The East Klang Valley Expressway, EKVEEast Klang Valley Expressway, Kuala Lumpur North Dispersal Expressway or Kuala Lumpur Outer Ring Road(KLORR) is a new expressway under construction in Klang Valley, Malaysia. The 39.5-kilometre-long (24.5 mi) expressway will connect Ukay Perdana in Ampang, Selangor and Bandar Sungai Long in Kajang. This expressway is part of the Kuala Lumpur Outer Ring Road (KLORR). The construction of the expressway was started on 1 September 2015.[1] Once completed, the expressway will benefit 140,000 motorists per day.[2]
The phase 1 of the expressway stretches 24.1 km and costs MYR 1.55 billion.[2]
EKVE Sdn Bhd (a member of Ahmad Zaki Resources Berhad (AZRB)), the developer of the expressway, is expected to begin construction of the RM 1.55 billion project in September 2015. Originally the project is expected to take 4 years to complete,[1] but a series of delays in the project meant that, in October 2020, the completion target were revised to be completed by the third quarter of 2021.[3]
As of November 2021, the project is 94.48% completed, and were expected to be completed by the end of 2022.[4] However, due to several lawsuit against EKVE Sdn Bhd involving a piece of land at Beverly Heights, the completion of the highway were delayed to 2023 as per announced by then Minister of Works, Fadillah Yusof in October 2022.[5] The opening of the highway also will be done in stages, with the Sungai Long-Ampang stretch will be the first stage to be opened in the second quarter of 2023.[5] The expected completion and opening were further delayed to 2024, when then new Minister of Works Alexander Nanta Linggi stated in a written parliamentary reply in March 2023 that the delay were caused by halting of works due to rising costs of construction.[6] Alexander also said that the completion of works percentage were revised to 91%.[6]
The many delays of EKVE means by the time of its completion, it will have to compete with several alternatives to its route that have been completed earlier, such as SUKE (completed September 2022) and MRT Putrajaya Line (completed March 2023).[7]
Construction of EKVE is attributed as the cause of several flash floods and mud floods in the areas the highway were built,[8][9][10] including the 2021–2022 Malaysian floods in the Ampang/Hulu Langat area.[11][12]
The phase 1 of the project is heavily criticized due to de-gazetting of 106.6 ha of the Ampang Forest Reserve, a critical source of water for Klang Valley.[13]
The phase 2 of the project (from Ukay Perdana to the Kuala Lumpur–Karak Expressway) would have cut through the Ulu Gombak forest reserve. The phase 2 has not been approved due to environmental concerns.[13]