The stadium, which has been closed since June 2013,[3] previously had a capacity of approximately 31,500.[1] While previously serving as the home ground of the Antrimhurling and Gaelic football teams, it was in a state of dereliction by 2021, with redevelopment plans pending for several years.[6] Though planning permission for the redevelopment of Casement Park was confirmed in July 2021,[7] by March 2023, it remained closed.[8]
A combined bid to host UEFA Euro 2028, by the Republic of Ireland and England, Northern Ireland, Scotland and Wales, included a proposal to redevelop the stadium.[4] While, by March 2024, some demolition work had commenced,[9] as of September 2024 it was reported that the redevelopment would not be funded or completed in time for the 2028 competition, which caused the stadium to be removed from hosting duties.[10]
History
Casement Park, one of the largest stadiums in Northern Ireland,[2] was built in the years following World War II, with the main stand reportedly incorporating steel reclaimed from disused military aircraft hangars in County Fermanagh.[11]
In all, Casement Park has hosted eight Ulster football finals. However, the Antrim ground has not held the provincial final since 1971, with St. Tiernach's Park in Clones hosting the final every year since except between 2004 and 2006 when it was moved to Croke Park, such was the demand for tickets. A major facelift of the stadium in 2000 saw more championship games played at Casement Park. Floodlights were added in 2006.[21]
In November 2016, Casement Park was included as part of the Irish Rugby Football Union's, ultimately unsuccessful, bid to host the 2023 Rugby World Cup. The stadium was also included in Northern Ireland's joint UEFA Euro 2028 bid.[23]
Redevelopment
Proposals
In 2006, proposals were raised to build a new multi-purpose stadium on the site of the old Maze prison near Lisburn, which was intended to host association football, rugby union and Gaelic games. However, opposition to the idea led to it being dropped in favour of a new venue in the Sydenham area of East Belfast. This led to Ulster GAA, which was one of the partners in the Maze project, to pull out in favour of remaining at Casement Park.[24]
Plans to redevelop Casement Park were announced in 2009, though it was not until 2011 that the Northern Ireland Executive announced that it had granted £138m for various stadium redevelopment projects throughout Northern Ireland, of which Ulster GAA would receive £61.4m to be used to redevelop Casement Park into a 40,000 all-seated stadium. A further £15 million was proposed from the Central Council of the Gaelic Athletic Association. If the plans had been approved, the venue would become the largest stadium in Ulster.[25] In early 2012 it was announced that the redevelopment work would start at the end of 2013 with a view to having the new stadium open by September 2015. It was expected that, after its completion, Ulster GAA would move its headquarters from St Tiernach's Park in Clones to the redeveloped Casement Park.[26][27]
Local residents of West Belfast objected to the proposal and in September 2013 the Mooreland and Owenvarragh Residents Association (MORA) issued a formal petition and letter of objection to the Northern Ireland Department of Environment, describing the new stadium plans "a monstrosity" and too expansive.[28] The residents filed a lawsuit as the date for the commencement of construction continued to be delayed. In December 2014 the High Court ruled a ministerial decision granting planning approval for the redevelopment of the stadium was unlawful, setting the proposal back further.[29] Ulster GAA responded with disappointment to the decision, though vowed to re-submit an improved design. They did so in October 2016, unveiling a smaller scale project with a reduced capacity of 34,500.[30] This design didn't obtain planning approval, as Northern Ireland's power-sharing government was dissolved in March 2017. This delay saw the anticipated total cost of the project increase to approximately £110 million.[31]
Antrim's 14 point "home" loss to Tyrone in the 2019 Ulster Senior Football Championship quarter-final in Armagh highlighted the run-down status of the Casement Park pitch and grandstands.[32] The GAA stated it was hopeful of receiving planning permission for the redevelopment in mid-Spring 2020.[33] This eventually came in October 2020 when Minister for InfrastructureNichola Mallon recommended planning approval.[34] As of 2020, the stadium was speculated to open in summer 2023, while the project still faced funding uncertainties.[35]
In July 2021, planning permission for the redevelopment of Casement Park was confirmed.[7] At that time, the redevelopment project (including a proposed capacity of 34,578) was set to commence in the first half of 2022 and expected to be a two-year build.[7] However, the planning approval was subject to a High Court review,[36] and in May 2022 an appeal against the stadium's redevelopment was rejected by the court, with work then projected to begin at an unspecified date in 2023 for "complet[ion] in 2025".[37][8]
In November 2023, after the previous contractor went into administration, the GAA stated that it was seeking a new primary contractor for the redevelopment project.[38] At that time, the architecture firm which had previously been engaged, Populous, was reportedly "still involved".[39] The GAA and Irish Football Association (IFA) both suggested that the selection of a new contractor would "not jeopardise" the deadline for the project.[38]
In March 2023 the GAA announced that, if redeveloped as proposed under the July 2021 proposal, it would give special permission (under Rule 42) for Casement Park to be included in a joint UK and Ireland bid to host the UEFA Euro 2028 Championship.[40] The bid, which was chosen in October 2023, proposed that Casement Park would be the sole host stadium in Northern Ireland.[11]
In February 2024, clearance work began at the start of the redevelopment project.[41] This included some demolition work on the stadium's former concrete terracing in March 2024.[9]
Unionist protests
The inclusion of Casement Park instead of Windsor Park as the Northern Irish venue led to Unionist protests, due to Casement Park being a hurling and Gaelic football stadium, traditional nationalist sports. Northern Ireland's national football stadium, Windsor Park, however, does not have a capacity large enough to comply with UEFA rules for hosting European Championship matches, which led to the selection of Casement Park. Windsor Park is located in a majority unionist area (with football being a traditional unionist sport), whereas Casement Park is located in a majority nationalist area and named for a revolutionary involved in the Easter Rising. Protests had been held regarding the inclusion of Casement Park with the theme being that the protestors did not want to attend games at the venue, due to its history and location.[42][43][44][45]
Funding problems
Casement Park's inclusion in the bid was subject to redevelopment work being completed. Such work was being funded by the Northern Irish Devolved Government and the Gaelic Athletic Association, however it was hope that the UK government would also contribute following a successful bid.[46]
It was reported on 13 June 2024 that detail of UK government funding for the stadium would not be published until after the UK general election on 4 July 2024.[47] On 16 June 2024, Northern Ireland's First Minister Michelle O'Neill said that Casement Park would be built "on [her] watch".[48]
On 13 September 2024, the British Government announced it would not contribute to the redevelopment of Casement Park, with the redevelopment being delayed and budget increased to £400 million (from the originally proposed £77.5 million),[49] putting hopes of Northern Ireland hosting any matches at the tournament in jeopardy.[46] On 16 September 2024, Casement Park was dropped as a host venue.[50]
Post Euro-withdrawal redevelopment
Following the withdrawal as a Euro Championship host stadium, the predicted redevelopment costs dropped to £270 million, as the stadium no longer needed to comply with UEFA regulations.[51]