By 2006, the bridge carried an average of 120,000 vehicles per week.[5] The toll was £3.00 each way for cars (higher for commercial vehicles), which made it the most expensive toll crossing in the United Kingdom.[6] In April 2012, the toll was halved to £1.50 each way after the UK government deferred £150 million from the bridge's outstanding debt.[7][8]
The journey was along straight single-carriageway roads across foggy moors interrupted by bottlenecks for most of the journey to Blyth, Nottinghamshire, where it met the A1, and the accident rate was high. Debates in Parliament were held on the low standard of the route across the windswept plains around Goole. It was not unexpected that under these conditions, a Humber Bridge, with connecting dual-carriageway approach roads and grade-separated junctions, would seem worthwhile. By the time the bridge opened, much of this inferior route had been transformed by dualling of the A63 and its bypasses, extending the M62 and the connecting of the M18 from Thorne to Wadworth. The obvious need for a Humber Bridge had been reduced by the late 1970s with the improvements of the motorway infrastructure in the region. Although welcome, these improvements detracted from the need for vehicles to cross a bridge from Hessle to Barton. The Humber Bridge was a victim of the success of the M62 before it opened. A hovercraft service, Minerva and Mercury, linked Hull Pier and Grimsby Docks from February to October 1969 but suffered relatively frequent breakdowns.[10]
An Act to provide for the construction and maintenance of a bridge across the river Humber with approach roads and other works to constitute a Board and for other purposes.
Plans for a bridge were drawn up in the 1930s when a team of engineers compiled a report on whether to bridge or tunnel the estuary. It was decided that a bridge would cost £1,750,000 over a tunnel which was costed at £7,200,000.[11] Revised plans were unveiled in 1955, but work did not begin until 27 July 1972.[12] The Humber Bridge Act 1959 (7 & 8 Eliz. 2. c. xlvi), was promoted by Kingston Upon Hull Corporation and established the Humber Bridge Board to manage and raise funds to build the bridge and buy the land required for the approach roads.[13]
The architect was R. E. Slater ARIBA.[19] The administration building (for the tolls) was designed by Parker & Rosner. The landscaping was designed by Prof Arnold Weddle. Wind tunnel testing took place at the National Maritime Institute (now part of BMT Limited) at Teddington, and the road deck was designed for wind speeds up to 105 miles per hour (170 km/h), but storms featuring considerably lower wind speeds have been cited as grounds for emergency repairs in recent years.
Construction
The main contractor for the steel superstructure was British Bridge Builders (the same grouping as for the Forth and Severn Road Bridges comprising Sir William Arrol & Co., then a unit of NEI Cranes Ltd, Cleveland Bridge & Engineering Company, and Redpath Dorman Long Ltd).[20] The contractor for the concrete towers, anchorages and sub-structure was John Howard & Co Ltd of Chatham, Kent, which was later bought by Amec.[21] Concrete was chosen for the towers, instead of steel, partly due to cost, but also to suit the landscape.[17]
Work began on the southern approach road in July 1972 by Clugston Construction of Scunthorpe. The 2.5 km (1.6 mi) approach road to the A1077 junction, by Costain Civil Engineering, began in September 1976. It included a 320 m (350 yd) span from the southern anchorage of seven pre-stressed concrete box sections and the A1077 junction, costing £4.25 million. Work on the bridge substructure (foundations) began in March 1973. To reduce heat of hydration in the concrete, which produces calcium silicate hydrate from belite, as much as 60 per cent of the Portland cement was replaced with ground granulated blast-furnace slag (GGBS). It took longer to build the southern anchorage due to a diaphragm wall design due to there not being enough shallow bedrock. The main southern approach roads from Barton to the M180 motorway junction at Barnetby were built in the late 1970s by Clugston Construction of Scunthorpe, opening in 1978.[22]
The towers were constructed by slipforming and the north tower was completed by May 1974. The southern foundations were completed in September 1975, with the pier completed in March 1976, and the southern tower was completed by September 1976; the bridge had been planned to open in 1976. The northern tower and anchorage was built on solid chalk but the southern tower and anchorage were built on fissured Kimmeridge Clay, 500 m (550 yd) from the southern shore and built with a difficult caisson design. The subcontractor for the concrete was Tileman & Co. of Shipston-on-Stour, south Warwickshire.
Cable spinning took place between September 1977 and July 1979. Each cable weighs 5,500 t (5,400 long tons), with 37 strands of 404 lengths of cable. The cable on the northern span has four extra strands. Each cable can take a load of 19,400 t (19,100 long tons). The deck is of box girder form, the box sections around 140 t (140 long tons) each. The first box sections were assembled in June 1975 and put into the main span on 9 November 1979. The toll buildings and north approach road were built by A. F. Budge of Retford, Nottinghamshire, costing £2.9 million. Work began on the administration building in November 1976. The toll system was manufactured by Plessey Controls of Poole, Dorset. Corrosion resistance on the steelwork was provided by Camrex Corrosion of Bellshill, North Lanarkshire. The road was laid by Tarmac Roadstone of Wolverhampton with mastic asphalt.[23] In 2017, the bridge was designated a Grade I listed building.[24][25]
A-frames
At road level the deck was fastened to the towers through four rocking A-frames, to allow for movement caused by the catenary supporting the deck from above deflecting with the weight of passing traffic, from thermal expansion, and from changes in wind loading. The devices catered for a maximum deflection of 2 metres. By 2011 it was noticed that the pivot-pin bearings carrying the frames had worn, allowing them to drop towards the support structure. Each frame was replaced by two new components: a vertical linkage to cater for longitudinal movement and a sliding bearing for lateral displacement.[26]
Opening
The bridge opened to traffic on 24 June 1981 at a final cost of £91 million (equivalent to £440,568,000 in 2023).[27][28] It was opened officially by Queen Elizabeth II on 17 July 1981, in a ceremony that included a prayer of dedication by the Archbishop of York and a fly-past by the Red Arrows.[17][28]
World record
With a centre span of 1,410 m (4,630 ft; 0.88 mi) and a total length of 2,220 m (7,280 ft; 1.38 mi), the Humber Bridge was the longest single-span suspension bridge in the world for 17 years, until the Akashi Kaikyō Bridge opened in Japan on 5 April 1998.[29]
Local benefits
The road-distance between Hull and Grimsby fell by nearly 60 mi (97 km); the town of Scunthorpe and environs were relieved of the passing traffic between Hull and Grimsby.[30][29]
Bridge statistics
The bridge's surface takes the form of a dual carriageway with a lower-level foot and cycle path on both sides. There is a permanent 50 mph (80 km/h) speed limit on the full length of the bridge.
Each tower consists of a pair of hollow vertical concrete columns, each 155.5 m (510 ft) tall and tapering from 6 m (20 ft) square at the base to 4.5 m × 4.75 m (14.8 ft × 15.6 ft) at the top. The bridge is designed to tolerate constant motion and bends more than 3 m (10 ft) in winds of 80 mph (129 km/h). The towers, although vertical, are 36 mm (1.4 in) farther apart at the top than the bottom due to the curvature of the Earth.[31]
The total length of the suspension cable is 71,000 km (44,000 mi).[32] The north tower is on the bank and has foundations down to 8 m (26 ft). The south tower is in the water, and descends to 36 m (118 ft) as a consequence of the shifting sandbanks that make up the estuary.
The bridge held the record for the world's longest single-span suspension bridge for 17 years, from its opening in July 1981 until the opening of the Akashi Kaikyō Bridge in April 1998. In June 2024, it became the thirteenth-longest, single-span suspension bridge. The central span, at 1,410 m (4,630 ft; 0.88 mi), is the longest in Britain and in the Western Hemisphere. It remains the longest single-span suspension bridge in the world that can be crossed on foot or by bicycle.[33]
The bridge is crossed twice during the annual Humber Bridge Half Marathon in June,[34] and Hull Marathon in September.[35]
Toll update project
In July 2013, work began on introducing a new electronic tolling system.[36] The existing Humber Bridge toll system was largely the same as it was when the bridge opened in 1981. The computer system was over 15 years old, absorbed an increasing amount of maintenance, and needed to be replaced.[36] The project would decrease waiting times and was welcomed by business and transport leaders.[36]
In the first phase, the toll booths and the toll plaza canopy were replaced, and in the second phase, writing, testing and setting up the new toll system was completed. From 2015 bridge users could set up an account with the bridge and pay into it.[37] Account holders receive a device called the HumberTAG, a small electronic tag that enables the system to recognise the bridge user; the toll is automatically deducted from the user's account. Two central lanes through the plaza are free-flowing; they do not have booths and account holders are able to cross the bridge without stopping.[38]
Incidents and suicides
During construction of the bridge, the road deck sections were floated up on barges then hoisted into place by cables. During one of these lifting operations some of the cables on two of the road deck sections failed, leaving the sections hanging at an angle. The sections were subsequently installed.[39]
On more than 200 occasions, people have jumped or fallen from the bridge since it was opened in 1981; only five people have survived.[40] Between 1990 and February 2001 the Humber Rescue Team launched its boat 64 times to deal with people falling or jumping off the bridge.[41] Notable incidents include the cases of a West Yorkshire woman and her two-year-old daughter who fell off the bridge in 2005 and that of a man jumping from the bridge to his death on the A63 road below in September 2006.[42][43][44]
Plans were announced on 26 December 2009 to construct a suicide barrier along the walkways of the bridge; design constraints were cited as the reason for not installing barriers during the construction of the bridge.[45]
In May 2017, a YouTuber with the username 'Night Scape', along with a small group, illegally scaled the bridge without safety equipment. The group of young men climbed up the structure to the top of the bridge using the suspension wires as handholds. Humberside Police and the Humber Bridge Board are reviewing the security measures.[46]
On 3 April 2021, the Humber Bridge was closed to pedestrians and cyclists following an unspecified 'recent incident'.[47] The decision came after multiple deaths at the bridge in the month of March.[48] Following the death of one individual that month, a petition calling for increased safety measures to 'secure' the bridge had gained thousands of signatures.[49] Concerns were raised over how the change will affect those who commute on foot or by bike.[50] On 6 May 2021, the bridge was reopened to pedestrians and cyclists between the hours of 0500 and 2100; only users registered in advance could use the bridge outside of those hours. More CCTV and notices were erected and more staff assigned to patrol the crossing.[51]
Finances
The bridge had a toll charge of £1.50 for cars from 1 April 2012, until for six months it was £3.00 and the only trunk road British toll bridge to charge motorcycles (£1.20). In 2004 many motorcyclists held a slow-pay protest, taking off gloves and helmets and paying the toll in large denomination bank notes. Police reported that the protest caused a queue 4 mi (6 km) long.[citation needed]
In 1996, Parliament passed the Humber Bridge (Debts) Act 1996 to reorganise the board's liabilities to ensure the bridge could be safely maintained. Much of the interest on the debt was suspended and deferred in a refinancing which saw no write off – the balance was to be paid using tolls.
In 2006, Shona McIsaac, Labour MP for Cleethorpes, tabled a Private Member's Bill, the Humber Bridge Bill.[52] The bill would have made amendments to the Humber Bridge Act 1959 (7 & 8 Eliz. 2. c. xlvi) "requiring the Secretary of State to give directions to members of the Humber Bridge Board regarding healthcare and to review the possibility of facilitating journeys across the Humber Bridge in relation to healthcare". The aim was to allow patients travelling between the banks for medical treatment to cross without paying the toll and to allow the Secretary of State for Transport to appoint two members of the board to represent the interests of the NHS. Even though the Bill received cross-party support (it was co-sponsored by Shadow Home Secretary David Davis and supported by all other MPs representing North Lincolnshire and the East Riding of Yorkshire) it ran out of time later that year.[53]
A protest at the bridge on 1 September 2007 was supported by the local Cancer Patients Involvement Group, the Road Haulage Association, Diana Wallis (MEP for Yorkshire and the Humber) and local business and council representatives.[54] The government responded to the petition on 14 January 2008, stating that "Concessions or exemptions from tolls on the Humber Bridge are a matter for the Humber Bridge Board".[55]
In October 2008, a joint campaign was launched by the Scunthorpe Telegraph, Hull Daily Mail and Grimsby Telegraph to abolish the toll. The papers' campaign, A Toll Too Far, was launched after a mooted increase in the toll, receiving much support from councillors and MPs serving Lincolnshire and the East Riding of Yorkshire. The campaign was to stave off a potential increase, secure a reduction to £1.00 and ultimately to be abolished. Thousands of readers backed the campaign with a paper and an online petition.[citation needed]
A public inquiry into the tolls was held in March 2009 by independent inspector Neil Taylor. In July 2009, the Department for Transport announced that it had decided not to allow the proposed increase. Transport Minister Sadiq Khan said he did not believe it was right for the tolls to be raised in the current economic climate.[56] In October 2009, the government approved a £6 million grant for maintenance costs, which meant that there would be no toll increase before 2011 at the earliest, by which time tolls would have been frozen for five years.[57]
The board applied again to the Department of Transport in September 2010, to raise the tolls from April 2011 but the government ordered a public inquiry into the application.[58] A three-day public inquiry was held in Hull in early March 2011.[59] Following the recommendation by the planning inspector, the government gave approval, on 14 June 2011, for the increase.[60] The toll was raised on 1 October 2011, at which point it became the most expensive in the United Kingdom.[6] The Severn Bridge/Second Severn Crossing charged £5.70 for Wales-bound traffic.[61]
In the 2011 Autumn Statement on 29 November, the Chancellor of the Exchequer, George Osborne, announced that the government had agreed to reduce the debt on the bridge by £150 million, which would allow the toll for cars to be halved to £1.50.[62] Following the government accepting the agreement, between the four local councils, to meet a portion of the debt if revenues proved insufficient, the Transport Secretary, Justine Greening, confirmed the reduction on 29 February 2012, with effect from April.[63]
Image gallery
View from the south bank showing the curvature of the bridge
Humber bridge control room
View from the eastern walkway
Close up of a bridge tower
View from below the Humber Bridge towers taken from north bank
^Kershaw, Ronald (19 December 1972). "Humber Bridge will close the Hull communications gap". The Times. No. 58, 660. p. 23. ISSN0140-0460.
^"New hovercraft service". The Times. No. 57488. 18 February 1969. p. 2. ISSN0140-0460.
^"Crossing the Humber". The Times. No. 45459. 12 March 1930. p. 11. ISSN0140-0460.
^"Humber Bridge Plan Revived". The Times. No. 53304. 20 August 1955. p. 3. ISSN0140-0460.
^"Humber Bridge Act 2013". legislation.gov.uk. The National Archives on behalf of HM Government. Retrieved 22 June 2018. The Humber Bridge Act 1959 established the Humber Bridge Board ("the Board") and conferred powers on it to construct and maintain a bridge across the river Humber, together with approach roads and other works