M6 is an under construction metro line of the Bucharest Metro. The M6 Line will connect Bucharest North railway station (Gara de Nord) to Henri Coandă International Airport (Aeroportul Otopeni). The line is expected to be completed by 2028.[1][2] As of 2019, only the section from 1 Mai station to Tokyo station had secured funding.[3] On March 8, 2022, the contract for construction was signed; the contract for the second section — from Tokyo station to the airport — was signed on May 2, 2023.
Construction work has effectively started on December 15, 2023, for the first section between the 1 Mai station of M4 and the future Tokyo station.
The M6 Line will have a total of 16 stations: 4 stations shared with the existing M4 Line and 12 planned new stations: Pajura, Expoziției, Piața Montreal, Gara Băneasa, Aeroport Băneasa, Tokyo, Washington, Paris, Bruxelles, Otopeni, Ion I.C. Brătianu, and Aeroport Otopeni.[2]