The Conwy Railway Bridge was designed by railway engineer Robert Stephenson in collaboration with William Fairbairn and Eaton Hodgkinson.[1] The original plan had been for suspension bridge complementing Thomas Telford's Conwy Suspension Bridge of 1826. After Stephenson's appointment as chief engineer, the design was changed because a suspension bridge was considered unsuitable for trains. Stephenson and his collaborators invented the wrought-iron box-girder structure to bridge the River Conwy in a single span.
During May 1846, groundwork for the bridge commenced. The architect Francis Thompson dressed the pylons at either end as barbicans, with crenellatedturrets, arrow slits and bartizans to complement the adjacent Conwy Castle. Unusually, the tubes were completed onshore before being attached to pontoons, floated along the river and jacked into position between the abutments. The bridge was officially opened in 1849. The bridge endorsed the construction of the larger Britannia Bridge. During 1899, the tubular sections were reinforced with cast iron columns to reduce the load on the span across the river. In September 1950, Conwy Tubular Bridge was recognised as being a Grade I listed building; it is also a scheduled monument (CN167).
History
Background
During the 1840s, the Chester and Holyhead Railway committed to building a railway line along the coastline of North Wales between Chester and Holyhead on Anglesey.[2] The line would improve transport and communications in the region and speed up traffic between London and Ireland as part of the national rail network that was under development.[2]
Robert Stephenson the chief engineer of the Chester and Holyhead Railway designed the bridge.[2] He devised a tunnel-like rigid tube which would be suspended above the Conwy to accommodate tracks inside it. The box-section tube possessed sufficient rigidity to be self-supporting over the span of the river.[2]
During February 1846, the men presented their design to the company who approved further development and experimentation to validate the design.[2] Several different cross sections were built including a one-sixteenth scale model of the Britannia Bridge, 23.8 meters in length fitted with a rectangular-section tube.[2] Testing incorporated various conditions, including wind and temperature variations. The designs for both the Conwy Railway Bridge and Britannia Bridge were similar.[2]
Construction
During May 1846, groundwork for the bridge commenced.[2] On either shore, the underlying bedrock was levelled close to the river's low water level for the foundations of the towers. For additional support, timber piles were driven at the south east corner of Conwy Tower where the masonry is seated on a wooden platform roughly 600mm below the low water level.[2]
The project's architect, Francis Thompson, dressed the pylons at either end as barbicans with crenellatedturrets, arrow slits and bartizans to complement the adjacent Conwy Castle that had stood on the promontory since the late 13th century.[2] As designed, the tubes were to be elaborately decorated meant to resemble castle walls with machicolatedcornices, stringcourses and loopholes. The fitting of external decorations was abandoned on the grounds of expense and extra weight.[2]
The bridge contractor was William Evan. The ironwork was constructed by Easton & Amos.[4] On 15 June 1846, the foundation stone of the towers was laid. The towers accommodated entrance portals within twin arches, through which the railway are carried into the tubes. The tubes are made of 16mm riveted wrought iron with cellular roofs and bases, and sheeted sides; each one weighs roughly 1,320 tonnes.[2] The tubes, which are 129.2 meters long and 4.4 meters wide, were constructed using shipbuilding techniques.[2] Once completed onshore, they were attached to pontoons, floated along the river and jacked into position between the abutments; steam-powered hydraulic engines lifted the bridge elements into place. On 6 March 1848, the first tube was floated; its installation took nine days to complete.[2]
Operational life
The bridge was officially opened in 1849, although the first tube had been completed for traffic during April 1848.[2] Stephenson wanted to test the structure, the first tubular crossing, to be sure it was capable of carrying the weight of a locomotive and its rolling stock. The testing was performed by Fairbairn and achieved favourable results. The bridge effectively endorsed the construction of the larger Britannia Bridge.[2][5]
During 1899, the tubular sections were reinforced with cast iron columns to reduce the load on the span across the river to accommodate the increasingly heavy trains being used on the route. The bridge's weight capacity had been exceeded according to a survey.[2] The columns were fitted with inspection gantries to ease maintenance but during the 2000s they were deemed to be unnecessary and were removed.[6]
In September 1950, Conwy Tubular Bridge was recognised as being a Grade I listed structure; it is also a scheduled monument (CN167), protecting it as a historical asset for the nation.[2] By the 21st century, the bridge is the only surviving example of a tubular bridge designed by Stephenson. The original Britannia Bridge was damaged beyond repair by fire in 1970; it was rebuilt as a two-tier truss arch bridge made of steel and concrete.[7][8]
The bridge is maintained by Network Rail as a part of the British railway network.[2] Its heritage is protected and actively managed by Cadw, the historic environment organisation of the Welsh Government.