Fastway aims to improve bus services in the Crawley, Gatwick and Horley area. The project included construction of new bus lanes, including guided bus lanes, construction of new bus waiting shelters and provision of electronic real-time passenger information and a fleet of new low-floor buses for Metrobus (part of the Go Ahead Group)
Construction work began in May 2002, and was scheduled to be completed by June 2005.[5] In October 2006, major work stopped, having completed around 60% of the planned work - 1.5 km guided and 5.8 km unguided bus lanes were constructed,[6] of the planned 2.5 km guided and 8.8 km unguided lanes.[7] The planned 24 traffic lights and 11 roundabouts were changed to 40 traffic lights and 2 roundabouts.
History
Phase 1 (Service 10) commenced in September 2003 between Bewbush and Gatwick, £50,000 over budget and four months behind schedule.[1] The opening was attended by Tony McNulty MP, the Parliamentary Under-Secretary of State for Transport[citation needed], and local dignitaries. The service was extended from 21- to 24-hour operation in May 2004 and now runs every 7 minutes during the day and every 20–30 minutes in the early morning, evening and Sunday.
In July 2005 the project was more than £6 million over budget. An independent inquiry was launched to investigate the losses, led by a task force from East Sussex County Council. The results of the inquiry were published in December 2005. ESCC concluded West Sussex had shown a pattern of "ineffective accountability, complacency, ineffective risk management and a lack of clear ownership of the financial management responsibilities".[8]
On 27 August 2005 Fastway service 20 was introduced, running between Broadfield, Three Bridges, Manor Royal, Gatwick Airport, Horley and Langshott.[9] On Mondays to Saturdays it runs approximately every 20-30 minutes during the day, and every 30 minutes in the early morning, late evening and all-day Sunday. Service 20 runs now 24-hours.[10]
Decision making process
Bus rapid transit was chosen to minimise start-up costs, and remove the need for public consultation exercises.[citation needed]
Fastway is the first bus rapid transit system in the world to be built outside a major city by a partnership of local authorities and private companies with automatic vehicle location, pre-trip and in-trip passenger information and automatic traffic signal priority from the start.[citation needed]
Funding
In June 2002 the official Fastway website was updated to show a cost of £27 million, with just under £10 million provided by the government.[11]
In September 2003, the Go-Ahead group withdrew their £3 million commitment to the project. The government increased its contribution to cover this as well as other rising costs, raising its contribution to £16.642 million.[12][13]
By July 2005, West Sussex County Council's share of the project's cost had increased five-fold from £6.2 million to almost £30 million, resulting in external audit and probe into the programme.[14] The inquiry found no wrongdoing by a single employee of the council when it concluded in December 2005, however did state that the council had "ineffective accountability, complacency, ineffective risk management and a lack of clear ownership of the financial management responsibilities".[15]
Services
The Fastway system is currently formed of three bus routes, all of which are operated by Metrobus:[16]
Route 10
Route 10 is the most frequent service on the network. It operates between Bewbush and Gatwick Airport via Broadfield, Crawley Town Centre and Manor Royal. It runs every 10 minutes during daytime on weekdays and Saturdays, every 12 minutes on Sundays and every 30 minutes overnight.[17]
Route 20
Route 20 operates between Pease Pottage and Langshott via Broadfield, Crawley Town Centre, Three Bridges, Gatwick Airport and Horley. It runs every 20-25 minutes during daytime on weekdays and Saturdays, every 30 minutes on Sundays and approximately every 45 minutes overnight.[18]
Route 100
Route 100 is the longest route on the network. It operates between Maidenbower and Redhill via Three Bridges, Crawley Town Centre, Manor Royal, Gatwick Airport, Horley and East Surrey Hospital. It runs every 20 minutes on weekdays and Saturdays, every 30 minutes on Sundays and hourly overnight.[19]
The project initially included a £3 million contribution by Metrobus, the bus operator, and its parent company, the Go-Ahead Group, but this was withdrawn after construction had started, and the money was replaced by West Sussex County Council.
The projected cost started at £27 million and was later revised to £32 million, then £35 million, with between £7.5 and £10 million from West Sussex County Council. The final cost of the scheme is still unknown, but has risen from the original estimates and was described as £6 million over budget
Metrobus has stated that passenger figures are up 10 percent, with 35 percent of journeys being to and from Gatwick. One million passengers were carried in the first seven months of operation.
Opposition
It has been noted[by whom?] that, while successful at reducing road traffic, Fastway has not tackled gaps in the existing public transport network, particularly Pound Hill.[20]
Accidents
On 31 October 2005 a Fastway bus travelling along Breezehurst Drive crashed into a terraced house. Two elderly residents were evacuated, and the damage required the house to be demolished. Four passengers suffered minor injuries.[21] According to Metrobus, the bus involved in the incident was a Scania OmniCity bus number 550 (registration YN05 HCF).[22] Another accident was reported in the same place in 2008.[23]
Passenger numbers
A survey in 2006 showed average passenger numbers during the 7-9am peak were 5, one for each bus
[24] By 2008 as the system became established the West Sussex County Council indicated that bus use in Crawley had increased by 25% following quality improvements.[25]
^Fastway Official Newsletter 13, "1.5km guided and 5.8km unguided bus lanes were constructed""Archived copy". Archived from the original on 27 September 2007. Retrieved 9 August 2007.{{cite web}}: CS1 maint: archived copy as title (link), retrieved 9 August 2007
^Fastway Official Website 12 August 2002, "Fastway Facts and Figures, as announced in 2002"[1], retrieved 12 August 2002
Official site from November 2002 on Archive.org [2], retrieved 5 August 2005.
Edmund Nuttall Ltd (fastway contractor), September 2004 news [3], retrieved 5 August 2005.
Local Transport Plan Settlement 2004-05 (PDF) [4], retrieved 5 August 2005.
Fastway will use £19 million public money and £14 million private money, and will used untested technology.[5][permanent dead link], retrieved 5 August 2005.
Fastway protest 'snowballs' [6], retrieved 5 August 2005.