The construction of a new bridge over the Tapti River at Athwa was proposed in 2006. S. N. Bhobe and Associates, Navi Mumbai, was selected as the designer for both of the bridges in 2008. S. N. Bhobe and Associates has been designing projects for the Surat Municipal Corporation (SMC) since 2006.[3] The same company previously designed the Fly Over Bridge at Nana Varachha junction, Fly Over Bridge at Kapodra Fire Station junction, Hajira - Adajan Flyover bridge and Shri Swami Dayanand Saraswati bridge across the Tapti River for SMC.[citation needed]
Construction work for the cable-stayed bridge started in 2010. The construction this portion of the bridge (River-Bridge) was contracted to Gammon India and the connected 3-way interchange flyover bridge on the Athwa side of the main river bridge was contracted to Rachana Construction. Spectrum Techno Consultant Private Limited was appointed as Project Manager Consultant to supervise the entire construction work and to ensure that the construction was taking place as per standards.[citation needed]
Incident
On 25 May 2014 concrete slab work was being carried out at the sharp turning portion of the 3-way interchange flyover bridge.
On 10 June 2014 workers started removing the staging plates (formwork) from the slab, whose concrete was poured 15 days earlier on 25 May. Around 8 a.m. the whole slab weighing 650 tonnes, and of 35 metres in length, collapsed from 40 feet high.[3][4]
16 workers were buried under the slab, 10 workers died on-the-spot and 6 sustained major or minor injuries.[5]
Investigation
Gujarat Engineering Research Institution in Vadodara was appointed to investigate the site, debris and material used for construction. Based on their report, the material used for construction was judged poor quality.
The design documents were sent to Sardar Vallabhbhai National Institute of Technology, Surat for verification. Their report said there were major flaws in the design of the sharply curved part of the bridge. The sharp curvature was not taken into account by the designer, instead the design calculation was based on a straight slab, actually the detailed analysis should have been performed for that curved section. The center of gravity of that slab was outside the bridge deck and that created a larger 'turning moment', making the slab unstable.[5][6]
Aftermath
Based on investigations, the Police Inspector of Umra Police Station lodged a first information report on 3 July 2014 against 18 accused under section 304 Part II, 337, 338 and 114 of the Indian Penal Code. This included three employees of 'S. N. Bhobe and Associates, Navi Mumbai', five engineers from 'Spectrum Techno Consultant Private Limited,' four directors and three others of 'Rachana Constructions', and three engineers from 'SMC Bridge Cell.'[3][7]
SMC Blacklisted 'S. N. Bhobe and Associates, Navi Mumbai' and transferred the design contract to 'L & T Infrastructure Eng. Ltd'.
Subsequently Gammon India was also blacklisted due to them abandoning the incomplete work in November 2014.[8] The remaining bridge construction contract of the Bridge was issued to 'Unique Construction, Surat'.[1]
The initial plan was to complete the construction in 30 months, but the collapse of one portion of the 3-Way Interchange Flyover Bridge during construction delayed the project.