Ocker Hill Power Station

Ocker Hill Power Station
Map
CountryEngland
LocationTipton
Coordinates52°32′N 2°02′W / 52.54°N 2.03°W / 52.54; -2.03
StatusDecommissioned
Construction began1901
Commission date1902
Decommission date1977
OwnersMidland Electric Corporation
(1902–1927)
West Midlands Joint Electricity Authority (WMJEA)
(1927–1948)
British Electricity Authority
(1948–1955)
Central Electricity Authority
(1955–1957)
Central Electricity Generating Board
(1958–1977)
OperatorAs owner
Cooling towers3
Cooling sourceRecirculating water
Power generation
Units operational2 × 34 MW + 2 × 30 MW (steam); 4 × 70 MW (gas turbines)
Units decommissionedAll
Nameplate capacity280 MW (gas turbine)

Ocker Hill Power Station was situated at Ocker Hill in Tipton, Staffordshire, at a point where the Walsall Canal intersected the L&NWR Wednesbury to Princes End railway line. It was opened in 1902[1] by the Midland Electric Corporation for Power Distribution Limited (MEC)[2] and supplied electricity at 7 kV two phase 50 Hz to much of the Black Country. At the time of its building it was stated by the Stourbridge County Express that it was planned to be the largest power station in England. Although this may have been the original intention, it was never achieved.

History

The original plant comprised two Ferranti 800 kW reciprocating steam alternators and a 1500 kW Ferranti/Yates and Thom machine. Because of the rapid advance in the design of steam turbines, no more reciprocating machines were installed, and by 1906 a Willans/Dick Kerr steam turbine had been installed to meet the growing load, the first of fifteen turbines to be installed during the life of the station.

By 1923 the plant comprised 1 × 800 kW and 1 × 1,500 kW reciprocating engines and generators, and 3 × 1,500 kW, 3 × 3,000 kW and 2 × 5,000 kW turbo-alternators, these were supplied from the boiler plant which produced a total of 492,000 lb/hr (62.0 kg/s) of steam.[3] Electricity was generated at 7000 volts, 2-phase, 50 Hz AC, with distribution at 7000, 2700, and 200 volts. In 1923 the station generated 38.858 GWh of electricity, some of this was used in the plant, the total amount sold was 33.482 GWh. The revenue from sales of current was £271,812, this gave a surplus of revenue over expenses of £139,070.[3]

Joint Electricity Authority

In 1927, ownership passed to the new West Midlands Joint Electricity Authority (WMJEA), and with the building of the National Grid in the early 1930s it became a "selected station". In 1948 it became part of the newly created British Electricity Authority (later to become, by reorganisation the Central Electricity Authority (CEA) and then the Central Electricity Generating Board (CEGB). It closed in 1977,[4] as a result of the mid-1970s recession, which also claimed many other serviceable stations.

In 1951, the station achieved brief fame in the technical world by being the first to run a large alternator, whose turbine was disabled, as a so-called "synchronous condenser", which enabled the generation of lagging reactive current in order to boost voltage at a weak point in the system. As it was deprived of its driving turbine, the alternator was run up to speed by using its rotor damping winding as a squirrel cage, the stator being fed from another turbo running at reduced speed and voltage. When the rotor had come up to speed, excitation was applied to achieve synchronism.

Originally equipped with reciprocating steam engines, during its long life a total of eighteen generating sets were installed and in turn replaced with larger units or scrapped. The final equipment was of fairly typical 1940's design with eight Babcock stoker-fired boilers using the range system, feeding two British Thomson-Houston 34 MW sets and two Richardsons-Westgarth 30 MW sets, running at 650 psi and 875 °F (468 °C) superheat. Two of the cooling towers were unique, nationally and probably globally, in having the control room, 33 kV switchgear, relay room, garages and main stores beneath them. The station was coal-fired throughout its life, although small quantities of more unusual low-cost fuels were burned, including coke, sawdust, and at one period chicken droppings. Fuel was delivered originally by canal and later by rail, with small quantities by road. Although in later years the station was small in comparison with modern stations, it was extremely successful, and had a high availability, load factor and thermal efficiency when compared with most stations similar in design and age. It was the first station in the country to use the innovative "Taprogge" system of on-load condenser tube cleaning. For thirteen years, from 1959 to 1971, the load factor never dropped below 50%, well above that of the system as a whole. In 1968-1970, Ocker Hill had the highest load factor of any CEGB stoker-fired station, and the third highest thermal efficiency. During periods of plant shortage, it repeatedly carried overloads of up to 20%.

Operations

The electricity generating capacity and output of the power station are shown in the table.[5][6][7][8][9][10]

Ocker Hill electricity capacity and output
Year 1946 1947 1948 1950 1954 1955 1956 1957 1958 1961 1962 1963 1967 1971 1981 1982
Installed capacity, MW 41.7 79 69 56 56 56 112 112 128 128 128 128 128 280 280
Electricity output, GWh 22.88 31.3 184.2 262.6 125.548 250.304 211.731 285.643 277.433 454.5 467.6 472.4 628.58 401.396 5.606 20.076
Thermal efficiency, % 12.73 119.72 20.97 23.72 23.86 23.68 23.61 28.87 23.81 23.35 23.39 24.02 22.59 16.98 23.19

The electricity output in GWh is as shown.

Gas turbine plant

In the 1970s a gas turbine plant was installed at Ocker Hill. This comprised four GEC Gas Turbine Quad Olympus 70 MW gas turbines with a capability to deliver 280 MW of electricity. In the year ending 31 March 1981 the plant delivered 5.61 GWh of electricity just 0.2 per cent of its capability. The gas turbines were intended only for peak-lopping and emergency use, hence the low load factor.[7]

Demolition

The buildings and cooling towers remained unused on site for a number of years. The buildings were dismantled and the towers were demolished in controlled explosions, No. 3 on 18 August 1985 and Nos. 1 and 2 on 15 September.[11] The site is now a housing estate, built in the mid-1990s, and the Black Country Spine Road runs through the former site of the coal plant. A small industrial estate was built on part of the site in the 1990s, including a road which follows the route of the former Princes End Branch railway line, which closed as a through route in 1981 (although the passenger stations along the route had been closed in 1916 due to wartime economy measures). The final stub linking the gas turbine power station to the South Staffordshire Line remained open until 1991, two years before the South Staffordshire Line itself closed.

References

  1. ^ "History of Tipton". Titpon Civic Society. Retrieved 25 August 2016.
  2. ^ "Midland Electric Company". Grace's Guide to British Industrial History. Retrieved 26 August 2016.
  3. ^ a b Electricity Commission (1925). Electricity Supply - 1920-1923. London: HMSO. pp. 180–3, 454–59.
  4. ^ "Power Stations". Hansard. 5 December 1975. Retrieved 25 August 2016.
  5. ^ Garrett, Frederick C., ed. (1959). Garke's Manual of Electricity Supply vol. 56. London: Electrical Press. pp. A-129.
  6. ^ CEGB (1972). CEGB Statistical Yearbook 1972. London: CEGB. p. 13.
  7. ^ a b CEGB Statistical Yearbook operating results 1980-81. 1981, CEGB, London.
  8. ^ CEGB (1982). CEGB Statistical Yearbook 1981-2. London: CEGB. p. 7. ISBN 0902543695.
  9. ^ CEGB Annual report and Accounts, 1961, 1962 & 1963
  10. ^ Electricity Commission, Generation of Electricity in Great Britain year ended 31st December 1946. London: HMSO, 1947.
  11. ^ Halifax, Justine (4 February 2016). "Pictures: How the Birmingham Canal further powered Tipton's growth". Birmingham Mail. Retrieved 25 August 2016.
  • Black Country Power. The Story of Ocker Hill Power Station 1897-1977. Malcolm J.Richards 2001. (Available as a CD from the Black Country Society).