287
716,872
649,871
702,747
732,024
715,179
570,901
8,275,593
2021
741,049
668,251
740,789
529,499
364,993
605,624
721,395
719,843
702,654
732,369
720,298
739,969
7,986,733
2022
745,709
670,409
739,405
671,858
725,765
699,163
716,382
647,562
0
0
5,616,253
2023
Reactor data
The Shearon Harris Nuclear Power Plant consists of one operational reactor. Three additional units were cancelled. Two additional reactors were planned and cancelled in 2013.[11]
As of September 2017, the Harris plant is one of three out of the 99 plants in the country to have no Nuclear Regulatory Commission (NRC) findings during the past 4 quarters of inspections.[15]
The NRC's risk estimate for an earthquake intense enough to cause core damage to the reactor at Shearon Harris was 1 in 434,783, according to an NRC study published in August 2010.[16][17]
Surrounding population
The Nuclear Regulatory Commission defines two emergency planning zones around nuclear power plants: a plume exposure pathway zone with a radius of 10 miles (16 km), concerned primarily with exposure to, and inhalation of, airborne radioactive contamination, and an ingestion pathway zone of about 50 miles (80 km), concerned primarily with ingestion of food and liquid contaminated by radioactivity.[18]
The 2010 U.S. population within 10 miles (16 km) of Shearon Harris was 96,401, an increase of 62.6 percent in a decade, according to an analysis of U.S. Census data for msnbc.com. The 2010 U.S. population within 50 miles (80 km) was 2,562,573, an increase of 26.0 percent since 2000. Cities within 50 miles include Raleigh (21 miles to city center), Durham (24 miles to city center), and Fayetteville (39 miles to city center).[19]
During FEMA's most recent evaluation of state and local government's plans and preparedness included emergency operations for the plant, no deficiencies or areas requiring corrective actions were identified.[20]
NC-WARN concerns
The anti-nuclear group "N.C. Waste Awareness and Reduction Network" (NC-WARN) questioned the facility's safety and security record calling it "insufficient" and claiming "it is the most dangerous nuclear plant in the US".[21][22] However, the plant's technical and security systems have passed all Nuclear Regulatory Commission (NRC) standards[23] as of 2008[update], including protection and security, and no worker or area resident has been injured as a result of the plant's operation.
Spent fuel pools
In 2010, Project Censored, a non-profit, investigative journalism project, ranked the safety issues at Shearon Harris the 4th most under-reported story of the year, because of the risk of fires at what are the largest spent-fuel pools in the country.[24]
In August 2007, NC WARN dropped a lawsuit against Progress Energy that was intended to delay or prevent expansion of Shearon Harris, claiming that continuing the legal battle would cost at least $200,000.[25]
Shutdown
On May 16, 2013, Shearon Harris Unit 1 initiated an unplanned shutdown when reviews of ultrasonic data from a refueling outage in spring 2012 determined a 1/4" flaw was inside the 6"-thick Reactor Pressure Vessel Head. The flaw was near the nozzle for a control rod drive mechanism and attributed to primary water stress corrosion cracking, though no actual leakage was detected. Due to high radiation levels, the repairs required robotic aid.[26]